Cent. Allied Ents., Inc. v. Adjutant General's Dept.

2010 Ohio 3229
CourtOhio Court of Claims
DecidedJune 18, 2010
Docket2007-07841
StatusPublished

This text of 2010 Ohio 3229 (Cent. Allied Ents., Inc. v. Adjutant General's Dept.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cent. Allied Ents., Inc. v. Adjutant General's Dept., 2010 Ohio 3229 (Ohio Super. Ct. 2010).

Opinion

[Cite as Cent. Allied Ents., Inc. v. Adjutant General's Dept., 2010-Ohio-3229.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

CENTRAL ALLIED ENTERPRISES, INC.

Plaintiff/Counter Defendant

v.

THE ADJUTANT GENERAL’S DEPARTMENT

Defendant/Counter Plaintiff Case No. 2007-07841

Judge Joseph T. Clark

DECISION

{¶ 1} Plaintiff/counter defendant, Central-Allied Enterprises, Inc. (CAE), brought this action alleging breach of contract, unjust enrichment, and constructive change order. Defendant/counter plaintiff, the Adjutant General’s Department (AGD), filed a counterclaim for breach of contract. The issues of liability and damages were bifurcated initially; however, prior to the commencement of trial and with the consent of the court, the parties agreed to proceed to trial on both issues. {¶ 2} The case concerns a project to rebuild the helicopter apron at the Akron Canton Army Aviation Support Facility. Initially, AGD hired Superior Asphalt Paving Company to mill the existing asphalt; however, the milling operation was halted when the surface began shifting due to excessive moisture in the soil. (Defendant’s Exhibit B.) AGD then hired Whitworth Borta (WB), an engineering company that specialized in the design of airports, to redesign the project and prepare the plans and specifications. {¶ 3} WB hired Hall’s Testing and Consulting (Hall) to assess the soil composition and to determine whether the soil had the appropriate strength-bearing characteristics necessary for airport construction. Hall prepared a report which concluded that the soil was suitable for construction “when brought to proper moisture conditions.” (Plaintiff’s Exhibit 4.) The Hall report was available for review pre-bid and was included as an addendum to the contract documents. {¶ 4} CAE’s field engineer, Joe Seck, testified that he read the Hall report and that he walked over the construction site prior to the submission of CAE’s bid. CAE was the low bidder and in July 2003, entered into a lump-sum contract with AGD. According to Seck, CAE was to reconstruct the access road, to excavate and replace the apron as designed, and to excavate the area located adjacent to the apron designated for a detention pond.1 WB’s design included lengthening the taxiway and reconstructing the apron. It is undisputed that the apron area spanned approximately 11 acres. WB’s plans called for removal of the existing asphalt and excavation of the soil to a depth of 20 inches, to be replaced with 12 inches of aggregate topped with eight inches of new asphalt in order to accommodate the heavier Chinook helicopters. Augustine Ubaldi, WB’s principle and professional engineer, testified that WB was not the construction manager but remained on site for quality assurance and to serve as the associate for AGD. WB also provided the layout at the site and established the grades. {¶ 5} CAE asserts that during the apron reconstruction, isolated areas of unsuitable soil were encountered in August and September 2004, such that CAE’s subcontractor was required to excavate several more inches to reach stable soil and to replace the excavated soil with additional aggregate. In some of these areas, CAE layered “geo-fabric” with the aggregate in order to bring the soil to suitable strength. CAE seeks reimbursement for the costs of this extra work not contemplated by the contract as bid. {¶ 6} CAE asserts that during those times when the unsuitable soil was discovered, representatives from WB and CAE were present but they were unable to reach an agreement as to payment for the added excavation. CAE chose to proceed with the work so as not to delay the project and both parties agreed that any additional costs would be reconciled by a final change order to be prepared and submitted upon CAE’s completion of the project. Seck testified that CAE’s work on the project was substantially complete in December 2004. According to Seck, the only remaining tasks included repair seeding, some asphalt paving, and a few electrical adjustments with the gate openers. Seck testified that he had requested final quantities from WB and that he was waiting for verification of quantities used for the excavation in order to prepare the final change order; however, WB did not provide such numbers to CAE. Seck testified that he completed his own calculations in reference to the undercuts and that he then asked WB to submit the proposed change order in January 2006, but that WB did not respond to that request either. (Plaintiff’s Exhibit 8.) {¶ 7} CAE eventually received an e-mail from Steve Potoczak, WB’s vice president, sent January 25, 2006, which states as follow: {¶ 8} “Joe and Ken: {¶ 9} “Just thought I would give you a courtesy email and tell you that we have stopped working on all work related to the AASF No.1 project because our contract is and has been expired and we have not been paid for some time now. I know you know about how it works to get back into the ‘system’ and get paid. So, bear with me on this one. Hopefully things will get straightened out soon. {¶ 10} “I’ve gotten your pay requests and was working on the closeout package (which includes a closeout change order for each of you) but have stopped for now. I would advise that you both check with the [AGD] and see if your contracts are expired too.” (Plaintiff’s Exhibit 9.) CAE subsequently instituted this action. {¶ 11} AGD contends that CAE’s claim is untimely, that CAE failed to submit a written change order both before incurring additional costs and prior to completion of CAE’s work on the project, and that AGD did not execute a written waiver of the requirement for a written change order. Thus, AGD contends that CAE’s failure to provide timely notice of the claim for extra work constitutes a waiver of such claim. In addition, AGD asserts that CAE cannot prevail on a claim for unjust enrichment or constructive change order when the work at issue is governed by the terms of an express contract. Finally, AGD has asserted a counterclaim, wherein AGD contends that although CAE may have excavated more soil and used more aggregate at the

1 A detention pond is designed to collect and store storm water runoff which is then allowed to leach into the ground. apron area, it excavated less soil and placed less aggregate material at the detention pond such that AGD is entitled to a rebate of approximately $11,000. {¶ 12} CAE disputes the counterclaim under the theory that this was a fixed-sum contract and that CAE performed all that was required to complete the project along with the extra work. CAE makes the distinction that the detention pond ended up being smaller than originally designed and that the area required less excavation to achieve the desired grade; however, such alterations were not accomplished by a change order issued by AGD. Therefore, CAE asserts that AGD cannot prevail on the counterclaim. In addition, CAE contends that AGD’s claim is untimely in that the proposed “deduct change order” was issued November 15, 2007, during the course of this litigation and well after the project was completed. {¶ 13} Differing site conditions are addressed in the contract under Article 7. Thus, once CAE determined that there were subsurface concealed conditions that differed materially from those described in the contract documents, the contract provided instructions, specific to such event, that were necessary in order to request additional payment. {¶ 14} In reference to extra or additional work not contemplated by the contract, the parties are directed as follows.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Maghie Savage, Inc. v. P.J. Dick Inc., 08ap-487 (5-5-2009)
2009 Ohio 2164 (Ohio Court of Appeals, 2009)
Struna v. Ohio Lottery Comm., Unpublished Decision (10-21-2004)
2004 Ohio 5576 (Ohio Court of Appeals, 2004)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
University Hospitals of Cleveland, Inc. v. Lynch
96 Ohio St. 3d 118 (Ohio Supreme Court, 2002)
Glidden Co. v. Lumbermens Mutual Casualty Co.
861 N.E.2d 109 (Ohio Supreme Court, 2006)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Univ. Hosps. of Cleveland, Inc. v. Lynch
2002 Ohio 3748 (Ohio Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 3229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cent-allied-ents-inc-v-adjutant-generals-dept-ohioctcl-2010.