Dawco Construction, Inc. v. United States

36 Cont. Cas. Fed. 75,821, 19 Cl. Ct. 656, 1990 U.S. Claims LEXIS 75, 1990 WL 19874
CourtUnited States Court of Claims
DecidedMarch 5, 1990
DocketNo. 429-86C
StatusPublished

This text of 36 Cont. Cas. Fed. 75,821 (Dawco Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawco Construction, Inc. v. United States, 36 Cont. Cas. Fed. 75,821, 19 Cl. Ct. 656, 1990 U.S. Claims LEXIS 75, 1990 WL 19874 (cc 1990).

Opinion

OPINION

MOODY R. TIDWELL, III, Judge.

An electrical subcontractor under a contract awarded by the United States through the Department of the Navy for the rehabilitation of a large number of housing units in San Diego, California, encountered numerous allegedly unforeseeable wiring problems in every unit. The subcontractor, at the contractor’s instructions, proceeded to correct the problems. Defendant refused to pay an additional sum for the “extra” work because the work was included within the contract. The contractor contended that the “extra” work was not included within the scope of the contract and it, therefore, was entitled to an additive equitable adjustment.

FACTS

In mid-1983 plaintiff executed a contract with the Navy for total rehabilitation of a 405-unit naval housing project known as Cabrillo-Larkdale.1 Plaintiff subcontracted with Lo-West Electric, Inc. to perform the electric work required by the contract within the 445 circuit boxes in the 405 units.2 The contract expressly required Lo-West to install new circuits in each unit and modify others but made no specific mention of pre-existing, not-modified circuits. As later found, Lo-West installed or modified between one-third to one-half of the circuits in each circuit box.

The General Provisions of the contract, Clause Thirteen, “CONDITIONS AFFECTING THE WORK,” required the contractor to take reasonable steps “to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof.” Paragraph Twelve of the General Provisions, “PERMITS AND RESPONSIBILITIES,” held the contractor solely “responsible for all damages to persons or property that occur as a result of his fault or negligence [t]o take proper safety ... precautions to protect the work, the workers, the public, and the property of others.” In addition, Technical Specification 16402 Part 3.1, “Installation,” directed plaintiff to comply with all state and local electric codes and “[cjonform with the National Electric Code [NEC].” One section of the NEC bearing directly on this case was paragraph 90-4. It stated:

Enforcement. This Code is intended to be suitable for mandatory application by governmental bodies exercising legal jurisdiction over electrical installations and for use by insurance inspectors. The authority having jurisdiction of enforcement of the Code will have the responsibility for making interpretations of the rules, for deciding upon the approval of equipment and materials, and for granting the special permission contemplated in a number of the rules. The authority having jurisdiction may waive specific requirements in this Code or permit alternate methods, where it is assured that equivalent objectives can be achieved by establishing and maintaining effective safety.

Prior to bidding, Mr. James Benson, plaintiff, Mr. Douglas Blum, a partner-owner of Lo-West, and representatives of defendant made a site inspection to view the [658]*658electric panels and outlets to attempt to determine if there were unknown wiring problems that might come to bear on the work. When Messrs. Benson and Blum arrived on the site they viewed only two panels out of the 445.3 Mr. Blum simply opened the panel door which permitted him see only the circuit breaker toggles and the directory card.4 Mr. Rudin, the other partner-owner of Lo-West, testified that it was not industry practice to remove the dead front during pre-bid site inspection unless there is some indication in the specifications or drawings of problems in the panel boxes. There was no indication or statement in the contract of wiring or circuit problems in the panel boxes and Mr. Rudin agreed with Mr. Blum that there was no need to look behind the dead front or to see more than the two panels offered for inspection by defendant.

During performance Lo-West discovered numerous conditions in the boxes that it had not anticipated. There were loose hot wires, doubled up circuits on a single circuit breaker (three to four wires attached to the same circuit breaker), some circuit breakers with no wires connected to them, a large number of broken circuit breakers, other forms of improper wiring, and wires with broken or missing insulation. There is no question but that several of the problems encountered were potentially very dangerous. In one especially egregious instance, a plumber received a severe electric shock when a pipe he was working with came into contact with an uninsulated wire, even though the circuit breaker feeding that circuit was in the “off” position. There were also other reported instances of electric shocks to persons working on the project, one involving Mr. Benson.

Lo-West informed plaintiff early in performance of the contract of the discovered conditions and Mr. Benson discussed them with Mr. Richard Thurman, the now-deceased contracts manager assigned to the Cabrillo-Larkdale project. Upon viewing the panel boxes Mr. Thurman agreed that a safety problem existed for the workmen and to leave them uncorrected would be unsafe and constitute violations of the state electrical code and the NEC. At the least, Mr. Thurman orally directed plaintiff to correct the dangerous conditions at that time.

Both Mr. Blum and Mr. Rudin described the process by which they performed this task. Mr. Rudin testified that two electricians were required. One would stand by the panel box while the other would roam throughout the unit. All but one of the circuit breakers would be turned off and the “roamer” would seek out the live circuit, ie., all of the outlets, etc., that were on that one circuit. That process was repeated for each circuit and breaker. The electrician standing by the panel box would then label the breaker on the directory card affixed to the back of the panel door. There were a variety of floor plans and no one panel box was identical to any other. Each panel box served from thirty to fifty outlets within each unit consisting of wall outlets, wall switches, ceiling lights, laundry facilities, fire and smoke detectors, furnaces and other miscellaneous outlets. This tracing and labeling procedure was followed for all circuits and circuit breakers in all of the units, including those circuits not added or modified by plaintiff. Mr. Rudin estimated that it took a total of approximately 1,000 man-hours to completely trace and label all of the circuits in all of the 445 panel boxes. The extra work for which equitable adjustment was sought consisted of “tracing, identifying and labeling” all circuits in each panel box, including those not added or modified.5

[659]*659The parties met on October 13, 1983 to discuss the wiring problems and other matters which plaintiff had submitted to defendant as claims. In attendance at this meeting were Messrs. Benson, Thurman, Heimerman (plaintiff’s quality control officer) and others. The minutes of that meeting were taken by Mr. Heimerman and copies were given to defendant. After discussing the wiring claim for tracing, identifying and labeling all circuits including the preexisting, not-modified circuits, Mr. Thurman instructed Mr. Benson to provide defendant with a cost proposal for the extra work. Mr. Heimerman’s notes indicate that the Resident Officer in Charge of Construction (ROICC) would approve the claim. Defendant did not object to, criticize or suggest corrections to Mr. Heimerman’s minutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
City of Alexandria v. The United States
737 F.2d 1022 (Federal Circuit, 1984)
W.M. Schlosser Co., Inc. v. The United States
767 F.2d 870 (Federal Circuit, 1985)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Ball State University v. United States
488 F.2d 1014 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,821, 19 Cl. Ct. 656, 1990 U.S. Claims LEXIS 75, 1990 WL 19874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawco-construction-inc-v-united-states-cc-1990.