Securityhunter, Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 15, 2018
DocketASBCA No. 60896
StatusPublished

This text of Securityhunter, Inc. (Securityhunter, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Securityhunter, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) Securityhunter, Inc. ) ASBCA No. 60896 ) Under Contract No. N39430-13-D-1265 )

APPEARANCE FOR THE APPELLANT: Robert F. Camey, Esq. Whiteford, Taylor & Preston L.L.P. Columbia, MD

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Russell A. Shultis, Esq. Assistant Director David M. Marquez, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT

Securityhunter, Inc., seeks a declaration interpreting a contract with the Naval Facilities Engineering Command (government). In particular, Securityhunter submitted a claim to the contracting officer contending that its obligation to complete performance of a task order was extinguished when the task order and base contract periods of performance expired. The contracting officer concluded in a final decision that Securityhunter remained obligated to complete performance. The Board agrees with the government. Securityhunter' s motion for summary judgment is denied and the government's motion for summary judgment is granted. Securityhunter's appeal is denied.

BACKGROUND

On May 21, 2013, the government awarded Securityhunter the firm-fixed-price, indefinite-delivery, indefinite-quantity contract identified above. The contract sought materials and services for Physical Security/Access Control systems, with work assigned through separate, firm-fixed-price task orders. (R4, tab 1 at 1-2, 4, 7-23, 33-34, 46-47) The contract's initial 365-day period of performance began on May 21, 2013. The contract also provided the government with two option years that it exercised. (R4, tab 1 at 1-3, 23) The second option year's period of performance ended on May 20, 2016 (R4, tab 1 at 32). Among the contract's clauses was Federal Acquisition Regulation I (FAR) 52.216-22, INDEFINITE QUANTITY (OCT 1995). Section (d) provided in pertinent part that:

I (d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and

II Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided that the I Contractor shall not be required to make any deliveries i under this contract after 365 days after contract award. I (R4, tab 1 at 4 7)

On May 7, 2014, the government issued Task Order 0008 (TO 8) under the contract (R4, tab 13). TO 8 incorporated a Performance Work Statement (PWS) for physical security/access control at the Naval Station Norfolk and the Naval Support Activity Hampton Roads (R4, tab 13 at 4, tab 5). 1 The PWS provided specific requirements for Securityhunter to install automated vehicle gates and related systems such as card readers, badging components, sensors, monitors, interfaces, communications, video, license readers, lighting, and related components and software (R4, tab 5 at 81-91). The task order's firm- fixed-price totaled $2,545,798.01 (R4, tab 13 at 521). TO 8 established a 365-day period of performance from May 7, 2014 until May 6, 2015 (R4, tab 13 at 526, tab 5 at 91).

Securityhunter submitted a claim to the contracting officer dated September 8, 2016, seeking an interpretation of the contract. Specifically, Securityhunter observed that, though the government had successfully extended other task orders issued under the contract, it had failed to extend TO 8. Securityhunter therefore stressed that both the contract and task order periods of performance had expired. It maintained that FAR 52.216-22(d) relieved it from any further obligations to complete performance. Accordingly, it declared that it was no longer under contract with the government to perform the PWS. It offered to outline what work remained to be completed. Securityhunter "demand[ ed] that it be released from any further performance under [TO 8] as a result of the expiration of the contract and the task order periods of performance." Securityhunter did not seek a monetary award. (R4, tab 16) The contracting officer denied Securityhunter's claim on October 21, 2016, concluding that Securityhunter was required

1 The task order states that the PWS was dated July 31, 2013 (R4, tab 13 at 523). However, the parties agree that the relevant PWS is one dated August 14, 2013 (app. prop. finding ,i 13, gov't prop. finding ,i 53 n.2).

I 2

l to continue performance of the task order "until the design, procurement, and installation of the necessary automated gate equipment is completed" (R4, tab 18 at 3). 2

This appeal followed. Securityhunter's complaint essentially repeats the allegations of its claim, contending that Securityhunter was relieved from any obligation to deliver supplies and services as a result of FAR 52.216-22(d). It asks that it be "released from any further performance under this task order." It does not seek a monetary award.

DECISION

Securityhunter moves for summary judgment, seeking a declaration from the Board that it was not required to make further deliveries under TO 8 after May 20, 2016. The government cross-moves for summary judgment, suggesting that Securityhunter has not been relieved of the task order's requirements.

Summary judgment should be granted if it has been shown that there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986). The Board's jurisdiction over appeals from the denial of claims includes the power to interpret the parties' contract rights. See Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1265-70 (Fed. Cir. 1999); Kaman Precision Prods., Inc., ASBCA Nos. 56305, 56313, 10-2 BCA ,r 34,529 at 170,287. However, its jurisdiction does not include the power to order specific relief. See MicroTechnologies, LLC, ASBCA Nos. 59911, 59912, 15-1 BCA ,r 36,125. Though Securityhunter's request for a "release" might imply that it seeks specific relief, its claim also requests "interpretation of the contract terms." The appeal is deemed to address contract interpretation. 3

1 Securityhunter 's Motion

Securityhunter's motion for summary judgment relies upon a specific assertion that it did not include in its claim to the contracting officer. It now contends that the government delayed its performance of TO 8 past both the task order's completion date of May 6, 2015, and the base contract's period of performance which, after extension,

2 The contracting officer also stressed that, should Securityhunter disagree with the decision, it remained obligated to continue performance under the contract's Disputes clause, FAR 52.233-1, pending resolution of any further review. 3 On July 26, 201 7, Securityhunter filed an objection to the admissibility of Rule 4 file, tabs 10 through 12, and a motion to strike exhibits attached to the government's brief in opposition to Security hunter's motion for summary judgment and supporting the government's motion. None of these materials are relied upon for the purpose of this decision and therefore the objection and motion are considered moot.

3 ended on May 20, 2016.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Securityhunter, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/securityhunter-inc-asbca-2018.