Consolidated Molded Products Corp. v. United States

600 F.2d 793, 26 Cont. Cas. Fed. 83,199, 220 Ct. Cl. 594, 1979 U.S. Ct. Cl. LEXIS 173
CourtUnited States Court of Claims
DecidedJune 13, 1979
DocketNo. 600-77
StatusPublished
Cited by5 cases

This text of 600 F.2d 793 (Consolidated Molded Products Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Molded Products Corp. v. United States, 600 F.2d 793, 26 Cont. Cas. Fed. 83,199, 220 Ct. Cl. 594, 1979 U.S. Ct. Cl. LEXIS 173 (cc 1979).

Opinion

PER CURIAM: This case comes before the court on defendant’s motion, filed May 10,1979, requesting that the court adopt the recommended decision of Trial Judge Fletcher, filed March 29, 1979, pursuant to Rule 166(c), on the parties’ cross-motions for summary judgment, as the basis for its judgment in this case, neither party having filed a request for review thereof by the court, and the time for so filing pursuant to the Rules of the court having expired. Upon consideration thereof, without oral argument, since the court agrees with the trial judge’s recommended decision, as hereinafter set forth, it hereby grants defendant’s motion and affirms and adopts the recommended decision as the basis for its judgment in this case. Therefore, the Board’s denial of plaintiffs claim must [596]*596be sustained, and, accordingly, plaintiff is not entitled to recover. Plaintiffs motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted, and the petition is dismissed.

OPINION OF TRIAL JUDGE

FLETCHER, Trial Judge:

This contract dispute involves an appeal by plaintiff, Consolidated Molded Products Corporation, from a decision of the Armed Services Board of Contract Appeals (Board), on December 7, 1976, designated as ASBCA No. 210168, 76-2 BCA ¶ 12,177. The Board denied plaintiffs claim for $166,265 arising out of a dispute over a firm fixed-price contract for the supply of parts for certain antipersonnel mines. By cross-motions for summary judgment, the parties have asked the court to review the Board’s decision in accordance with the well-known standards of the Wunderlich Act, 41 U.S.C. §§ 321-22 (1970).

On April 27, 1973, the U.S. Army Munitions Command awarded plaintiff contract No. DAAA 09-73-C-0238 for the delivery of 514,600 "MINE, APERS, M18A1, PARTS FOR” at a unit price of $2.63 or a total contract price of $1,353,398. The contract incorporated by reference to Standard Form 32 the standard "Changes”, "Default”, and "Disputes” provisions.

For nearly 8 years, plaintiff had supplied defendant with the same items, approximating nearly 5,000,000 units during that period. The above-described contract, in conjunction with: 1) the Government’s exercise of an option for increased quantities under that contract, 2) remaining unfilled orders under a previous contract, and 3) a bid on an additional solicitation, resulted in the plaintiff contracting to supply an additional gross total of 1,247,740 units to the Government between November 1973, and January 1975.

However, during the last quarter of 1973, the United States experienced the onset of an "energy shortage” which quickly evolved into the well-remembered "energy crisis” as a result of an oil embargo imposed by certain producing nations in the Middle East, namely, the so-called OPEC group. The embargo resulted in severe shortages of petroleum and petroleum derivative products in the United [597]*597States. Consequently, during the months following November 1973, plaintiff experienced increasing difficulty in obtaining petroleum-based resin products essential to the fulfillment of its previously described contractual obligations.

By Mid-March of 1974, plaintiff had exhausted its total supply of epoxy resins, and no further shipments were forthcoming from its contract-designated supplier, Devcon Corporation. In addition, plaintiff had been unable to place purchase orders with any other suppliers on a firm price and delivery basis. Commencing on November 16, 1973, plaintiff kept the contracting officer fully advised of the deteriorating supply situation.

In a letter to the contracting officer dated May 1, 1974, plaintiff further outlined its supply situation. After noting that production had been stopped on April 3 due to the unavailability of epoxy resin, plaintiff explained that, because of the shortage of all petroleum derivative products, prices for such supplies as could be obtained had increased, and plaintiff had for the most part absorbed those increased costs. Plaintiff further believed that the only feasible solution was to terminate the balance of the order under contract 0238 and add those quantites to contract 0028 or to another solicitation. Plaintiff also stated that it had been advised the epoxy resin shortage would be a relatively short-term problem because the United States Department of Commerce had directed Devcon’s supplier to provide Devcon with sufficient material to meet the plaintiffs needs. In any event, plaintiff was sure that it would "still be left with the problem of substantially higher material costs.” Therefore, under separate cover, the contractor submitted four alternative proposals. Alternative I proposed a no-cost termination of contracts 0238 and 0028. The remaining three alternatives called for shifting orders from contract 0238 to contract 0028 coupled with price adjustments.

The contracting officer responded to the above letter by a letter dated May 31, 1974, stating that the delivery delays resulting from the epoxy resin shortages would constitute an excusable delay within the meaning of the "Default” clause of the contract and that, consequently, the contractor was entitled to an equitable adjustment in the form of a [598]*598delivery schedule revision. The letter went on to request a detailed breakdown of claimed additional expenses accompanied by citations to contractual authority under which entitlement to an equitable price adjustment could be claimed, and closed by advising that plaintiffs suggested alternatives for disposition of the contract remained under evaluation.

By mid-June 1974, plaintiff was able to advise that it had received commitments from Devcon for deliveries of a continuing supply of epoxy resins and that production had been resumed. On August 16, 1974, the contractor submitted the breakdown of its claim for increased expenses due to production interruption. The claimed amount was $166,265.

On November 8, the contracting officer responded to the plaintiffs submission by a letter denying any claim to an equitable price adjustment, and further refused the requested termination as not in the best interest of the Government. That decision was made final by the contracting officer in his opinion dated February 25, 1976. On appeal to the Armed Services Board of Contract Appeals, the contracting officer’s denial of the contractor’s claim was affirmed.

The essence of the plaintiffs contention before the ASBCA was that when supplies of the necessary epoxy resin became unavailable and the parties had no knowledge of when this condition would be relieved, the contract became impossible to perform. Therefore, in its view, plaintiff was constructively excused from further performance. When the epoxy resins again became available (albeit at higher prices), the resumption of production created a contract de novo in the nature of a constructive change entitling the contractor to an equitable adjustment in the original contract price. In support of its position, • plaintiff relied on the Restatement of Contracts, the Uniform Commercial Code, and a number of state judicial authorities. The Board felt it unnecessary to consider those authorities at length because of its conviction that Federal Government contract cases are controlled, not by state law, but by Federal law, citing Penn-Ohio Steel Corp. v. United States, 173 Ct. Cl. 1064, 354 F.2d 254

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WSP USA Solutions Inc.
Armed Services Board of Contract Appeals, 2022
Securityhunter, Inc.
Armed Services Board of Contract Appeals, 2018
Maitland Bros. v. United States
36 Cont. Cas. Fed. 75,835 (Court of Claims, 1990)
Penberthy Electromelt International Inc. v. United States
33 Cont. Cas. Fed. 74,887 (Court of Claims, 1986)
Prestex, Inc. v. United States
31 Cont. Cas. Fed. 71,508 (Court of Claims, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
600 F.2d 793, 26 Cont. Cas. Fed. 83,199, 220 Ct. Cl. 594, 1979 U.S. Ct. Cl. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-molded-products-corp-v-united-states-cc-1979.