W.M. Schlosser Co., Inc. v. The United States

767 F.2d 870, 32 Cont. Cas. Fed. 73,663, 1985 U.S. App. LEXIS 15023
CourtCourt of Appeals for the Federal Circuit
DecidedJune 28, 1985
DocketAppeal 85-746
StatusPublished
Cited by10 cases

This text of 767 F.2d 870 (W.M. Schlosser Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W.M. Schlosser Co., Inc. v. The United States, 767 F.2d 870, 32 Cont. Cas. Fed. 73,663, 1985 U.S. App. LEXIS 15023 (Fed. Cir. 1985).

Opinions

NIES, Circuit Judge.

This is an appeal from a decision of the General Services Board of Contract Appeals (board), 84-3 BCA U 17,610, denying a claim by W.M. Schlosser Company, Inc. for the cost of preparing certain drawings in connection with a building renovation contract. The board determined that the drawings were required by the express language of the contract and that an initial submittal by Schlosser had not satisfied that provision of the contract. We affirm.1

Background

On September 28, 1981, the General Services Administration (GSA) awarded Schlosser a contract for miscellaneous repair and improvements at the HEW-North Building in Washington, D.C. at a fixed price of $1,126,738. One aspect of the contract was for the installation of fire/smoke dampers into the building’s existing duct-work. The dampers were designed to shut off the air flowing through the ducts in the event of a fire in the building. Since much of the building’s ductwork was concealed, bids for the contract were based on “contract drawings” supplied by GSA, depicting what was believed to be the layout and size of existing ductwork. To account for any discrepancies between the actual site conditions and those set forth in the contract drawings, the contract included a standard Change Order clause as well as the following “Measurements” clause:

6. MEASUREMENTS

6.1 All dimensions shown of existing work and all dimensions required for work that is to connect with work now in place, shall be verified by the Contractor by actual measurements of the existing work. Any discrepancies between the contract requirements and the existing conditions shall be referred to the Contracting Officer before any work affected thereby has been performed. [Emphasis added.]

The contract also required the following submittals by the contractor:

2. SUBMITTALS
2.1 Manufacturer’s Data: Within 15 days after award of contract and before executing any work, six copies of information in the completely marked and coordinated package sufficient to assure full compliance with the contract requirements shall be submitted to the Contracting Officer for approval. Piecemeal submittal of data is not acceptable. Information shall be submitted for all material and equipment the Contractor proposed to furnish for accomplishment of the contract work. Submittals for each manufactured item shall be manufacturer’s descriptive literature, equipment drawings, diagrams, performance and characteristic curves, and catalog cuts and shall include the manufacturer’s name, trade name, catalog model or number, nameplate data, size, layout dimensions, capacity, specification reference, applicable commercial, Federal and military specification references, and all other information necessary to establish contract compliance.
2.2 Shop Drawings: Within 30 days after award of contract, six copies of consolidated shop drawings in one complete package shall be submitted to the Contracting Officer for approval. The drawing shall be drawn to a minimum scale of Vs" inch equals 1' - 0"; shall be a minimum of 8V2" x 11" in size; and shall include plans, elevations, and sections of equipment and control spaces identifying and indicating proposed and existing location, layout, and arrangement of items of equipment, control panels, accessories, piping, ductwork, and other items that must be shown to assure a coordinated installation. Drawings also shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices. If any equipment is disapproved, drawings shall be revised to [872]*872show approved equipment resubmitted. Piecemeal submittals of drawings or marked-up contract drawings or copies are not acceptable.
15. SHOP DRAWINGS
(a) The term “shop drawings” includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract.
(b) If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate his approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor’s approval may be returned for resubmission. The Contracting Officer will indicate his approval or disapproval of the shop drawings and if not approved as submitted shall indicate his reasons therefor.

Hamilton & Spiegel, Inc. (H & S), to whom Schlosser subcontracted the portion of the contract dealing with installation of dampers, relied entirely on the contract drawings to size individual dampers. H & S sent Schlosser a submittal for the dampers it proposed to install, setting forth the type of damper, its size and location, as well as manufacturer’s literature, catalog cuts, and drawings taken from sales brochures on dampers. Schlosser forwarded the submittal to GSA’s project architect, identifying it as “Manufacturer’s Data.” The architect approved the submittal and returned it to Schlosser, marked as a transmittal of “Shop drawings.” Schlosser then forwarded the material to H & S, identifying it as approved “Manufacturer’s Data.” H & S then ordered the dampers.

Upon cutting access openings in the building walls to install the dampers, H & S discovered that the existing site conditions did not correspond in some cases to the specifications of the contract drawings. As a consequence, some of the dampers ordered were incorrectly sized, while others could not be installed due to obstructions. Schlosser notified GSA of this situation and requested instructions on how to proceed. When GSA requested to see the “shop drawings” showing the actual site conditions, it was informed that the subcontractor had made no such drawings. GSA then directed that they be prepared, so that the extent of the problem could be evaluated.

By letter of April 19, 1982, Schlosser advised GSA that H & S had “agreed to provide shop drawings.” H & S prepared and submitted to GSA (through Schlosser) detailed drawings of all new damper locations on Mylar transparencies. Schlosser then filed a claim with the contracting officer in the amount of $16,776 for the costs of additional work and materials (including dampers) allegedly incurred as a result of the discrepancies between the contract drawings and the actual site conditions, including the costs associated with preparing the Mylar drawings.

Subsequently, both parties agreed that the Mylar drawings claim would be pursued under a separate change order. The contracting officer then authorized payment of $9,600 of the original $16,776 claim for the additional labor and materials required to modify existing ducts and to replace dampers which H & S had ordered, but which were not the right size. Schlosser then submitted a separate claim for the costs of preparing the Mylar drawings in the amount of $19,762. The contracting officer denied the claim on the basis that appellant was obligated to provide these drawings under the “shop drawing” requirement specified in paragraph 2.2 of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northrop Grumman Corp. v. United States
42 Cont. Cas. Fed. 77,381 (Federal Claims, 1998)
Abbott v. United States
41 Fed. Cl. 553 (Federal Claims, 1998)
Kanehl v. United States
40 Fed. Cl. 762 (Federal Claims, 1998)
Dawco Construction, Inc. v. United States
36 Cont. Cas. Fed. 75,821 (Court of Claims, 1990)
Weeks Dredging & Contracting, Inc. v. United States
34 Cont. Cas. Fed. 75,356 (Court of Claims, 1987)
Dewey Electronics Corp. v. The United States
803 F.2d 650 (Federal Circuit, 1986)
Mary G. Bonner v. Merit Systems Protection Board
781 F.2d 202 (Federal Circuit, 1986)
Cascade Pacific International v. The United States
773 F.2d 287 (Federal Circuit, 1985)
W.M. Schlosser Co., Inc. v. The United States
767 F.2d 870 (Federal Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
767 F.2d 870, 32 Cont. Cas. Fed. 73,663, 1985 U.S. App. LEXIS 15023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wm-schlosser-co-inc-v-the-united-states-cafc-1985.