Alexander v. Good Marble & Tile Co.

4 S.W.2d 636, 1928 Tex. App. LEXIS 278
CourtCourt of Appeals of Texas
DecidedMarch 16, 1928
DocketNo. 408.
StatusPublished
Cited by19 cases

This text of 4 S.W.2d 636 (Alexander v. Good Marble & Tile Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alexander v. Good Marble & Tile Co., 4 S.W.2d 636, 1928 Tex. App. LEXIS 278 (Tex. Ct. App. 1928).

Opinion

HICKMAN, C. J.

This litigation is based upon a contract for the construction of the seven-story Alexander bank and office building on North First and Bine streets in the city of Abilene. For convenience the parties will be designated here as they were in the contract, the appellant J. M. Alexander being the owner, the appellees Walsh & Bur-ney being the contractor, and the appellee *637 Good Marble & Tile Company being the sub-, contractor. Suit was instituted by the subcontractor against the contractor for approximately $7,500, alleged to be due for the installation of the marble and terrazzo work in the building, and to establish and foreclose, as against the owner, a mechanic’s and materialmen’s lien on said building and the lots on which it is situated. The contractor filed a cross-action over against the owner for approximately $7,900, as the alleged balance unpaid on the original contract between him and the owner for the construction of the building. The owner answered denying any indebtedness to the contractor, and alleging that' the building had not been completed, and that it would cost more to complete and repair same in accordance with the contract than the balance unpaid on the contract price. He also denied that he had accepted the building, and particularly pleaded that a large part of the marble which was installed by the subcontractor had been rejected by the architect. He prayed for judgment against the contractor for the amount necessary to carry out the contract, after crediting the same with the balance of the unpaid contract price. He also prayed for judgment for approximately $2,400, which he alleged to be due him under the terms of the contract for delay in completing the banking room and a certain storeroom on the first floor. The case was submitted to the jury upon special issues, upon the answers to which judgment was rendered in favor of the subcontractor against the contractor for approximately $8,000, with a foreclosure against the building in the amount of the judgment in favor of the contractor against the owner, which was approximately $7,800. Judgment was also rendered in favor of the subcontractor against the owner for the same amount as the judgment against the owner in favor of the contractor, but it was decreed that no execution should issue in favor of the subcontractor against the owner personally.

Able briefs have been filed presenting many assignments and propositions; but, since we have concluded that it is necessary to remand the case for another trial, we believe our views on the controlling questions of law may be stated without the necessity of discussing separately the various assignments and propositions.

The original contract between the owner and the contractor required>the latter to furnish all labor and material for the erection and completion of the building according to the plans, specifications, and drawings made by David S. Castle, architect, in a good, substantial, and workmanlike manner, to the satisfaction and under the direction of said architect and his superintendents. In consideration that the contractor should completely and faithfully execute the work, furnish the material and labor therefor, and fully carry out the contract according to its true spirit and by and at the times mentioned to the full and complete satisfaction of David S. Castle and his superintendents, the owner obligated himself to pay the contractor $219,787 on certificates of the architect or his superintendent from time to time as the work progressed, to wit, 85 per cent, of the estimated value of the same. The contract contained the further provision, in substance, that in relation to the contract, the work to be or that has been performed under it, or in relation to the plans; drawings, and specifications, which were made a part thereof, the decision of David g. Castle, the architect, should be final and binding on all parties thereto.

Prom the foregoing description of the terms of the contract it is apparent that the parties thereto vested the architect with authority and power to make decisions on all issues which might arise in the course of the construction of the building with reference to labor, material payments, etc.

Recovery was had upon this contract. The law is well settled that, when a contractor sues the owner for money due upon a contract of this character, it is incumbent upon him, in order to recover against the owner, to plead and prove that the architect has issued to him a certificate showing his right to the payment, or that such final certificate has been withheld by the architect fraudulently, or that his withholding thereof was so arbitrary as to amount to bad faith, or that the owner has waived his right to insist upon same. Childress v. gmith et a., 90 Tex. 610, 38 g. W. 518, 40 S. W. 389; Kansas City, E. P. & M. Ry. Co. v. Perkins, 88 Tex. 66, 29 S. W. 1048; Jones et al. v. Gilchrist, 88 Tex. 88, 30 S. W. 442; Boettler v. Tendick, 73 Tex. 488, 11 S. W. 497, 5 L. R. A. 270; Kilgore v. Baptist Society,,89 Tex. 465, 35 S. W. 145; Kettler Brass Mfg. Co. v. O’Neil, 57 Tex. Civ. App. 568, 122 S. W. 900; Llano Granite & Marble Co. v. Hollinger et al. (Tex. Civ. App.) 148 S. W. 337; Harrell v. City of Lufkin (Tex. Com. App.) 280 S. W. 174.

No issue was submitted to the jury calling for a determination of whether the withholding of the certificate by the architect was fraudulent or in bad faith, or whether the owner waived the same. A finding against appellant on one of these issues is essential to support a judgment against him on the contract, and in the absence of such finding the judgment must be reversed.

Appellees insist that under article 2190, R. S. 1925, it becomes our duty to presume, in support of the judgment of the trial court, that the issue of fraud was found by the trial judge in such manner as to support the judgment. This same question has been presented to this court a great many .times, *638 and we have uniformly held that a plaintiff owes no duty to request the submission of issues essential to the defendant’s defense, and a defendant likewise owes no duty to request the submission of issues essential to plaintiff’s recovery.

Under such a situation it is the well-settled rule that, where a party to a suit fails to request the submission of an issue necessary to make out his cause of action or defense, as the case may be, and such issue is not by the court submitted to the jury, it is waived. Authorities almost without number could be cited in support of this holding, but we shall refer to but a few of the leading ones. Conflicts in the construction of article 2190 are to be found in the opinions of some Courts of Civil Appeals, rendered prior to the time that the Supreme Court construed this article. In the case of Kirby Lumber Co. v. Conn, 114 Tex. 104, 263 S. W. 902, our Supreme Court, through Justice Greenwood, wrote on this .question, construing the article above. The Supreme Court again wrote on the same question in the recent case of Ormsby v. Ratcliffe (Tex. Sup.) 1 S. W. (2d) 1084. That case was pending before that court on applidation for writ of error from this court, and Justice Pierson took occasion again to write upon the same subject, on account of the great confusion which seemed to exist in the minds of able counsel regarding the same. That opinion clearly construes the statute. Again, in the case of Bulin et al. v. Smith, 1 S. W. (2d) 591, the Commission of Appeals, speaking through Judge Speer, reaffirms the rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baldwin v. Smith
586 S.W.2d 624 (Court of Appeals of Texas, 1979)
Higginbotham v. O'Keeffe
340 S.W.2d 350 (Court of Appeals of Texas, 1960)
Smith v. Phillips Pipe Line Co.
128 F. Supp. 61 (N.D. Oklahoma, 1955)
Davis v. Haslam Lumber Co.
213 S.W.2d 771 (Court of Appeals of Texas, 1948)
Harris v. Thornton's Department Store
94 S.W.2d 849 (Court of Appeals of Texas, 1936)
Miller v. Fenner, Beane & Ungerleider
89 S.W.2d 506 (Court of Appeals of Texas, 1935)
Panhandle & Santa Fe Ry. Co. v. Burt
71 S.W.2d 390 (Court of Appeals of Texas, 1934)
American Surety Co. of New York v. Shaw
69 S.W.2d 47 (Texas Commission of Appeals, 1934)
Turner v. Big Lake Oil Co.
62 S.W.2d 491 (Court of Appeals of Texas, 1933)
Continental Oil Co. v. Berry
52 S.W.2d 953 (Court of Appeals of Texas, 1932)
Fort Worth & Denver City Ry. Co. v. Greathouse
41 S.W.2d 418 (Court of Appeals of Texas, 1931)
Bedford-Garth Age Stone Co. v. Ramey
34 S.W.2d 387 (Court of Appeals of Texas, 1930)
Roberts v. J. B. Colt Co.
31 S.W.2d 196 (Court of Appeals of Texas, 1930)
Livezey v. Putnam Supply Co.
30 S.W.2d 902 (Court of Appeals of Texas, 1930)
Wright v. King
17 S.W.2d 98 (Court of Appeals of Texas, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
4 S.W.2d 636, 1928 Tex. App. LEXIS 278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alexander-v-good-marble-tile-co-texapp-1928.