Baldwin v. Smith

586 S.W.2d 624, 1979 Tex. App. LEXIS 4066
CourtCourt of Appeals of Texas
DecidedAugust 16, 1979
Docket1259
StatusPublished
Cited by13 cases

This text of 586 S.W.2d 624 (Baldwin v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin v. Smith, 586 S.W.2d 624, 1979 Tex. App. LEXIS 4066 (Tex. Ct. App. 1979).

Opinion

MOORE, Justice.

The principal question involved in this case is whether the Texas Deceptive Trade Practices-Consumer Protection Act 1 applies to a building and construction contract which has been substantially performed.

On September 9, 1976, appellant, Alan Baldwin, d/b/a Alan Baldwin, Builder, entered into a written contract with appellee, Roland D. Smith, to construct a house on land owned by Smith. Under the terms of the contract Baldwin was to construct the house in a good and workmanlike manner according to plans and specifications supplied by the Veterans Administration for and in consideration of the sum of $31,300. This suit arose when Baldwin, the builder, instituted suit against Smith for, among *627 other things, damages resulting from additional costs for “extras” in the construction of the house and for interfering with the completion of the house. Smith answered with a general denial and a counterclaim for damages alleging that Baldwin failed to construct the house in a good and workmanlike manner in accordance with the plans and specifications, and that Baldwin also breached the contract by failing to pay interim interest in the amount of $2,900. Smith further alleged that the conduct of Baldwin in failing to construct the house in a good and workmanlike manner and in accordance with the plans and specifications within the 180-day period as agreed under the terms of the contract, constituted a deceptive trade practice as defined by Section 17.46 of the Act. His prayer was for actual damages in an amount necessary to complete the house, for $2,900 interim interest paid by him, and for attorney’s fees. Further, he prayed that his actual damages be trebled under the provisions of Article 17.50 of the Act.

After a trial before the court, sitting without a jury, the trial court rendered a take-nothing judgment against the builder, Baldwin. After having concluded that the builder had substantially performed the contract, the court entered judgment in favor of Smith on his counterclaim for the sum of $1,500 to cover the cost in remedying several defects and also rendered judgment in favor of Smith for the sum of $2,900 for interim interest paid by him. After finding that the total sum of $4,400 represented Smith’s actual damages, the court found that the failure to remedy the defects and the failure to pay the interim interest were in violation of the Texas Deceptive Trade Practices Act. Accordingly, the court rendered judgment in favor of Smith for treble damages for the total sum of $13,200. In addition, the court entered judgment in favor of Smith for attorney’s fees in the amount of $10,000, together with additional attorney’s fees in the event the judgment was appealed. Appellant, Alan Baldwin, perfected this appeal.

We reverse and render in part; we reform in part; and as reformed, affirm.

The facts, for the most part, do not appear to be in dispute. On September 9, 1976, the parties entered into a Builder’s and Mechanic’s Lien Contract in which Baldwin agreed to construct a house for Smith according to the plans and specifications within 180 days for and in consideration of the sum of $31,300. Under the terms of the contract, Baldwin, the builder, agreed to build the house in a good and workmanlike manner according to the plans and specifications supplied by the Veterans Administration. Baldwin further agreed to pay and save Smith harmless from all interim interest. On the same date, Smith executed a promissory note to Baldwin in the amount of $31,300 payable within 180 days. Baldwin assigned the note to Mutual Savings Institution, with recourse, in order to obtain interim financing with which to build the house. The house was to be constructed on or before March 9, 1977. Baldwin commenced construction and by January 29, 1977, Mutual Savings Institution 2 estimated that the house was 98% complete. On that date Baldwin allowed Smith to move his furniture into the house. On March 12,1977, three days after the expiration of the 180-day period, Smith and his mother began physical occupancy of the house. On March 28, 1977, some sixteen days after the expiration of the 180-day period for completion, Smith ordered Baldwin to leave the premises. Baldwin left on that date.

At the request of appellant Baldwin, the trial court filed extensive findings of fact and conclusions of law. Among the findings of fact the trial court found: (a) Baldwin, the builder, substantially performed the contract; (b) Baldwin failed to build the house in accordance with the plans and specifications in certain respects; (c) Baldwin failed to construct the house in a good *628 and workmanlike manner in certain respects; (d) Smith’s cost of remedying the defects and completing the house in accordance with the plans and specifications was $1,500; (e) Smith did not accept the defects and deviations from the plans and specifications when he moved into the house on March 12, 1977, except the fireplace-size deviation; (f) Baldwin represented that the work to be done by him would be done in a good and workmanlike manner, which it was not, and Baldwin represented his work would be of a particular standing (V.A. approved) which it was not; (g) under the terms of the contract Baldwin agreed to hold Smith harmless from any obligation to pay interim interest; (h) Smith paid interim interest accruing on the note after the 180-day period expired in the amount of $2,900; (i) that the sum of $10,000 would be a reasonable and necessary attorney’s fee for the prosecution of Smith’s claim under the Deceptive Trade Practices Act; (j) that the sum of $2,500 would be a reasonable attorney’s fee to prosecute the case through the Court of Civil Appeals, $1,000 if application for writ of error is filed, and $500 if the writ is granted.

Under the conclusions of law, the trial court concluded, among other things, that: (a) the damages of $1,500 as costs of remedying defects and $2,900 in interim interest paid by Smith to Mutual were the only proved actual damages sustained by Smith; and (b) that these damages should be trebled under the Act.

Other findings of fact and conclusions of law made by the court will be set forth in our discussion of the various points of error briefed by the parties.

Appellant attacks the judgment by seven points of error. No effort will be made in this opinion to discuss appellant’s points in the order of their appearance in the brief.

Under the third point of error appellant urges that the trial court erred in awarding appellee damages in the amount of $1,500 for repairing the defects in the house. He contends that the evidence establishes that he fully performed his contract and repaired the defects complained of by Smith.

The question as to whether the contract was fully performed or was only substantially performed is one of fact to be determined by the trier of fact. 13 Am.Jur.2d Building and Construction, sec. 129 (1964). Appellant testified that he had corrected all of the defects and that the contract had been fully performed. In rebuttal, appellee called two witnesses who testified with regard to the condition of the house. According to the testimony of Gaylon Schulle, the structure was practically complete. He estimated the cost of correcting the defects would amount to $1,500.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laredo Independent School District v. Trevino
25 S.W.3d 263 (Court of Appeals of Texas, 2000)
Murphy v. Canion
797 S.W.2d 944 (Court of Appeals of Texas, 1990)
Penick v. Penick
783 S.W.2d 194 (Texas Supreme Court, 1990)
Jonas Realty Corp. v. Coker
716 S.W.2d 169 (Court of Appeals of Texas, 1986)
Honeywell, Inc. v. Imperial Condominium Ass'n
716 S.W.2d 75 (Court of Appeals of Texas, 1986)
Jim Walter Homes, Inc. v. Valencia
679 S.W.2d 29 (Court of Appeals of Texas, 1984)
Widmer v. Stamps
663 S.W.2d 875 (Court of Appeals of Texas, 1984)
Smith v. Baldwin
611 S.W.2d 611 (Texas Supreme Court, 1980)
Norwood Builders, Inc. v. Toler
609 S.W.2d 861 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
586 S.W.2d 624, 1979 Tex. App. LEXIS 4066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-v-smith-texapp-1979.