Ecc International Constructors, LLC v. Secretary of the Army

79 F.4th 1364
Court of Appeals for the Federal Circuit·Decided August 22, 2023·No. 21-2323·Published·Cited by 22 cases

Opinion

Case: 21-2323 Document: 54 Page: 1 Filed: 08/22/2023

United States Court of Appeals for the Federal Circuit ______________________

ECC INTERNATIONAL CONSTRUCTORS, LLC, Appellant

v.

SECRETARY OF THE ARMY, Appellee ______________________

2021-2323 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in No. 59586, Administrative Judge Owen C. Wilson, Administrative Judge Richard Shackleford, Administra- tive Judge Timothy Paul McIlmail. ______________________

Decided: August 22, 2023 ______________________

ROY DALE HOLMES, Cohen Seglias Pallas Greenhall & Furman, Philadelphia, PA, argued for appellant. Also rep- resented by MICHAEL H. PAYNE.

CORINNE ANNE NIOSI, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellee. Also represented by BRIAN M. BOYNTON, PATRICIA M. MCCARTHY. ______________________ Case: 21-2323 Document: 54 Page: 2 Filed: 08/22/2023

Before PROST, LINN, and CUNNINGHAM, Circuit Judges. PROST, Circuit Judge. ECC International Constructors, LLC (“ECCI”) ap- peals a decision of the Armed Services Board of Contract Appeals (“Board”) dismissing its claim for lack of jurisdic- tion. The claim stems from a contract the U.S. Army Corps of Engineers (“USACE”) awarded ECCI in 2010 to design and build a military compound in Afghanistan. In 2014, ECCI filed a claim seeking compensation for construction delays allegedly attributable to the government. After six years of unsuccessful settlement discussions between the government and ECCI, followed by a nine-day hearing on the merits before the Board, the government—three months after the hearing—moved to dismiss ECCI’s claim for lack of subject-matter jurisdiction for failure to state a “sum certain.” The Board granted the government’s mo- tion. ECCI appeals. We consider sua sponte whether the requirement (as established by the Federal Acquisition Regulation (“FAR”)) that claims submitted under the Contract Disputes Act (“CDA”) state a “sum certain”—i.e., specify the precise dol- lar amount sought as relief—is jurisdictional. For the rea- sons below, we conclude that the sum-certain requirement is a nonjurisdictional rule subject to forfeiture. Accord- ingly, we reverse the Board’s dismissal and remand for pro- ceedings consistent with this opinion. BACKGROUND We first outline the nature and consequences of juris- dictional rules before turning to the facts of this case. I The Supreme Court in recent years has clarified the scope of the term “jurisdiction.” “Jurisdiction, [the] Court has observed, is a word of many, too many, meanings.” Wil- kins v. United States, 143 S. Ct. 870, 875 (2023) (quoting Case: 21-2323 Document: 54 Page: 3 Filed: 08/22/2023

ECC INTERNATIONAL CONSTRUCTORS, LLC v. 3 SECRETARY OF THE ARMY

Arbaugh v. Y & H Corp., 546 U.S. 500, 510 (2006)). In- creasingly, “the Court has undertaken to ward off profli- gate use of the term.” Fort Bend Cnty., Tex. v. Davis, 139 S. Ct. 1843, 1848 (2019) (cleaned up) (quoting Sebelius v. Auburn Reg’l Med. Ctr., 568 U.S. 145, 153 (2013)). Properly construed, “the word ‘jurisdictional’ is generally reserved for prescriptions delineating the classes of cases a court may entertain (subject-matter jurisdiction) and the per- sons over whom the court may exercise adjudicatory au- thority (personal jurisdiction).” Id. These rules are distinct from “nonjurisdictional claim-processing rules, which ‘seek to promote the orderly progress of litigation by requiring that the parties take certain procedural steps at certain specified times.’” Id. at 1849 (quoting Henderson v. Shinseki, 562 U.S. 428, 435 (2011)). “Characterizing a rule as a limit on subject-matter ju- risdiction ‘renders it unique in our adversarial system.’” Id. (quoting Auburn, 568 U.S. at 153). “Harsh conse- quences attend the jurisdictional brand.” Id. (cleaned up). As the Supreme Court has noted, “[j]urisdictional rules may also result in the waste of judicial resources and may unfairly prejudice litigants.” Henderson, 562 U.S. at 434. Because objections to subject-matter jurisdiction may be raised at any time, “a party, after losing at trial, may move to dismiss the case because the trial court lacked subject- matter jurisdiction.” Id. at 434–35. “Indeed, a party may raise such an objection even if the party had previously acknowledged the trial court’s jurisdiction. And if the trial court lacked jurisdiction, many months of work on the part of the attorneys and the court may be wasted.” Id. at 435. Further, “courts must enforce jurisdictional rules sua sponte, even in the face of a litigant’s forfeiture or waiver.” Santos-Zacaria v. Garland, 143 S. Ct. 1103, 1112 (2023). “Because the consequences that attach to the jurisdic- tional label may be so drastic,” the Supreme Court has “urged that a rule should not be referred to as jurisdictional unless it governs a court’s adjudicatory capacity.” Case: 21-2323 Document: 54 Page: 4 Filed: 08/22/2023

Henderson, 562 U.S. at 435. In light of the Supreme Court’s direction to “police this jurisdictional line,” Wilkins, 143 S. Ct. at 876, we consider whether the FAR require- ment to state a sum certain in bringing a claim under the CDA, 41 U.S.C. §§ 7101–7109, is indeed jurisdictional. II This case presents facts that reflect the concerns un- derlying misapplication of the jurisdictional label. In September 2010, the USACE awarded ECCI Con- tract No. W912ER-10-C-0054 to design and construct a Special Operations Forces Joint Operations Center com- pound at Mazar-e-Sharif, Afghanistan, for $29,186,338.00. Shortly after beginning work on the project, ECCI alleges it began experiencing delays. On February 12, 2014, ECCI submitted a request for equitable adjustment to the con- tracting officer pursuant to the CDA seeking $13,519,913.91 for 329 days of alleged government delays. J.A. 47. ECCI’s claim asserted that “significant delays caused by the [g]overnment during the project, hindering [ECCI’s] ability to efficiently complete the project[,] . . . . entitle ECCI to a time extension for the contract as well as financial compensation, as requested in accordance with the contract.” J.A. 54. ECCI structured its delay claim into three categories of government-caused delay: (1) delay in reviewing the 95% and 100% design submissions (“design delay”); (2) delay as- sociated with directives to perform additional work beyond the scope of work or changed contract requirements (“addi- tional work delay”); and (3) delay associated with changed security requirements (“security changes”). Id. The claim and its attachments included a chart summarizing the “to- tal days of critical path impact experienced by ECCI and its primary subcontractors” each month, J.A. 150 (claim, Figure 34); a table breaking down the critical path impact days for various aspects of the 95% and 100% design sub- missions, J.A. 156–62 (Attachment A); and a cost estimate Case: 21-2323 Document: 54 Page: 5 Filed: 08/22/2023

ECC INTERNATIONAL CONSTRUCTORS, LLC v. 5 SECRETARY OF THE ARMY

report with estimates for direct costs (e.g., labor, labor overhead, equipment, and subcontractors), indirect costs (e.g., general and administrative expenses), and daily costs for each month in which delay occurred, J.A. 315–64 (At- tachment W). Although ECCI’s claim requested a contract- ing officer’s final decision, ECCI did not receive a final decision from the contracting officer. ECCI accordingly considered the nonresponse a deemed denial of its claim. 1 On October 23, 2014, ECCI filed an appeal with the Board, which docketed the appeal as ASBCA No. 59586. J.A. 1407. And so began a complex negotiation and litiga- tion history.

Free access — add to your briefcase to read the full text and ask questions with AI

Ecc International Constructors, LLC v. Secretary of the Army, 79 F.4th 1364 (Fed. Cir. 2023).

79 F.4th 1364 (Ecc International Constructors, LLC v. Secretary of the Army) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.A.M. Construction Services, Inc.
Armed Services Board of Contract Appeals, 2026
Dunbar-Brown v. United States
Federal Claims, 2026
Endure Industries, Inc.
Armed Services Board of Contract Appeals, 2026
Sanchez v. United States
Federal Claims, 2026
Lift Up Trucking, LLC
Armed Services Board of Contract Appeals, 2026
Rocky Freeman v. J. Lincalis
Third Circuit, 2025
Warfighter Defense Inc.
Armed Services Board of Contract Appeals, 2025
GE Renewables US, LLC
Armed Services Board of Contract Appeals, 2025
D-STAR Engineering Corp.
Armed Services Board of Contract Appeals, 2025
Envistacom, LLC
Armed Services Board of Contract Appeals, 2025
Dari Concepts, LLC
Armed Services Board of Contract Appeals, 2025
AECOM Technical Services, Inc.
Armed Services Board of Contract Appeals, 2025
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
A4 Construction Company, Inc.
Armed Services Board of Contract Appeals, 2024