American Insurance v. Heritage Construction Corp.

268 F. Supp. 336
CourtDistrict Court, N.D. California
DecidedDecember 22, 1965
DocketNo. 42328
StatusPublished
Cited by2 cases

This text of 268 F. Supp. 336 (American Insurance v. Heritage Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Insurance v. Heritage Construction Corp., 268 F. Supp. 336 (N.D. Cal. 1965).

Opinion

MEMORANDUM OF DECISION

SWEIGERT, District Judge.

Plaintiff, the American Insurance Company, a New Jersey corporation engaged in the business of issuing construction faithful performance and mechanics’ lien surety bonds in California, commenced this action on May 1, 1964, against defendants, Heritage Construction Corporation and others, residents of California engaged in the improvement of certain real property in San Mateo County, for a decree declaring that plaintiff has no liability to defendants under a certain surety bond hereafter mentioned, and that defendants are liable to plaintiff for any sums plaintiff may be required to pay thereunder to labor, material or subcontractor claimants.

Jurisdiction is invoked under the diversity jurisdiction of this Court.

The case is before the Court following a trial by the Court of the issues raised by the pleadings and by a pre-trial order filed herein August 6, 1965.

The following facts are either undenied or found by the Court from the evidence in the case:

On August 16, 1962, defendants entered into a contract (Plaintiff’s Ex. 2) with Ervin P. Yarwig whereunder Var-wig undertook to construct certain offsite improvements on a real estate tract in San Mateo County known as Mills Estate No. 24.

The Contractor, Varwig, had furnished a contractor’s surety bond dated August 15, 1962 (Plaintiff’s Ex. 1) issued by plaintiff herein, for Varwig’s faith[338]*338ful performance of the construction contract and for his payment of all labor, material and subcontractor’s claims on the job.

Varwig commenced work on August 16, 1962 and physically completed his work in December, 1963. On March 25, 1964, defendants received information to the effect that one of Varwig’s subcontractors intended to file a mechanics’ lien and subsequently received similar information from other subcontractors and materials men.

By letter of March 31, 1964, defendants gave notice to plaintiff surety company that the contractor had defaulted in his payment of labor, material and subcontractor claims. A similar letter notice, dated April 3, 1964, was delivered by hand to plaintiff on that date.

By May 1, 1964, it was discovered that a total of $115,000 of labor, material and subcontractor claims for work on the job remained unpaid by Varwig.

Plaintiff surety company refused to acknowledge liability for these claims.1

Instead of paying them, plaintiff commenced this action alleging in substance and effect that defendants had failed to comply with the terms and conditions of the surety bond in that: (1) Defendants and Varwig did not abide by the terms of the construction contract, as required by the surety bond, but instead altered the terms of the construction contract in that premature payments were made by defendants to Varwig; (2) Defendants failed to notify plaintiff of the default of Varwig within the time required by the surety bond.

Disposing first of plaintiff’s contention that defendants failed to give notice of Varwig’s default within the time provided by the surety bond, the evidence so clearly establishes that defendants did give timely notice that plaintiff has not bothered to pursue in post trial briefs its contention to the contrary.

The Court, therefore, finds from the evidence that defendants did on March 31, 1964, and on April 3, 1964, give written notice of the principal’s (i. e., Var-wig’s) default and that said written notice was given as promptly as possible and also within ten days after such default became known to defendants or to their representatives authorized to supervise performance of the construction contract — -all within the meaning of and in compliance with Condition First of the surety bond.

Plaintiff’s next contention is that defendants did not abide by the terms of the construction contract, as required by the surety bond, in that certain progress payments were prematurely made.

Condition Second of the surety bond issued by plaintiff (Plaintiff’s Ex. 1) provides as follows:

“Second: That the Owner shall faithfully perform all of the terms, covenants and conditions of such contract on the part of the Owner to be performed; and shall also retain the last payment and all reserves and deferred payments until the complete performance of said contract, and until the expiration of the time within which notice of claims or claims of liens by persons performing work or furnishing materials, appliances, teams or power under said contract may be filed, and until all such claims shall have been paid, unless the Surety shall consent, in writing, to the payment of said last payment, reserves or deferred payments.”

The construction contract (Plaintiff’s Ex. 2) provides under General Conditions, p. 10, Section VIII, Par. 2, as follows:

“PARTIAL PAYMENTS: It is hereby stipulated and agreed that the First Party shall once each month cause an estimate in writing to be made by the Engineer of the total amount of work [339]*339done at the time of such estimate, and the value thereof. The First Party shall retain ten per cent (10%) of such estimated value as part security for the fulfillment of this Contract by Contractor, and shall monthly pay to the Contractor the remaining ninety per cent (90%), after deducting therefrom all previous payments and other sums to be retained under the terms of this Contract. No estimate or payment shall be made when, in the judgment of the Engineer, the work is not proceeding in accordance with the provisions of this Contract or when the total value of the work done since the last estimate amounts to less than one thousand dollars ($1,000).”

Plaintiff contends that, among the progress payments made to Varwig (See Plaintiff’s Ex. 4), a payment of $64,750.-95 to the Contractor on October 31, 1962, was a premature payment and a departure from the construction contract in that it was not a “once each month” payment, as required by the contract, because the work started on August 16, 1962; Varwig received a first payment of $21,798 on September 14, 1962, a second payment of $56,282.40 on October 17, 1962 and this third payment of $64,-750.95 less than a month (i. e., 14 days) thereafter.

The evidence shows, however, that none of these three payments exceeded 90% of Varwig’s progress billings and that, in fact, after the October 31, 1962 payment, the accumulated retentions were still far in excess of the required 10% retention.

The absurdity and extreme technicality of this contention are manifest when one observes that the October 31st payment might even have been properly made concurrently with the previous October 17th payment without reducing the progress retention below the required 10%.

The Court holds and finds that neither this October 31st payment, nor any of the other progress payments made by defendants, substantially altered or breached the construction contract. Plaintiff next contends that defendants failed to retain 10% of all progress payment claims presented by Varwig, as required by the same Section VIII, Par. 2 of the construction contract, in that defendants retained 10% of only the original unit bid amounts and did not retain <?n the basis of actual “as built” amounts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
268 F. Supp. 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-insurance-v-heritage-construction-corp-cand-1965.