Tecon Corporation, Green Construction Company, and Winston Brothers Company, Joint Venture, Trading as Tecon-Green-Winston v. The United States

411 F.2d 1271, 188 Ct. Cl. 436, 1969 U.S. Ct. Cl. LEXIS 32
CourtUnited States Court of Claims
DecidedJune 20, 1969
Docket143-67
StatusPublished
Cited by10 cases

This text of 411 F.2d 1271 (Tecon Corporation, Green Construction Company, and Winston Brothers Company, Joint Venture, Trading as Tecon-Green-Winston v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tecon Corporation, Green Construction Company, and Winston Brothers Company, Joint Venture, Trading as Tecon-Green-Winston v. The United States, 411 F.2d 1271, 188 Ct. Cl. 436, 1969 U.S. Ct. Cl. LEXIS 32 (cc 1969).

Opinion

PER CURIAM.

This case was referred to Trial Commissioner Roald A. Hogenson with directions to make recommendation for conclusions of law on plaintiff’s motion for summary judgment and defendant’s cross-motion for summary judgment under the order of reference and Rule 99 (c). The commissioner has done so in an opinion and report filed on October 4, 1968, wherein such facts as are necessary to the opinion are set forth. Plaintiff filed a request for review of the commissioner’s report and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. It is, therefore, concluded that plaintiff’s specifications ■ of errors of law and fact in the decision of the Corps of Engineers Board of Contract Appeals should not be sustained; that the board’s findings of fact are supported by substantial evidence; that the board’s decision is correct as a matter of law; that plaintiff’s motion for summary judgment should be, and is, denied; that defendant’s cross-motion for summary judgment should be, and is, allowed ; and that plaintiff’s petition should be, and is, dismissed. .

OPINION OF COMMISSIONER

HOGENSON, Commissioner: On plaintiff’s motion and defendant’s cross-motion for summary judgment, and the supporting briefs of the parties, this case presents 'issues pertaining to the finality of a decision of the Corps of Engineers Board of Contract Appeals, ENG BCA 2704, 67-1 BCA ft 6148. The challenged decision denied plaintiff’s claim presented to the board under the standard changes, suspension of work, and disputes articles of the contract (DA-34-066-CIVENG — 60-1407) entered into on January 11, 1960, by and between plaintiff and defendant, acting by and through the Corps of Engineers, Department of the Army. Under such contract, plaintiff constructed the spillway, power intake, and power substructure of the Eufaula Dam on the Canadian River in Oklahoma. Plaintiff asserts that the board’s decision is not final and conclusive under the standards of judicial review prescribed by the Wunderlich Act, 41 U.S.C. §§ 321-322 (1964), in that such decision contains specified errors of law and in that certain designated findings of fact are not supported by substantial evidence; and that upon the facts established in the record of the administrative proceedings, plaintiff is entitled to recover as a matter of law. Plaintiff moves this court for entry of judgment to that effect, and since the board deferred consideration of issues of damages and made no decision thereon. *1273 requests suspension of proceedings herein to permit the parties to reinvoke administrative remedies for determination of the equitable adjustment of the contract price. Defendant asserts that the board’s decision is entitled to finality, and requests that plaintiff’s petition be dismissed.

Plaintiff is a joint venture known as Tecon-Green-Winston,- consisting of Te-con Corporation of Dallas, Texas; Green Construction Company of Des Moines, Iowa; and Winston Bros. Company of Minneapolis, Minnesota. The pertinent contract, employing unit prices on some items with estimated quantities, had an estimated price of $14,672,709.

The basic dispute before the board, now on review before this court, is the question of the responsibility for the reworking of the fabrication of certain steel girders, called trunnion anchorage thrust girders, installed near the tops of central piers of the dam, as parts of the structures and mechanisms employed to operate the tainter gates to be raised and lowered to control the quantities of water passing over the spillway. The reworking of such girders was necessitated by cracking of some of the welds' originally placed to secure together various parts of each of such girders.

Plaintiff had the required 22 girders fabricated under subcontract with Creamer Industries, Inc., at the latter’s plant in Fort Worth, Texas, and the necessary reworking of all of such girders was also done by such subcontractor at the same plant.

Plaintiff’s claim is that the production of such girders was a practical impossibility under the defendant’s original specifications and drawings, that substantial modifications were required and employed to accomplish fabrication free of cracking in the welds, and that plaintiff is entitled under the changes article of the contract to an equitable adjustment of the contract price on account of the increased cost resulting from such defective specifications and drawings. Plaintiff’s claim is further that the reworking of the girders caused delays in the performance of other contract work, i.e., installation and construction of the handrail bridge and non-overflow sections, spillway bridge, tainter gates and other related items, and that under the suspension of work article of the contract, plaintiff is entitled to an equitable adjustment on account of the increased costs resulting from such delays.

The girders in dispute are now described as specified in the original contract documents, with the limited modifications as constructed on refabrication later detailed.

Each girder consisted of various steel plates, all being 2 inches thick except some 1-inch plates specifically described as such hereinafter. The girder is described in horizontal position, although actually installed inclined. It was about 12 feet long, about 2.2 feet wide, and about 3.3 feet high. It can be described as shaped like a large I beam with added structural members.

Flanges. The bottom of the girder, or bottom flange, was a horizontal plate, having the length (12 feet) and the width (2.2 feet) of the overall girder. The top flange (or top plate of the girder) had the same width as the bottom flange, and extended in horizontal plane for most of the length of the girder. However, near each end of the girder, the top flange curved downward (1-foot radius curve) and then continued vertically (for the remainder of, being most of the 3.3-foot height of the girder) to the bottom flange. Thus, the top flange can be described as a continuous flange constituting the top horizontal plate and both vertical end plates of the girder, with an appropriate downward curvature of the continuous flange at each end of the girder from the horizontal to the vertical plane.

At the bottom of each end of the girder, the end edge of the top flange was welded to the upper surface of the bottom flange.

Actually, each flange consisted of two plates, extended in succession length *1274 wise, with their adjoining ends welded together. After the two plates for the top flange had been welded together, such continuous flange was bent into the curvatures above described. Thus, each flange had a welded joint other than those at the junctures of the top and bottom flanges. This welded joint for each flange was located on the top or bottom of the girder in corresponding position with the other, both of such welds being intermediate between the ends of the girder. Each flange was somewhat wider at one end of the girder than at the other, due to the fact that each flange had one plate about 2.7 feet wide and the other plate 2.2 feet wide.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Maitland Bros. v. United States
36 Cont. Cas. Fed. 75,835 (Court of Claims, 1990)
Hart Precision Products, Inc. v. The United States
852 F.2d 1294 (Federal Circuit, 1988)
Consolidated Molded Products Corp. v. United States
600 F.2d 793 (Court of Claims, 1979)
Dynalectron Corp. v. United States
518 F.2d 594 (Court of Claims, 1975)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
J. A. Maurer, Inc. v. United States
485 F.2d 588 (Court of Claims, 1973)
Sylvania Electric Products, Inc. v. United States
458 F.2d 994 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
411 F.2d 1271, 188 Ct. Cl. 436, 1969 U.S. Ct. Cl. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tecon-corporation-green-construction-company-and-winston-brothers-cc-1969.