C. W. Blakeslee & Sons, Inc. v. United States

89 Ct. Cl. 226, 1939 U.S. Ct. Cl. LEXIS 214, 1939 WL 4250
CourtUnited States Court of Claims
DecidedMay 1, 1939
DocketNo. 43250
StatusPublished
Cited by16 cases

This text of 89 Ct. Cl. 226 (C. W. Blakeslee & Sons, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. W. Blakeslee & Sons, Inc. v. United States, 89 Ct. Cl. 226, 1939 U.S. Ct. Cl. LEXIS 214, 1939 WL 4250 (cc 1939).

Opinion

Williams, Judge,

delivered the opinion of the court:

.Plaintiffs, and the United States, through its contracting officer, entered into a contract on December 7, 1933, whereby plaintiffs agreed to furnish all labor and materials and perform all work required for the construction of the substructure of the Vertical Lift Railway Bridge over the Cape Cod Canal, at Buzzards Bay, Massachusetts, in accordance [241]*241with certain specifications made a part of the contract. Under paragraph No. 102 of the specifications the work to be performed was stated to be the construction of two main piers and two abutments for the bridge, together with certain filling, excavation, grading, removal of' existing structures, and other incidental work.

It is stated in Article 133 of the specifications that wash borings have been made at various points at the site of the work; that these borings were made in the usual manner and with reasonable care arid their locations, depths, and the character of material apparently encountered ■ have been recorded in good faith on the contract plans. It is further stated in Article 133 that there is no expressed or implied agreement that the depths or the character of the material have been correctly indicated and that bidders should take into account the possibility that conditions affecting the cost or quantities of work to be done may differ from those indicated.

Article No. 134 states that borings apparently indicate that boulders may be encountered in varying numbers and sizes at any or all the excavations to be made for the work.

Article 303, as to method of construction, in part provided:

The contractor may construct the piers by . such method as he may elect, subject to the approval of the contracting officer both as to general method and as to details. Each bidder must describe in his bid, in 'writing, the general method he proposes to use, and must be prepared at the time of submitting his bid to submit to the contracting officer full information as to the method,, and consideration will be given to the method proposed, in determining the award of the contract.
* * * * * *
For the construction of these piers it is expected that the contractor will elect to rise one of two methods, either:
(a) the open cofferdam method, involving the usé of steel sheet piling, driven to proper alignment and depth, and adequately braced; or
(b) the caisson method, involving the use of a caisson, presumably of, the open well type to permit excavation in the open, but with provision- for sealing wells and applyiny compressed air if same be found necessary or desirable.

[242]*242Representatives of the plaintiffs visited the site of the-work before. making estimates of the cost of the work or submitting their bid. They-went to the defendant’s engineers’ office and made an examination of the wash borings made by the defendant. They made no borings themselves but relied upon the samples and data of the borings made-by or for the Government to inform themselves before bidding as to the subsurface conditions at the site of the work. It is shown, and we have found, that to make either wash or core borings around the entire perimeter of the proposed excavation would have been impracticable and too expensive, and also that plaintiffs did not have sufficient time to make-borings of their own. Plaintiffs in their bid elected to use-the open cofferdam method in the prosecution of the work.. Eleven contractors other than the plaintiffs submitted bids,, some of whom proposed to use the cofferdam method and others the caisson method. The plaintiffs’ bid was accepted by the defendant and the contract entered into in accordance with the terms thereof. The defendant’s contracting officer approved the method of performing the work proposed by plaintiffs both as to general method and as to details.

'The open cofferdam method of operation entails the driving around a driving frame and down to the specified elevation of interlocking steel sheeting. This forms the perimeter of the particular pier to be constructed. The dimensions of the main channel piers were 44 x 88 feet. As the-sheeting is driven down, the enclosed area is excavated, and when finally excavated to the required depth, the area is poured with concrete and the pier constructed in it. In the operation, the toe of the steel sheething must always be from 8 to 10 feet below the excavation, and the enclosed area is kept free from water or seepage of other subsurface material.

The plaintiffs commenced work promptly and as the work progressed the presence of boulders and impacted gravel seriously hampered the plaintiffs in the driving of the steel sheet piling. This necessitated the removal of boulders at the bottom or toe of the sheeting, and when this was done the outside pressure caused blow-ins or boils which [243]*243filled the cofferdam with sand and water. This delayed the work and made it difficult and hazardous. In March 1934 the plaintiffs and the defendant commenced discussing and studying the situation thus presented. These discussions continued until June 18, 1934, during which time plaintiffs continued their efforts to construct the main channel piers by the cofferdam method. During this time they repeatedly informed the- defendant’s contracting officer that it would be impossible to complete the work by that method as the nesting of boulders made penetration and the driving of the sheeting to grade impossible. On June 18, 1934, plaintiffs and the defendant substantially reached an agreement that the cofferdam method of construction be abandoned, and a new method of construction with changed plans and altered specifications was adopted. A series of change orders were thereupon issued by the contracting officer in which changes in the method of construction were authorized. As a result of the change orders plaintiffs were relieved from excavating to the originally specified depths and were directed, in lieu thereof, to drive oak piles as a foundation for the channel piers. On the receipt of these change orders plaintiffs proceeded with the work under the changed method and completed it promptly and efficiently, without any excess cost beyond that other than as provided in the change orders themselves.

Plaintiffs started work on the change orders for the main piers June 16, 1934. -Based on the original contract price and the work completed at that time, apportioned to the total amount to be done to form the complete structure, their earnings on the main piers, as shown by the United States engineers’ certificates and. vouchers of payment, amounted to $86,380. The actual cost of the work to them on the piers up to this time was $206,595.21, for which they had estimated $66,879.14 in their bid, a claimed loss of $139,-716.07. Adding to this amount their anticipated rate of profit of 10%, raises the loss to $153,687.68. Plaintiffs seek to recover the amount of this loss, which it is contended was the excess cost of completing that portion, of the entire job that was completed up to the date of the first change order, over and above what would .have been the cost of [244]*244completion to that, date, if the subsurface conditions at the site of the work had been such as they had a right to assume they would be from the defendant’s representations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Flippin Materials Co. v. United States
312 F.2d 408 (Court of Claims, 1963)
Archie and Allan Spiers, Inc. v. United States
296 F.2d 757 (Court of Claims, 1961)
Leal v. United States
149 Ct. Cl. 451 (Court of Claims, 1960)
Cassidy & Gallagher, Inc. v. United States
95 Ct. Cl. 504 (Court of Claims, 1942)
Triest & Earle, Inc. v. United States
95 Ct. Cl. 209 (Court of Claims, 1941)
Blauner Construction Co. v. United States
94 Ct. Cl. 503 (Court of Claims, 1941)
General Contracting Corp. v. United States
92 Ct. Cl. 5 (Court of Claims, 1940)
P. J. Carlin Construction Co. v. United States
92 Ct. Cl. 280 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
89 Ct. Cl. 226, 1939 U.S. Ct. Cl. LEXIS 214, 1939 WL 4250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-w-blakeslee-sons-inc-v-united-states-cc-1939.