GSI Construction Corp.

CourtArmed Services Board of Contract Appeals
DecidedJune 25, 2025
Docket63828
StatusPublished

This text of GSI Construction Corp. (GSI Construction Corp.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GSI Construction Corp., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) GSI Construction Corp. ) ASBCA No. 63828 ) Under Contract No. FA4417-23-C-0009 )

APPEARANCE FOR THE APPELLANT: Mr. Josh Owens President

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq. Air Force Deputy Chief Trial Attorney Michael J. Farr, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MELNICK

GSI Construction Corporation (GSI) contracted to provide renovation services to the Air Force’s 1st Special Operations Contracting Wing (government). The solicitation requested an initial price valid during a base period, followed by an escalated option price valid during a later period in the event the award was delayed. GSI seeks a recovery that would provide it with the option price because although the government awarded the contract in the initial period, it did not issue the notice to proceed and allow site access until the later period. We find the government unreasonably delayed the notice to proceed and site access, entitling GSI to costs under the terms of the contract’s suspension of work clause.

GSI is pro se and elected to proceed under Board Rule 11. The government did not agree. Under hybrid proceedings implemented by the Board, GSI submitted evidentiary materials in support of its case in chief under Rule 11, while the government was allowed to call live witnesses to testify under oath in support of its case. The Board then allowed further briefing by the parties.

FINDINGS OF FACT

1. The government originally issued a solicitation in 2022 for renovation, repair, and construction of an addition to a child development center (R4, tab 1). The period of performance was to be 515 days (R4, tab 1 at 8). Because there were no funds for the contract when the solicitation was issued, no award would be made until funds became available (R4, tab 7 at 2). Nevertheless, as amended, proposals were due June 6, 2023 (R4, tab 9 at 2). The amended solicitation recited the work to be performed in two sets of line items. The base set (items one through eight) sought pricing valid through September 30, 2023. (R4, tab 7 at 3-5) The identical option set of line items (1001-08) sought pricing valid from October 1 through December 31, 2023 (R4, tab 7 at 5-7). Prices would be evaluated for the period during which funds became available (R4, tab 7 at 20). GSI’s proposal escalated its option period prices above its base prices by a total of $539,000 (app. supp. R4, tab 1 (Proposal at 4-7)).

2. Funds for the project were certified on August 15, 2023, and on that date the government notified GSI that it was the successful offeror. The notification required GSI to submit a certificate of insurance within 10 days, which GSI did. (R4, tab 15; tr. 15, 150) The awarded contract, dated August 17, accepted GSI’s pricing for line items one through eight (R4, tabs 10, 15). Relevant provisions included the requirement that GSI submit performance and payment bonds, which it did on September 6, 2023, and corrected the next day (R4, tab 10 at 2, tabs 25, 31; tr 31-33). GSI was to begin performing within 10 days of the notice to proceed (R4, tab 10 at 2, 31). GSI could not mobilize to the site and begin construction until it received that notice (tr. 116). Drawing G4 of the contract required GSI to submit a sequence of construction plan (also called a phasing plan) for approval prior to starting construction (R4, tab 10 at 627). Finally, the contract incorporated Federal Acquisition Regulation (FAR) 52.242-14, SUSPENSION OF WORK (APR 1984) (id. at 30).

3. GSI submitted an initial phasing plan on September 4, 2023, which it revised for the final time on September 13 (R4, tabs 22, 39; tr. 105, 122-23, 156). Though the revised plan was acceptable to it, the government failed to issue an express approval (tr. 45-47).

4. Critical to GSI avoiding escalated costs was that it finalize material orders to lock in vendor pricing and commence construction as far in advance of labor cost increases as possible (Owens decl. ¶ 14). 1 Before many materials could be ordered, GSI needed to access the work site to verify conditions and make measurements. However, the government did not allow GSI onto the site until it issued the notice to proceed. (Id.). Similarly, various materials had to be approved by the government through a submittal process (tr. 25). These included items to be selected by the government for color, texture, size, wording, and layout. Other items required customized engineering that had to be approved before manufacture. GSI could not lock in material prices until submittals were approved. (Owens decl. ¶ 14; tr. 142-44) GSI inquired about providing submittals to the government as early as August 31, 2023. The government initially told it not to present them. (R4, tab 20) Although the

1 Mr. Owens’ amended declaration, dated January 23, 2025, served as GSI’s opening Rule 11 submission.

2 government later offered some feedback, it would not officially act on submittals until after it issued the notice to proceed (R4, tabs 43, 45, 48; tr. 25-29).

5. On September 7, 2023, the government informed GSI that it was considering issuing the notice to proceed by October 2 (R4, tab 33 at 1). GSI indicated that was fine and would prepare for it (R4, tab 34 at 1). However, during the September 19 preconstruction meeting, the government informed GSI that it would not issue the notice on October 2 because the necessary preparatory tasks had not been completed. GSI could expect the notice in mid-October. (R4, tab 41 at 1; tr. 55-56, 128-30) The tasks the government had to perform included the removal of kitchen equipment, food, and utensils. Also, communications and surveillance equipment, televisions, intercoms, computer lines, and office staff had to be relocated. Additionally, various Air Force officials and parents of the children attending the center had to be notified. (Tr. 54-58)

6. On September 26, 2023, GSI inquired about the notice to proceed (R4, tab 52 at 3). On September 28, it complained to the government that upon award of the contract it purchased bonds and hired personnel. It said it would lose money if it did not start work the following week. (Id. at 1) On October 16, GSI again asked about the notice to proceed, observing the government had said to expect it by the middle of the month after missing the original October 2 date. It stressed the situation had become critical for it given its commitment of time and resources. (R4, tab 57) GSI urgently sought to start construction (tr. 137). The government internally acknowledged the request the next day, observing that delaying the notice “too long” could lead to a claim from GSI. It then considered October 23 as the date for the notice to proceed, with the architect informing the center’s management that she believed it would be another month after the notice before construction started. (R4, tab 58 at 1, tab 59 at 2)

7. On October 20, 2023, the contracting officer issued a notice to proceed to GSI, effective October 23 (R4, tab 60 at 6). However, the facility remained unavailable (Owens decl. ¶ 13). The center had still not finished the preparation work necessary before GSI could begin work (tr. 118-19, 156-57). GSI had to suggest that the government grant a 42-day extension to contract performance, delaying its mobilization to the site until December 4, because the government did not have the facility ready (tr. 120-21, 132-33, 138, 174-75). GSI was finally given access to the project site on December 4. We find the government took 109 days from the date of award to make the facility available to GSI. (Tr. 178)

8. Considering GSI provided compliant bonds by September 7, 2023, a reasonable date for the government to issue the notice to proceed was the one to which

3 GSI consented, October 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Parish v. United States
98 F. Supp. 347 (Court of Claims, 1951)
John A. Johnson & Sons, Inc. v. United States
180 Ct. Cl. 969 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
GSI Construction Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gsi-construction-corp-asbca-2025.