W.M. Schlosser, Inc. v. United States

50 Fed. Cl. 147, 2001 U.S. Claims LEXIS 155, 2001 WL 899633
CourtUnited States Court of Federal Claims
DecidedAugust 8, 2001
DocketNo. 00-495C
StatusPublished
Cited by4 cases

This text of 50 Fed. Cl. 147 (W.M. Schlosser, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.M. Schlosser, Inc. v. United States, 50 Fed. Cl. 147, 2001 U.S. Claims LEXIS 155, 2001 WL 899633 (uscfc 2001).

Opinion

OPINION AND ORDER

HEWITT, Judge.

This is a dispute arising out of a contract between plaintiff W.M. Schlosser, Inc. (Sehlosser) and defendant, acting through the United States Department of the Navy (Navy), for the construction of a project know as the Explosive Test Facility, Naval Surface Warfare Center, Indian Head, MD (project). Complaint (Compl.) f 2.1 Schlos-ser’s two-count complaint seeks equitable adjustments to recover increased field overhead costs resulting from delay and increased costs resulting from differing site conditions. Compl.HH 9,14. The Navy’s contracting officer issued final decisions denying Sehlosser’s [149]*149claims on May 24, 2000, Compl. U 9, and October 27, 1999, Defendant’s Proposed Findings of Uncontroverted Facts in Support of Motion for Summary Judgment (DPFUF) II28,2 respectively. Sehlosser appeals those decisions and requests full payment of its claims. Compl. 119,14.

Defendant moves for summary judgment as to both counts. Defendant’s Motion for Summary Judgment and Defendant’s Brief in Support of Motion for Summary Judgment (Def.Mot.). The matter has been fully briefed. For the reasons set forth below, the court GRANTS defendant’s motion.

1. Background

Sehlosser is a Maryland corporation engaged in construction contracting. Compl. 111. On June 4, 1996, plaintiff entered into Contract No. N62477-94-C-0025 with defendant for construction of a project known as the Explosive Test Facility, Naval Surface Warfare Center, Indian Head, Maryland. Id. H 2. The project involved the construction of five bombproof buildings, as well as parking lots and ancillary sheds. Def. Mot. at 1. Notice to proceed was given on June 19,1996. Id. at 2.

A. Count I: Field Overhead Expenses

The contract provided that the cost of “field overhead” and “overhead on subcontractors” on work resulting from modifications and change orders would be calculated as a percentage of the direct costs of the changed work. Def. Mot. Appendix (App.) at 4. The contract also specifically provided that “[fjield overhead will be evaluated as a percent mark-up and NOT a direct cost to the change proposal.” Id. Plaintiffs bid for these costs was 8 percent of the direct cost of the additional work. Id.

Over the course of performance of the contract, ninety-five changes were either agreed to by the parties or imposed by defendant. DPFUF U 6. These modifications and change orders increased the contract price of $10,696,000.00 by $622,555.50 to $11,318,555.50. DPFUF U 3, 6. Eight of the changes — Nos. A00030 (30), A00033 (33), A00034 (34), A00039 (39), A00044 (44), A00055 (55), A00056 (56), and A00066 (66)— extended the contract completion date by 224 days. DPFUF II6.

With respect to modifications 34, 39, and 44, which together accounted for 46 days of contract period extension, plaintiff was paid $713.73 per day to cover direct costs of field overhead, a type of compensation not contemplated by the contract.3 Compl. 1Í 7; DPFUF II7; Def. Mot. at 6. Plaintiff later requested per diem compensation of $713.73 for field overhead for the remaining 162 days by which the contract was extended. Compl. 118. The contracting officer issued a final decision denying the claim for per diem compensation on May 24, 2000. Id 119; Def. Mot.App. at 30-33; Defendant’s Reply to Plaintiff’s Opposition to Motion for Summary Judgment (Def.Rep.) Attachment (Att.) 2.

B. Count II: Differing Site Conditions

In Count II of its complaint, plaintiff contends that it encountered a differing site condition in the form of unsuitable soil. Compl. 1112. Because it encountered soil “consisting of organic materials and clay” which was “unsuitable for the required construction,” plaintiff “was forced to excavate the unsuitable soil, remove it from the construction site, and import select suitable fill incurr[ing] additional costs of $43,809.05.” Id. Ill 12-13. Defendant replies that the contract itself including the geotechnical report (geotechnical report) provided in the bid package reveals that soils on site did not meet contract specifications and that plaintiff was or should have been aware that it would need to import suitable fill. Def. Mot. at 12-14. By letter dated July 27, 1999, plaintiff requested the contracting officer’s final decision on its claim. Compl. H14. The contracting officer issued a final decision [150]*150denying the claim in a letter dated October 27, 1999.4 DPFUF 1128; Def. Mot.App. at 135.

II. Discussion
A. Summary Judgment and Standard of Review

In deciding defendant’s motion for summary judgment, the court construes all fa'cts in the light most favorable to the nonmovant. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The court will grant the motion when “there is no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.” Rule of the Court of Federal Claims (RCFC) 56; see also Anderson, 477 U.S. at 247, 106 S.Ct. 2505.

B. Count I: Delay

1. Contract Provision for Overhead Expenses and Plaintiffs Claim of Change

The starting point in interpreting a contract is the plain language of the contract. Textron Def. Sys. v. Widnall, 143 F.3d 1465, 1468 (Fed.Cir.1998). Schlosser’s contract with the Navy specified how increased overhead resulting from changes to the contract should be calculated. The contract provides that “[f]ield overhead will be evaluated as a percent mark-up and NOT a direct cost to the change proposal.” Def. Mot.App. at 4.

Plaintiff bid 8% for purposes of this provision and was paid a markup of 8% on work performed under modifications and change orders. DPFUF HH 4,7; Def. Mot.App. at 4. However, with respect to modifications 34, 39, and 44, defendant reports that it “inadvertently failed to apply the percentage method,” Def. Mot. at 3, and paid for delay overhead on a per diem basis instead, DPFUF IT 10. Defendant describes these payments as a “mistake.” Def. Mot. at 3. Plaintiff contends that, notwithstanding the language of the contract, “the Navy agreed to pay Schlosser’s extended field overhead costs” at a per diem rate for all periods of delay. Plaintiffs Opposition to Motion for Summary Judgment (Pl.Opp.) at 2.

In resolving this dispute, the court looks to Federal Circuit precedent, which teaches that the “primary function of the court [in a contract dispute] is the ascertainment of the intention of the parties.” Alvin, Ltd. v. United States Postal Serv., 816 F.2d 1562, 1565 (Fed.Cir.1987) (quoting 4 Samuel Williston & Walter H.E. Jaeger, A Treatise on the Law of Contracts § 601 (3d ed.1961)). In Alvin, the United States Postal Service (Postal Service), prior to 1978, entered into leases for real property. Id. at 1563.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Bailey v. United States
54 Fed. Cl. 459 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
50 Fed. Cl. 147, 2001 U.S. Claims LEXIS 155, 2001 WL 899633, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wm-schlosser-inc-v-united-states-uscfc-2001.