Bedford-Garth Age Stone Co. v. Ramey

34 S.W.2d 387
CourtCourt of Appeals of Texas
DecidedOctober 22, 1930
DocketNo. 3426.
StatusPublished
Cited by3 cases

This text of 34 S.W.2d 387 (Bedford-Garth Age Stone Co. v. Ramey) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bedford-Garth Age Stone Co. v. Ramey, 34 S.W.2d 387 (Tex. Ct. App. 1930).

Opinion

JACKSON, J.

The plaintiff, R. A. Ramey, instituted this suit in the district court of. Lubbock county, Tex., against the defendants D. E. Braucht, R. M. Amrine, L. W. Zir jacks, and the Bed-ford-Carthage Stone Campany, to recover damages for an alleged breach of a contract.

The plaintiff alleged that about July 3,1924, he made and entered into a contract with the Texas Technological College at Lubbock, Tex., to erect, according to plans and specifications, a building known as the Administration building, for a consideration of $371,383. That by the terms of said contract he was bound to complete and deliver said building by July 1, 1025, and, for each day’s delay after said date, he was bound and obligated by said contract to pay to the Texas Technological College the sum of $500 as agreed liquidated damages.

That at the time of the execution of said contract, the plaintiff entered into a bond in the penal sum of $124,000, with the Maryland Casualty Company as surety, binding the plaintiff to a faithful performance of the work according to the contract, plans, and specifications.

That the contract, plans, and specifications required that the outside walls of said building were to be constructed of Leuders stone.

That on July 11, 1924, plaintiff, relying on the representations of the defendants that they were equipped to quarry, cut, carve, fur-, nish, and deliver Leuders stone without interruption or delay, as rapidly as it would be needed in the erection of said building, entered into a contract with the defendants hy which they bound and obligated themselves to furnish the quantity of stone as required and needed in the construction and erection of said building, for the sum of $73,000.

Plaintiff sufficiently alleges notice to the defendants of the terms and provisions of his contract with the Texas Technological College, charges them with knowledge that it would be necessary for him to keep in his employ a large number of stonecutters, carpenters, painters, tile setters and marble setters, and superintendents, in order to erect said building, and that such skilled labor was difficult to obtain and was not available at Lubbock, Tex. That the defendants knew that any delay would cause plaintiff serious damages, that such damages would be difficult to ascertain, and on account thereof it was provided in said contract that:

“Shipments are to be made as follows, to-wit: Eirst car thirty days after shop drawings submitted to the company are approved and these, together with all necessary details or information, are received by the company. Balance as follows: two ears per week thereafter until full order is completed. * * *
“In the event that the company does not make shipments as above agreed, through no fault of the purchaser, the company agrees to pay to the purchaser as liquidated damages for each and every day that the stone is not shipped as agreed, the sum of $100.00.’’

In compliance with the provisions of said contract, plaintiff furnished the defendants with, and they received and approved, shop drawings for cutting the stone, together with the necessary details and information, and on August 9, 1924, shipped to plaintiff the first carload of stone. That they were bound and obligated under the contract to ship two cars each week thereafter until their contract had been fulfilled. That the defendants refused to comply with their said contract iu that they failed to furnish the plaintiff stone in the quantities and at the times as stipulated. That during many weekly periods after August 10th, they failed to make any shipments, some weeks shipped but one carload, and wholly failed and refused to ship sufficient stone to enable plaintiff to proceed with the walls with such speed as was required for him to complete said building within the time limit stipulated in his contract with the Texas Technological College. That near the completion of the building the defendants, for a period of three months, refused to ship any stone whatever and made the last shipment on July 30, 1925, some 30 days after the time limit of plaintiff’s contract for completing and delivering the building had expired.

That under the contract with plaintiff, the defendants were obligated to complete the shipments of stone on or before January 10, 1925, but, in fact, did not complete such shipments until July 30,1925, a delay of 16S days. That because of the provision in the contract for liquidated damages, and the failure of the defendants to comply therewith, they are liable and bound to plaintiff in the sum of $100 per day as liquidated damages for 168 days’ delay in the shipments of stone, which is the sum of $16,800. That plaintiff has paid the defendants on the contract price of $73,000 all save a balance óf $7,017.34, for which last amount the defendants are entitled to a credit on whatever sum the plaintiff may recover as damages.

The plaintiff, in the event he was not allowed to recover on his claim for liquidated damages, alleges in detail the damages he claims to have sustained; but, as he recovered on the claim for liquidated damages, no further statement of his pleading is necessary.

*389 The defendants answered by general demurrer, special exceptions, general denial, and specially alleged that, as a moving consideration for the written contract between the plaintiff and the defendants, the plaintiff was allowed to take advantage of 4 per cent, discount on 90 per cent, of each invoice, prq-vided the same was paid within 15 days from the date thereof. That plaintiff took advantage of said discount, but did not make the payments within the time specified, which was a material consideration, as the plaintiff was advised that the payments must be made as contracted if the invoices were discounted, in order that the defendants -would have the money to finance the supply of stone under the contract. That plaintiff took the discount, but failed to pay the invoices as provided, and such default on his part was a direct and proximate cause of the delay on the part of the defendants. That such delays in payment aggregated about 150 days.

The defendants by way of cross-action sued pláintiff and his surety, the Maryland Casualty Company, for the sum of $7,690.09, the balance due on the purchase price of said stone. They attached to and made a part of their answer an itemized statement of the stone shipped, and also attached to their answer a copy of the contract made and entered into between plaintiff and defendants, the following provisions of which they set out:

“That said purchaser shall furnish or cause to be furnished such details or explanations as may be necessary to delineate the plans and specifications and enable said company to perform said work as herein provided.
“The company shall not in any event be held responsible for any loss, damage, detention, or delay caused by the owner, the architect, the purchaser or any other contractor or subcontractor upon the building; the delays in transportation, fire, strikes, lookouts, civil or military authority, or by insurrection riot; or by any other cause beyond its control or in any event for consequential damages.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
Pathman Construction Co. v. Hi-Way Electric Co.
382 N.E.2d 453 (Appellate Court of Illinois, 1978)
Gillioz v. State Highway Commission
153 S.W.2d 18 (Supreme Court of Missouri, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
34 S.W.2d 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bedford-garth-age-stone-co-v-ramey-texapp-1930.