Daydanyon Corp. v. Department of Defense

600 F. App'x 739
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 9, 2015
Docket2014-1507
StatusUnpublished
Cited by3 cases

This text of 600 F. App'x 739 (Daydanyon Corp. v. Department of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daydanyon Corp. v. Department of Defense, 600 F. App'x 739 (Fed. Cir. 2015).

Opinion

DYK, Circuit Judge.

DayDanyon Corporation (“DayDanyon”) appeals a decision of the Armed Services Board of Contract Appeals (the “Board”) granting summary judgment to the government on DayDanyon’s claim that the ordering deadline of the contract at issue was December 24, 2010, and that the government breached the contract by failing to order the guaranteed minimum quantity of Collapsible Joint Modular Intermodal Containers (“JMICs” or the “containers”) by that date. Because the Board correctly interpreted the contract ordering period as ending on April 23, 2011, we affirm.

*740 Background

On April 23, 2009, the Defense Supply Center Philadelphia (“DSCP”), now known as Defense Logistics Agency Troop Support (“DLATS”), awarded Contract No. SPMSED-09-D-0001 (the “contract”) to DayDanyon for JMICs for use by the Naval Sea Systems Command. The contract provides, in relevant part:

This is a[n] Indefinite Quantity Contract. Orders may be issued on this contract for a period of TWO YEARS.
After First Article Test approval, the required delivery for production quantities under this contract is 120 days after the date of the resulting delivery orders. The Guaranteed Minimum is a total of 500 containers, whether placed for a single CLIN, or combination of CLINS that collectively total 500 containers. The guaranteed minimum is 500 containers per year. Since this is a two year base contract the minimum quantity is multiplied by 2.

J.A. 196. The contract also incorporated several Federal Acquisition Regulation (“FAR”) provisions, including FAR 52.216-22 INDEFINITE QUANTITY (OCT 1995), which provides, in relevant part:

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after Two Years[.]

J.A. 211; see also 48 C.F.R. § 52.216-22. 1

On April 29, 2010, DSCP approved Day-Danyon’s First Article Test sample, and authorized DayDanyon to begin production of the JMICs. On May 3, 2010, DSCP issued two delivery orders for a total of 500 units under the contract, each with a delivery date of August 31, 2010, 120 days following receipt of the order. As of November 23, 2010, the contracting officer had extended the delivery date of the orders to two dates in March 2011. DayDa-nyon did not deliver any JMICs to DSCP by the March 2011 delivery dates.

On April 6, 2011, DayDanyon sent the contracting officer a certified claim for $720,700.00, alleging that DSCP breached the- contract by failing to order the guaranteed minimum of 1,000 JMICs by December 24, 2010. According to DayDanyon’s claim, although the contract had “a two year base period running through April 23, *741 2011,” DSCP was required to order the 1,000 JMICs by December 24, 2010, 120 days prior to the conclusion of the base period, because the contract provided that “delivery orders will specify delivery no less than 120 days from the date of the order,” and because DayDanyon “shall not be required to make any deliveries under this contract after [t]wo [y]ears.” J.A. 522 (quoting J.A. 211). The contracting officer responded that DayDanyon’s claim was “premature” because “[t]he two year base period for [the contract] expires on April 23rd, 2011.” J.A. 526. On April 20, 2011, the contracting officer terminated the contract for default, leading to a default termination claim submitted by DayDanyon on July 11, 2011. On May 18, 2011, Day-Danyon filed another claim, which was materially identical to the April 6, 2011, claim. On July 15, 2011, the contracting officer denied the May 18, 2011, claim, explaining that because the contract was terminated on April 20, 2011, prior to the April 28, 2011, expiration of the base period, the government was not required to order the remainder of the guaranteed minimum quantity of JMICs.

DayDanyon appealed to the Board, which consolidated DayDanyon’s appeals of three separate claims: (1) the default termination claim, No. 57681; (2) the April 6, 2011 claim, No. 57611; and (3) the May 18, 2011, claim, No. 57717. The Board dismissed the May 18, 2011, claim as dupli-cative of the April 6, 2011, claim. On the default termination claim, the Board denied the government’s motion for summary judgment. 2 On DayDanyon’s breach claim, relating to the government’s failure to order the requisite number of JMICs, the Board granted the government’s motion for summary judgment because it rejected DayDanyon’s interpretation of the contract to require the government to order 1,000 JMICs by December 24, 2010, as opposed to April 23, 2011.

DayDanyon appeals. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10). 3 We review the Board’s legal determinations, including interpretations of contracts, de novo. Rockies Express Pipeline LLC v. Salazar, 730 F.3d 1330, 1335-36 (Fed.Cir.2013) (citations omitted).

Discussion

The parties do not dispute that the contract required the government to order 1,000 JMICs prior to the termination of the contract, and that the government only *742 ordered 500 JMICs before December 24, 2010. Instead, the dispute is over the date by which the government was required to order the additional 500 JMIGs. DayDa-nyon contends that the applicable deadline was December 24, 2010, 120 days prior to the end of the two-year ordering period provided in the contract. The government responds that the deadline was April 23, 2011, the end of the two-year ordering period.

DayDanyon’s contention is refuted by the plain language of the contract, which clearly provides for a two-year ordering period. See Bell/Heery v. United States, 739 F.3d 1324, 1331 (Fed.Cir.2014) (“When interpreting a contract, if the provisions are clear and unambiguous, they must be given their plain and ordinary meaning.” (citations and quotation marks omitted)). The contract unambiguously provides that “[ojrders may be issued on this contract for a period of TWO YEARS.” J.A. 196. This language is repeated in the contract’s incorporation of FAR 52.216-18, which provides that “orders may be issued” from the “DATE OF CONTRACT AWARD [April 23, 2009]” through “TWO (2) YEARS.” J.A. 210; see also J.A. 211 (checking the box adjacent to “Base period of two or more years.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paragon Defense Solutions, Inc.
Armed Services Board of Contract Appeals, 2025
Securityhunter, Inc.
Armed Services Board of Contract Appeals, 2018
Delfasco LLC
Armed Services Board of Contract Appeals, 2017

Cite This Page — Counsel Stack

Bluebook (online)
600 F. App'x 739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daydanyon-corp-v-department-of-defense-cafc-2015.