GE Renewables US, LLC

CourtArmed Services Board of Contract Appeals
DecidedJune 24, 2025
Docket63842
StatusPublished

This text of GE Renewables US, LLC (GE Renewables US, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GE Renewables US, LLC, (asbca 2025).

Opinion

DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) GE Renewables US, LLC ) ASBCA No. 63842 ) Under Contract No. W91278-21-C-0010 )

APPEARANCES FOR THE APPELLANT: Dawn-Carole Harris, Esq. Ken Algiene, Esq. Counsel

Daniel J. Cook, Esq. Thomas E. Daley, Esq. DLA Piper LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Kaley E. Angus, Esq. Kristine M. Knodel, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Mobile

OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE GOVERNMENT’S MOTION TO DIMISS

The appellant GE Renewable US, LLC (GE) seeks a declaration that it has the right to pursue a price adjustment under an economic price adjustment clause. The United States Army Corps of Engineers (government) moves to dismiss for failure to state a claim (Motion), arguing that GE has failed to state a sum certain for what is essentially a monetary claim. GE argues that the government forfeited that defense because the litigation had far progressed when it filed the Motion. In the alternative, GE argues that the Motion is meritless because its claim merely raises an issue of contract interpretation that does not require it to state a sum certain.

For the reasons discussed below, we conclude that the government has not forfeited the Motion because litigation only had progressed to the discovery phase DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

when GE filed the Motion. Moreover, the Motion has merit. Because the only significant consequence of a declaration that GE has the right to seek a price adjustment under an economic price adjustment clause would be a price adjustment— as opposed to a change in contract performance or the avoidance of costs—the claim is essentially monetary. As a result, the claim had to state a sum certain. However, based upon a review of the record, the claim did not state a sum certain. Thus, we dismiss the appeal without prejudice for failure to state a claim. 1

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION 2

1. On March 29, 2021, the government awarded Contract No. W91278-21-C- 0010 (Contract) to GE (compl. ¶ 25). The Contract incorporated by reference Federal Acquisition Regulation (FAR) 52.216-4, ECONOMIC PRICE ADJUSTMENT— LABOR AND MATERIAL (JAN 2017) (compl. ¶ 26). FAR 52.216-4 stated that:

(a)The Contractor shall notify the Contracting Officer (CO) if, at any time during contract performance, the rates of pay for labor (including fringe benefits) or the unit prices for material shown in the Schedule either increase or decrease. . . . The notice shall include the Contractor’s proposal for an adjustment in the contract unit prices to be negotiated under paragraph (b) of this clause, and shall include, in the form required by the CO, supporting data explaining the cause, effective date, and amount of the increase or decrease and the amount of the Contractor’s adjustment proposal.

(b)Promptly after the CO receives the notice and data under paragraph (a) of this clause, the CO and the Contractor shall negotiate a price adjustment in the contract unit prices and its effective date.

48 C.F.R. § 52.216-4.

1 Because we dismiss for failure to state a claim, we need not—and do not—address the government’s alternative argument that GE failed to certify its claim, which purportedly exceeded $100,000 (mot. 7-8). 2 For purposes of deciding this motion only, we accept the factual allegations in the complaint and the claim as true.

2 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

2. On June 23, 2022, GE sent a written notification to the government of its intent to pursue a price adjustment under the Economic Price Adjustment Clause (EPA) (compl. ¶ 31). The government rejected a price adjustment on the grounds that EPAs do not apply to construction contracts such as the Contract (id. ¶¶ 33, 35, 37).

3. On December 6, 2023, GE submitted a “merit-only” claim, asserting that “there is no quantum” (R4, tab 1 at 1). Under the “relief sought” section, the claim indicated that “GE requests that the CO determine that FAR 52.216-4 is enforceable and GE has a right to an adjustment under the clause. GE further requests that the CO direct the parties to enter into negotiations for a bilateral modification to resolve the issue.” The claim did not seek a sum certain. (Id. at 7)

4. On February 5, 2024, the CO issued a final decision denying the claim (compl. ¶ 39).

5. This appeal followed. Like the claim, the complaint indicates that this is a merit-only appeal for contract interpretation, and does not seek a sum certain (compl. at 10).

6. On March 21, 2025, the government filed the Motion. Under the scheduling order in effect at the time, discovery was to close on April 7, 2025 (Bd. corr. ltr. dtd. January 27, 2025).

DECISION

The government has not forfeited its right to bring the Motion. Moreover, the Motion has merit. GE fails to state a claim because its claim is essentially a monetary claim, but lacks a sum certain.

I. The Motion to Dismiss Is Timely

The government has not forfeited the Motion. The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101 et seq., requires a contractor to submit a claim as a jurisdictional prerequisite to filing an appeal to the Board. Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed. Cir. 1995) (en banc). However, the CDA does not define the term “claim.” 41 U.S.C. §§ 7101 et seq. Nevertheless, the FAR defines a claim as, a “written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the

3 DOCUMENT FOR PUBLIC RELEASE. The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release.

contract.” 48 C.F.R. § 2.101. Thus, the United States Court of Appeals for the Federal Circuit has recognized that, while the requirement is not jurisdictional:

[I]t is mandatory for a party submitting a claim under the CDA seeking monetary relief to include a sum certain indicating for each distinct claim the specific amount sought as relief. . . . If a party challenges a deficient sum certain after litigation has far progressed, however, that defense may be deemed forfeited.

ECC Int’l Constructors, LLC v. Sec’y of Army, 79 F.4th 1364, 1380 (Fed. Cir. 2023) (holding that the government forfeited a lack of a sum certain defense by not raising it until after a hearing on the merits). In particular, we have held that the government had not forfeited a lack of a sum certain defense by raising it during discovery. A4 Constr. Co., ASBCA No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
GE Renewables US, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ge-renewables-us-llc-asbca-2025.