United States v. American Surety Co.

322 U.S. 96, 64 S. Ct. 866, 88 L. Ed. 1158, 1944 U.S. LEXIS 1212
CourtSupreme Court of the United States
DecidedApril 24, 1944
Docket381
StatusPublished
Cited by24 cases

This text of 322 U.S. 96 (United States v. American Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. American Surety Co., 322 U.S. 96, 64 S. Ct. 866, 88 L. Ed. 1158, 1944 U.S. LEXIS 1212 (1944).

Opinion

Mr. Justice Murphy

delivered the opinion of the Court.

On June 24, 1931, one John V. Grogan entered into a contract 1 with the United States to construct certain public buildings at the United States Inspection Station at *97 Babb-Piegan, Montana. Respondent became the surety on Grogan’s performance bond to the United States. The completion date of the contract was March 4, 1932, but this was extended to June 20, 1933. Grogan failed to complete the work by the extended date. The Government, however, allowed him to continue with the construction. On July 20, 1934, thirteen months later, the work was still uncompleted. Pursuant to its authority under Article 9 of the construction contract, the Government thereupon terminated Grogan’s right to proceed with the work because of his continuing default. The Government finished the work through another contractor, expending $2,044.04 more than it would have been required to expend had Grogan completed the work.

The United States brought this suit in the District Court to recover the excess cost and also to recover liquidated damages of $9,875 for the delay occasioned by Grogan’s default. The liquidated damages were computed on the basis of an agreed $25 per day for the 395 days between June 20, 1933, the extended date for completion, and July 20,1934, when the contract right to proceed was terminated. Grogan was not served and never appeared. The District Court denied respondent’s motion to strike from the complaint the paragraph alleging a right to liquidated damages. United States v. Grogan, 39 F. Supp. 819. The court subsequently rendered judgment, after trial without a jury, for the United States for $2,044.04 as excess cost of completion and $9,875 as liquidated damages for delay. See United States v. Grogan, 44 F. Supp. 871. On appeal, the court below affirmed the judgment as to the excess cost but reversed as to the liquidated damages. American Surety Co. v. United States, 136 F. 2d 437. The public importance of the issue of the Government’s right to liquidated damages under these circumstances led us to grant certiorari. 320 U. S. 729.

*98 Section 21 of the Act of June 6, 1902, 2 provides that all contracts for the construction of any public building under the control of the Treasury Department shall contain a stipulation calling for liquidated damages for delay in completion of the work and that such stipulation shall be conclusive and binding upon all parties. Proof of actual damages is rendered unnecessary. This statute, however, does not purport to require liquidated damages to be paid in amounts or under circumstances beyond those stipulated by the parties. Robinson v. United States, 261 U. S. 486, 488. It was pursuant to this statutory command that Article 9 of the construction contract in issue was inserted. Thus this article is determinative of the Government’s right to liquidated damages under the circumstances of this case.

Article 9, set out in the margin, 3 provides in effect that: (1) if the contractor refuses or fails to prosecute the work *99 with proper diligence or to complete his work within the specified time, the Government may at any time terminate his right to proceed and prosecute the same to completion by contract or otherwise, in which case the Government may recover from the contractor or his surety any excess cost occasioned thereby; (2) “if the Government does not terminate the right of the contractor to proceed, the contractor shall continue the work, in which event the actual damages for the delay will be impossible to determine and in lieu thereof the contractor shall pay to the Government as fixed, agreed, and liquidated damages for each calendar day of delay until the work is completed or accepted the amount as set forth in the specifications.” In this instance, paragraph 5 of the accompanying specifications provides that “the contractor shall pay to the government the amount of Twenty-Five Dollars ($25.00) as fixed, agreed, and liquidated damages for each calendar day’s delay in the completion of the contract.” This paragraph merely provides the agreed rate of the per diem liquidated damages to be paid in the situations contemplated by Article 9. It is obviously not intended to spell out the situations where liquidated damages are to be paid and cannot, con *100 trary to the Government’s contention, control the language of Article 9 4

The impact of Article 9 on the facts of this case is clear. The contractor having failed to complete his work within the specified time, the Government exercised its option under the first part of Article 9 to terminate his right to proceed. This power to terminate could be exercised before or on the stipulated completion date or, as in this case, at any date thereafter. The Government then made other arrangements to complete the construction work and was entitled to, and did recover, the excess cost occasioned thereby. It thus waived its right to liquidated damages under the second part of Article 9. That right is conditioned upon the Government not terminating the contractor’s right to proceed. Where there is such a termination, even though it be subsequent to the stipulated completion date, the right to liquidated damages disappears. Such has been the uniform and correct result heretofore reached in the application of this type of contract provision. See United States v. Cunningham, 125 F.2d 28; United States v. Maryland Casualty Co., 25 F. Supp. 778; Maryland Casualty Co. v. United States, 93 Ct. Cls. 247. See also Fidelity & Casualty Co. v. United States, 81 Ct. Cls. 495; Commercial Casualty Insurance Co. v. United States, 83 Ct. Cls. 367; American Employer’s Insurance Co. v. United States, 91 Ct. Cls. 231.

The Government has urged us to read the second part of Article 9 as though the right to liquidated damages were *101 based, not upon a condition precedent that the Government not terminate, but upon a continuing condition, under which liquidated damages would accrue “so long as the Government does not terminate” the contractor’s right to proceed. This is said to be the only way to give full effect to the prime purpose of § 21 of the 1902 Act to eliminate the uncertainties and difficulties of establishing actual damages to the Government by delay in obtaining the use of a public building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Excel Underground, Inc. v. Brant Lake Sanitary District
941 N.W.2d 791 (South Dakota Supreme Court, 2020)
International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
West v. United States Postal Service
907 F. Supp. 154 (E.D. Virginia, 1995)
Pacific Employers Insurance v. City of Berkeley
158 Cal. App. 3d 145 (California Court of Appeal, 1984)
Subsurfco, Inc. v. B-Y Water District
337 N.W.2d 448 (South Dakota Supreme Court, 1983)
Arctic Contractors, Inc. v. State
564 P.2d 30 (Alaska Supreme Court, 1977)
Olazábal v. United States Fidelity & Guaranty Co.
103 P.R. Dec. 448 (Supreme Court of Puerto Rico, 1975)
United States v. Marietta Manufacturing Co.
53 F.R.D. 390 (S.D. West Virginia, 1971)
Transamerica Insurance v. McKeesport Housing Authority
309 F. Supp. 1321 (W.D. Pennsylvania, 1970)
Hartford Accident & Indemnity Co. v. United States
127 F. Supp. 565 (Court of Claims, 1955)
H. Herfurth, Jr., Inc. v. Acker
177 F.2d 38 (D.C. Circuit, 1949)
Manart Textile Co. v. United States
77 F. Supp. 924 (Court of Claims, 1948)
Dineen v. United States
71 F. Supp. 742 (Court of Claims, 1947)
Schmoll v. United States
63 F. Supp. 753 (Court of Claims, 1946)
Fireman's Fund Indemnity Co. v. United States
63 F. Supp. 750 (Court of Claims, 1945)
United States v. Standard Rice Co.
323 U.S. 106 (Supreme Court, 1944)
National Surety Corp. v. United States
102 Ct. Cl. 671 (Court of Claims, 1944)
Modern Industrial Bank v. United States
101 Ct. Cl. 808 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
322 U.S. 96, 64 S. Ct. 866, 88 L. Ed. 1158, 1944 U.S. LEXIS 1212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-american-surety-co-scotus-1944.