Trafalgar House Construction, Inc. v. ZMM, Inc.

567 S.E.2d 294, 211 W. Va. 578, 2002 W. Va. LEXIS 100
CourtWest Virginia Supreme Court
DecidedJune 19, 2002
Docket30246
StatusPublished
Cited by28 cases

This text of 567 S.E.2d 294 (Trafalgar House Construction, Inc. v. ZMM, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trafalgar House Construction, Inc. v. ZMM, Inc., 567 S.E.2d 294, 211 W. Va. 578, 2002 W. Va. LEXIS 100 (W. Va. 2002).

Opinion

PER CURIAM.

In this appeal of a January 25, 2001 order from the Circuit Court of Kanawha County, the appellants contend that the circuit court improperly granted summary judgment to the appellees. After careful consideration of the record, we find genuine issues of material fact exist for jury resolution, and reverse the circuit court’s order.

I.

The instant case arises from the construction of a Job Corp facility for the United States Department of Labor (“the DOL”) in Charleston, West Virginia. The DOL hired appellee DMJM/HTB to select a site for the facility, and in turn DMJM/HTB chose appel-lee ZMM, Inc., to be the architect for the facility. ZMM, Inc., then contracted with appellees Chapman Technical Group, Ltd., and The H.C. Nutting Company to perform various civil and geotechnical engineering of the site.

Once a site was chosen and plans crafted for the construction of the facility, bid documents were prepared by the appellees so that contractors and subcontractors could estimate their costs. As the lowest bidder on the government project, appellant Trafalgar House Construction, Inc. (“Trafalgar House”) was hired as the general contractor for the project. Trafalgar House subcontracted the task of moving rock, dirt and otherwise preparing the site for construction to appellant Kimberly Industries, Inc. (“Kimberly”), which also relied upon the bid documents in preparing its estimate.

The dispute between the parties is a result of alleged errors contained in the bid documents, primarily regarding the amounts of dirt and of rock needed to complete the preparation of the site.

In April 1995, Kimberly began excavating portions of the site and discovered significant amounts of “uncontrolled fill,” material which could not support the construction of the buildings. Kimberly was required by the DOL to remove the unacceptable uncontrolled fill, dispose of it, and replace it with acceptable engineered fill. Approximately 88,000 cubic yards of material was removed, and an off-site mine was established so that 88,000 cubic yards of engineered fill could be imported.

*582 Also, while the bid documents estimated that 27,000 cubic yards of rock would be needed to complete the project, Kimberly discovered that 46,000 cubic yards of rock were actually needed. Furthermore, while 27,000 cubic yards of rock were available on the site, Kimberly discovered that only 10,-000 cubic yards were usable; the remainder was of poor quality and had to be removed from the site as waste. Kimberly was required to set up an off-site quarry and mine 36,000 cubic yards of rock to be imported for use at the site.

Kimberly argues that it incurred nearly $5 million in additional costs excavating and replacing the uncontrolled fill and in importing usable rock fill. As early as July 1996, both Trafalgar House and Kimberly were retaining engineering firms and attorneys to investigate methods to recover the additional costs incurred. Both appellants sought to determine why the bid documents prepared by the appellees misrepresented the actual conditions discovered under the surface of the construction site, and sought to establish the extent to which subsurface conditions differed from those portrayed in the bid documents so as to support a claim for additional compensation under the contract.

On April 5, 1996, Kimberly filed a “Request for Equitable Adjustment” with the DOL to obtain additional compensation under its contract. The Request for Equitable Adjustment alleged a “Type I” condition existed at the site, that is, that the on-site subsurface conditions varied materially from those indicated in the plans and other bid documents. Kimberly asserted that the additional costs “stem[med] from differing site conditions or defective specifications regarding the anticipated soils on the project.”

In order to litigate its Request for Equitable Adjustment claim with the DOL, Kimberly filed a Freedom of Information Act request in August 1996. The DOL did not respond to the Freedom of Information Act request until December 1996, and then only produced a few documents. In fact, the DOL did not rule on the Request for Equitable Adjustment until 1999.

In April 1997, two years after beginning construction, appellant Kimberly sued appellant Trafalgar House to recover the additional costs of construction. Using the authority of the court, during March and April 1998 the appellants subpoenaed all of the plans and other project documents from the DOL and the appellees.

The appellants assert that on or about April 15, 1998, in the thousands of pages of documents they received in response to the subpoenas, they discovered that the appel-lees knew before construction began that there would be shortages of dirt and rock on the site, but deleted references to those shortages from bid documents that were provided to the appellants. The appellants inferred from the documents that the appellees knew there would be a shortage of usable material, but concealed that knowledge in an attempt to shift the cost of those shortages onto unsuspecting contractors such as the appellants.

Shortly thereafter the appellants settled their dispute with each other, and on July 1, 1998, filed the instant suit against the appel-lees. The appellants asserted that the appel-lees had fraudulently and/or negligently misrepresented the site’s adverse subsurface conditions in the bid documents.

After substantial discovery, the appellees filed motions for summary judgment. The appellees first argued that under the statute of limitation, the appellants had two years from the date their cause of action was discovered to file a lawsuit. Citing to documents from the appellants’ files, the appel-lees argued that during 1995, and certainly as late as the April 5, 1996 Request for Equitable Adjustment, the appellants knew that the plans and bid documents prepared by the appellees were “defective” and had “misrepresented” site conditions. The appel-lees therefore argued that the appellants’ July 1, 1998 action was barred by the statute of limitations.

Additionally, the appellees contended that the appellants had conducted their own investigation of the site before bidding on the contract, and had even disregarded calculations of rock and dirt made by the appellees in favor of their own. In other words, the appellees argued that even if they made *583 fraudulent misrepresentations of the site conditions, the appellants did not rely upon those representations.

In an order dated January 25, 2001, the circuit court agreed with the appellees. The order concluded that the appellants knew, no later than April 5, 1996, that the appellees had failed to disclose important information in the bid documents, such that the documents “misrepresented” the site conditions. The circuit court therefore held that the ap-pellees’ action for fraudulent or negligent misrepresentation was barred by the statute of limitation. Additionally, the circuit court concluded that the appellants had conducted an independent investigation of the site, and had therefore not relied upon any representations contained in the bid documents prepared by the appellees.

This appeal by the appellants followed.

II.

We review a circuit court’s order granting summary judgment de novo. Syllabus Point 1,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ware v. John Doe
S.D. West Virginia, 2025
Fruth, Inc. v. Cardinal Health, Inc.
S.D. West Virginia, 2024
Pierson v. Kuba
N.D. West Virginia, 2024
Grimmett v. Technology Credit Union
S.D. West Virginia, 2023
Heater v. General Motors LLC
N.D. West Virginia, 2021
Shuff v. Bank of America, N.A.
S.D. West Virginia, 2021
Shelton v. Collins Career Center
S.D. West Virginia, 2020
Brown v. Belt
S.D. West Virginia, 2019
Johns v. Eastman Chemical Co.
248 F. Supp. 3d 765 (S.D. West Virginia, 2017)
Covol Fuels No. 4, LLC v. Pinnacle Mining Co.
14 F. Supp. 3d 724 (S.D. West Virginia, 2014)
Robinson v. Quicken Loans Inc.
988 F. Supp. 2d 615 (S.D. West Virginia, 2013)
Quicken Loans, Inc. v. Brown
737 S.E.2d 640 (West Virginia Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
567 S.E.2d 294, 211 W. Va. 578, 2002 W. Va. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trafalgar-house-construction-inc-v-zmm-inc-wva-2002.