United States v. Hyde Construction Co.

236 F. Supp. 770, 1964 U.S. Dist. LEXIS 8005
CourtDistrict Court, N.D. Oklahoma
DecidedDecember 31, 1964
DocketCiv. No. 5493
StatusPublished

This text of 236 F. Supp. 770 (United States v. Hyde Construction Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hyde Construction Co., 236 F. Supp. 770, 1964 U.S. Dist. LEXIS 8005 (N.D. Okla. 1964).

Opinion

DAUGHERTY, District Judge.

This memorandum opinion deals with the counterclaim of the defendant, Hyde Construction Company, Inc., against the plaintiff, upon which the issues have been joined, evidence received by the Court, arguments heard, briefs submitted and suggested findings of fact and conclusions of law received by the Court.

The plaintiff’s first cause of action has been previously dismissed. Judgment has heretofore been rendered by the Court in the amount of $14,533.20 on the plaintiff’s second cause of action against the defendant, Hyde Construction Company, in accordance with the answer of said defendant, in which liability was [771]*771admitted, and the pretrial stipulation entered herein. Execution of this judgment has been stayed pending disposition of the counterclaim of the defendant, Hyde. A third party complaint has been filed herein which will await disposition pending the action of the Court covered by this memorandum.

In brief, the said counterclaim is based on the proposition that the defendant, Hyde Construction Company, Inc., has overpaid the plaintiff in connection with the furnishing of sand by the plaintiff to said defendant. Said defendant takes the position that its liability to the plaintiff for said sand is governed by a Purchase Order dated March 4, 1960 (signed by Traxler Materials, Inc., to whose rights plaintiff herein has succeeded), and calling for the delivery of sand in accordance with government specifications at the rate of 75$ per ton. Said defendant states that it received a certain amount of sand which computed at the rate of 75$ per ton obligated it to pay plaintiff the sum of $190,977.50, whereas in fact the said defendant has paid to the plaintiff the sum of $320,281.36. The difference, less the amount of the aforementioned judgment on the second cause of action, is the amount sought to be recovered by the said defendant on its counterclaim.

By way of - defense to the counterclaim, the plaintiff says that said Purchase Order was never abided by or conformed to by the parties from the start and on March 8, 1961, the parties with legal consideration entered into a new agreement fixing the price of sand to be delivered by the plaintiff to the defendant and under said agreement the plaintiff was to be paid for the sand delivered under a joint venture arrangement basically at cost plus 10%. In effect, the plaintiff claims that said March 8, 1961, agreement legally superseded and replaced the earlier Purchase Order of March 4, 1960, and that the rights of the parties should be determined under the March 8, 1961, agreement. Plaintiff further points out that under date of November 18,1961, by another agreement, the parties terminated the March 8, 1961, purchase' agreement, specified the means of determining the amount due plaintiff thereunder and also provided for a delayed method of paying the amount due from the said defendant, Hyde, to the plaintiff.

The Purchase Order and all agreements involved are in evidence and they speak for themselves. The defendant, Hyde Construction Company, Inc., in effect claims that the plaintiff had threatened to shut down its sand plant and move off the location on the basis that it was losing money and thereby forced the defendant into entering into a new agreement; that in these circumstances the new agreement fails for a lack of consideration and the rights of the parties should be determined under the original Purchase Order which would result in the plaintiff owing the said defendant the amount sought under its counterclaim. The plaintiff, on the other hand, claims that the parties thereto had a bona fide dispute about operations under the Purchase Order and the plaintiff also undertook additional work not contemplated by the Purchase Order but included in the later agreement; that a valid consideration exists for the later agreement which is reflected by the evidence and the March 8, 1961, agreement itself, which, spoiled out the rights and obligations of the parties ; that such March 8,1961, agreement should be the instrument determining such rights, in which case the defendant must fail on its counterclaim against the plaintiff.

From a careful consideration of the evidence herein, the Court finds that by the original arrangement of the parties under the said Purchase Order of March 4, 1960, the plaintiff’s plant was to be and in fact was located on the river bed at the dam site; that the defendant, Hyde, was to furnish trucks for hauling the sand from the plant to the dam, and the defendant Hyde was to furnish the necessary equipment to mix blow sand with the sand produced by the plaintiff from the river bed at the dam site and to do the necessary mixing.

[772]*772Early in the operation the mixing process gave trouble. The Court believes that this was due to the nature of the sand at the dam site which was deposited by two converging rivers. It became necessary to move off the dam site and up one of the rivers some three or four miles. At this location the sand was satisfactory. Blending was also taken over by the plaintiff who used the equipment of the defendant, Hyde, for such purpose. More trucks were provided due to the increased haul from the new plant location to the dam. The price of the sand to the plaintiff under the new arrangement became an issue and was discussed by the parties. The defendant, Hyde, reported that it had to have the sand at any cost. Exactly what it would cost to produce the sand under the new arrangement was in dispute, the plaintiff estimating $1.25 per ton and the defendant believing that it could be produced for less than $1.00 per ton. There were some discussions about the Davis-Baeon Act which called for higher wages on the dam site than at the new location up stream and also about the plaintiff becoming a commercial producer at the new location. It appears to the Court that the Davis-Bacon Act wages were paid while on the dam site and wages were paid at the lower rate at the new location, and while efforts were made to sell some sand to other people the sand under Government specifications was not suitable and none, or practically none, was ever sold. The Court does not believe that the move up stream was made by the plaintiff to get a lower wage rate but rather was due to the mixing problem and the commercial production effort was merely desirable if possible but never developed.

It appears that at all times up to March, 1961, the difficulties encountered in mixing, hauling and the cost of production were recognized by both parties and the steps necessary to overcome the same were likewise recognized and agreed upon by both parties. On March 8,1961, the parties reconciled "the difficulties including the price dispute between them by entering into two agreements, one an agreement making the plaintiff and the defendant, Hyde, joint venturers in the production of sand, and the second, a purchase agreement between the defendant. Hyde from the joint venture of the plaintiff and the defendant Hyde. Under this arrangement the plaintiff was assured of a 5% profit over and above cost of the-sand and the defendant Hyde was assured of getting the sand and stood a chance of making some money under the joint venture, depending upon the actual cost of producing the same and hauling the same and by selling some sand commercially if possible. Also the blending process problem and method was settled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
236 F. Supp. 770, 1964 U.S. Dist. LEXIS 8005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hyde-construction-co-oknd-1964.