Smith v. Phillips Pipe Line Co.

128 F. Supp. 61, 1955 U.S. Dist. LEXIS 3632
CourtDistrict Court, N.D. Oklahoma
DecidedJanuary 8, 1955
DocketNo. 3063
StatusPublished
Cited by6 cases

This text of 128 F. Supp. 61 (Smith v. Phillips Pipe Line Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Phillips Pipe Line Co., 128 F. Supp. 61, 1955 U.S. Dist. LEXIS 3632 (N.D. Okla. 1955).

Opinion

WALLACE, District Judge.

The plaintiffs, J. Herb Smith and M. M. Donaho, citizens of Texas, doing business as Smith-Donaho Contracting Company, a copartnership, bring this action against the defendant, Phillips Pipe Line Company, a Delaware corporation, to recover sums allegedly due for pipeline woi’k done by plaintiffs for defendant Phillips in Kansas and Missouri. Plaintiffs seek recovery for pipe laid by them while working as the assignee of a written contract originally negotiated between defendant Phillips and the Smith Contracting Corporation, a Texas corporation (additional defendant on counterclaim and cross-claim). Plaintiffs urge they are entitled to receive more money than the amount called for in the written contract1 for the reason that inclement weather, not within the contemplation of the contracting parties was encountered during the pipeline work;2 and, place their request for recovery upon two alternate theories: (1) The original written agreement was supplanted by an oral contract whereby plaintiffs gave up their right to await the carrying out of the written agreement until working conditions returned to normal and defendant Phillips in turn agreed to pay the plaintiffs the actual cost of construction of said line under the conditions then existing; or, (2) The work performed by plaintiffs pursuant to the written contract under the existing weather conditions constituted “extra work” above and beyond that work called for under the terms of the written agreement. Defendant Phillips, in answering, denies it owes plaintiffs any sum except that specifically called for under the express terms of the written contract and in addition counterclaims against plaintiffs Smith-Donaho and cross-claims against Smith Contracting Corporation and Smith Corporation’s surety, Hartford Accident and Indemnity Company, a Connecticut corporation, alleging that the contractors’ obligations under the written agreement were not fully discharged.3 Hartford cross-claims against Smith Corporation pursuant to its right of indemnity and subrogation and against plaintiffs Smith-Donaho and their surety, Houston Fire and Casualty Insurance Company, a Texas corporation, for any amount recovered by Phillips in this action against Hartford; and, Houston cross-claims against SmithDonaho, asking for indemnity as to any such judgment.

After considering all the introduced evidence and the briefs of counsel pertaining to plaintiffs’ first cause of action, the Court has concluded that plaintiffs have failed to establish a right to recover from defendant Phillips. Plaintiffs’ cause fails for several distinct reasons:

(1) A written contract cannot be modified by an unexecuted oral agreement.

The gravamen of plaintiffs’ complaint against defendant Phillips is that various employees and officials of the de[63]*63fendant company by oral promises wherein assurances were given that plaintiffs would lose no money induced the plaintiffs to continue work called for in the original written agreement between the parties when under such contract, due to unforeseen inclement weather conditions, plaintiffs were not obligated to so continue; and, that such promises amounted to an oral modification of the provision of the written agreement dealing with the compensation to be paid the plaintiffs.

Clearly, the Oklahoma law prohibits the plaintiffs’ assertion. Although it is unfortunate that plaintiffs in proceeding on the project in question incurred expense well beyond the contract price agreed to by defendant Phillips,4 the Oklahoma legislature has pointedly forbade the altering of legal rights solemnly . established by written agreement by mere parol understandings, where such oral understandings, have not been entirely executed by both parties.5 The alleged parol agreement in question has at most been executed by only one party.6

(2) The alleged oral agreement, even if not barred by statute, is unenforceable due to a lack of consideration running between the parties.

The consideration which plaintiffs urge supports the alleged parol understanding is the detriment suffered by plaintiffs in continuing to lay pipe in conformity with the written specifications at a time when the weather conditions were extremely adverse. Plaintiffs assert that when they advised defendant’s employees that no further work would be done on the pipeline in question until the ground once again became reasonably adapted for such work the defendant’s employees assured the plaintiffs that if plaintiffs would continue with the pipeline work as outlined in the written agreement and proceed with the laying of pipe as rapidly as possible, the defendant company would see to it that the [64]*64plaintiffs would not lose any money in carrying out such contract.

It is fundamental that the discharge of a promise previously made and for which the promisor is legally obligated cannot stand as new and separate consideration for a subsequent agreement.7 This principle is directly applicable to the instant case. All of the work done by plaintiffs was work specifically called for in the written contract. In addition, at the time of the execution of the original written contract all parties clearly understood that the work was to be done between December 17, 1951, and February 23, 1952.8 Obviously, the weather to be encountered in Kansas and Missouri at such time of the year was one of the items to be considered by the bidder in determining the total cost figure bid and the premature thaw in question cannot be used to vitiate the contractual duty of the plaintiffs to finish the job in question by February 23, 1952.9 Even if defendant’s employees did induce plaintiffs to continue work by various promises of reimbursement, plaintiffs in proceeding merely did that which they were already legally obligated to do under the prior valid written agreement and hence suffered no legal detriment. This rationale also dispenses with the issue of fraud urged by plaintiffs in their brief. Regardless of the inducements held out by defendant’s employees, plaintiffs were at most prevailed upon to do what they already contractually owed. There can be no element of fraud in per[65]*65suading a promisor to discharge an obligation in conformity with the terms of an existing agreement.

Secondly, the plaintiffs failed to establish that the employees of defendant Phillips did in fact promise to protect plaintiffs from any financial loss on the job in question. The evidence in its entirety demonstrates that at most the officers and employees of defendant Phillips held out to plaintiffs the hope that the plaintiffs might receive aid from Phillips because of the unfortunate circumstances surrounding the job in question, but such representations by said employees were more nearly in the nature of a “gratuity”, than that of a definite promise to specifically remunerate plaintiffs.10

The Court also fails to find merit in plaintiffs’ alternative contention under their second cause of action that the work in question, being performed in unseasonably bad weather, constituted “extra work” under the terms of the written agreement. As defined in the contract, extra work consisted of work not called for expressly in the written agreement and not included in the contractor’s bid.11

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
128 F. Supp. 61, 1955 U.S. Dist. LEXIS 3632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-phillips-pipe-line-co-oknd-1955.