weston/bean Joint Venture v. United States

115 Fed. Cl. 215, 2014 U.S. Claims LEXIS 417, 2014 WL 1004043
CourtUnited States Court of Federal Claims
DecidedMarch 14, 2014
Docket1:11-cv-00031
StatusPublished
Cited by1 cases

This text of 115 Fed. Cl. 215 (weston/bean Joint Venture v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
weston/bean Joint Venture v. United States, 115 Fed. Cl. 215, 2014 U.S. Claims LEXIS 417, 2014 WL 1004043 (uscfc 2014).

Opinion

OPINION AND ORDER DENYING CROSS MOTIONS FOR SUMMARY JUDGMENT

ELAINE D. KAPLAN, Judge,

U.S. Court of Federal Claims

These consolidated eases arise out of a contract between the plaintiff, Weston/Bean Joint Venture (hereinafter “WB”), and the Army Corps of Engineers, for dredging of the Miami River and disposal of contaminated sediments. The cases are before the Court on the parties’ cross motions for summary judgment.

In its complaint and briefs, WB alleges that when it began to perform its work under the contract, the subsurface conditions it found were materially different from those indicated in the contracting documents. Specifically, WB alleges that while the contract indicated that the sediments it would be required to dredge and process would consist of fine or coarse particles less than one to two inches in size, the actual sediments WB encountered contained significant amounts of large gravel, as well as cobbles and boulders. Compl. (No. 11-31) (hereinafter “Compl. 1”) ¶¶ 67-73, 96-98; Pl.’s Resp. 9-11. It further claims that these allegedly unforeseeable conditions required it to incur significant excess costs related to the processing and disposal of the sediments. Compl. 1 ¶¶ 106-113, 116-119; Compl. (No. 11-360) (hereinafter “Compl. 2”) ¶ 83; Pl.’s Resp. 11-13. WB also claims that certain work that the Army Corp of Engineers directed it to perform in connection with the project constituted a constructive change, that the government provided defective specifications for the project which resulted in damage to certain seawalls, that the government breached its implied duty to cooperate, that it unreasonably failed to grant extensions of time to complete work, and that the government improperly retained or assessed liquidated damages. Compl. 1 ¶¶ 102-105, 118; Compl. 2 ¶¶ 70-74, 80, 102, 132-137; Pl.’s Resp. 11-75. WB seeks an equitable adjustment of the contract amount, a time extension of 348 days, and *217 $12,423,937.23 in damages, plus interest, costs and attorney fees. Pl.’s Resp. 1-2.

Both WB and the government have submitted voluminous briefs and exhibits in support of their cross motions for summary judgment. In addition, the Court held oral argument on the cross motions on March 7, 2014. For the reasons set forth below, the Court has concluded that there exist disputed issues of material fact which render summary judgment inappropriate. Further, the Court has concluded that the proper resolution of plaintiffs claims would benefit from full development of the record at trial. Accordingly, the cross motions for summary judgment are denied.

DISCUSSION

A. Jurisdiction

The Court has jurisdiction over WB’s contract claims under the Tucker Act. 28 U.S.C. § 1491(a)(1) (conferring jurisdiction on the Court of Federal Claims to hear “any claim against the United States founded ... upon any express or implied contract with the United States, or for liquidated or unliquidat-ed damages in cases not sounding in tort”).

B. Standard for Summary Judgment

The standards for granting summary judgment are well established. Summary judgment may be granted where there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. Rules of the Court of Federal Claims (RCFC) 56(a); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). A fact is material if it “might affect the outcome of the suit under the governing law.” Id. at 248, 106 S.Ct. 2505. An issue is genuine if it “may reasonably be resolved in favor of either party.” Id. at 250, 106 S.Ct. 2505.

The moving party bears the burden of establishing the absence of any genuine issue of material fact, and all significant doubts regarding factual issues must be resolved in favor of the party opposing summary judgment. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). “The fact that both parties have moved for summary judgment does not mean that the court must grant judgment as a matter of law for one side or the other; summary judgment in favor of either party is not proper if disputes remain as to material facts.” Id. at 1391. Further, the court should act with caution in granting summary judgment and may deny summary judgment “where there is reason to believe that the better course would be to proceed to a full trial.” Anderson, 477 U.S. at 255, 106 S.Ct. 2505.

C.Summary Judgment is Inappropriate; the Adjudication of WB’s Claims Would Benefit From Full Development of the Record at Trial.

The gravamen of WB’s complaint consists of a “Type I” differing site conditions claim based on the alleged existence of “subsurface or latent physical conditions at the site which differ materially from those indicated in [the] contract.” FAR 52.236-2(a); Int’l Tech. Corp. v. Winter, 523 F.3d 1341, 1348 (Fed.Cir.2008); see also Renda Marine, Inc. v. United States, 509 F.3d 1372, 1376 (Fed.Cir.2007) (differentiating Type I and Type II differing site conditions). A contractor seeking to “ ‘establish entitlement to an equitable adjustment by reason of a Type I differing site condition ... must prove, by a preponderance of the evidence, that the conditions indicated in the contract differ materially from those [the contractor] encountered] during performance.’” Randa/Madison Joint Venture III v. Dahlberg, 239 F.3d 1264, 1274 (Fed. Cir.2001) (quoting H.B. Mac, Inc. v. United States, 153 F.3d 1338, 1345 (Fed.Cir.1998); see also Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1581 (Fed.Cir.1987)) (internal quotations omitted). To determine whether plaintiff has met this burden, the court must “place itself into the shoes of a ‘reasonable and prudent’ contractor, and ascertain whether the conditions actually encountered were reasonably unforeseeable on the basis of all the information available to the contractor at the time of bidding,” Spirit Leveling Contractors v. United States, 19 Cl.Ct. 84, 94 (1989) (quoting P.J. Maffei Bldg. *218 Wrecking Corp. v. United States, 732 F.2d 913, 917 (Fed.Cir.1984)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
115 Fed. Cl. 215, 2014 U.S. Claims LEXIS 417, 2014 WL 1004043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westonbean-joint-venture-v-united-states-uscfc-2014.