South Texas Building Co. v. Ideal Engineering, Inc.

402 S.W.2d 292
CourtCourt of Appeals of Texas
DecidedMay 5, 1966
Docket14750
StatusPublished
Cited by12 cases

This text of 402 S.W.2d 292 (South Texas Building Co. v. Ideal Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Texas Building Co. v. Ideal Engineering, Inc., 402 S.W.2d 292 (Tex. Ct. App. 1966).

Opinions

COLEMAN, Justice.

This is a suit by a sub-contractor against the prime contractor and the owner to recover the balance due under a construction contract. The trial was to the court without a jury. No findings of fact were requested. There is no statement of facts.

The parties entered into certain stipulations of fact in the trial court, which have been included in the transcript. The judgment entered in favor of the sub-contractor recited that evidence was heard and considered.

South Texas Building Company contracted to construct for Twelve Oaks Properties a nursing home project on Lots 7, 8, 11 and 12, Block 2, Reynolds Acres Addition in Houston, Texas. Pursuant to a published invitation to bid Ideal Engineering, Inc. approached South Texas’ building superintendent and discussed with him the possibility of effecting a saving on the total cost of the project, and Ideal was requested by the superintendent to submit its suggestions to the engineer employed by the owner’s architect. Ideal was furnished a copy of the job specifications by South Texas. Ideal discussed with the engineer the substitution of certain items required by the specifications, and then submitted a proposal to South Texas based on the use of the substituted items. Thereafter Ideal and South Texas entered into a contract. Among the substituted items were a cooling tower and certain pumps. These items were installed by Ideal after securing prior written approval of the engineer employed by owner’s architect to which Ideal had been referred by South Texas’ building superintendent.

Payments were made to Ideal by South Texas periodically. On February 10, 1964, a payment of $20,000.00 was made, leaving due under invoices previously presented the sum of $9,009.00. After this payment was received Ideal was advised by the superintendent that the F.H.A. would not approve the cooling tower and two pumps. Ideal offered to remove the tower and pumps and to substitute equipment which would be approved if South Texas would pay the additional cost of the equipment of approximately $3,000.00. This offer was rejected by South Texas.

On April 10, 1964, Ideal attempted to hook up the cooling tower and was advised by the superintendent that it could not do so and would not be permitted on the job any further since the cooling tower had been rejected by the FHA. Other than this, involving three days’ work by two men, the contract, including the equipment approved by the engineer, had been completed by Ideal. On that date patients were in the nursing home. The cooling tower and pumps were subsequently put into use and were used up to the date of trial.

Ideal contends that the sum of $17,219.80 is due under the contract. On March 26, 1964, Ideal caused a lien to be filed against the property recorded in Vol. 97, page 302, Mechanics’ and Materialmen’s Lien Records, Harris County, Texas. There was no prayer for foreclosure of this lien in the plaintiff’s petition, and no foreclosure was granted by the judgment.

[294]*294The contract recites that the project was to be erected with funds obtained pursuant to a commitment from the Federal Housing Commissioner for insurance of a loan. The FHA required the removal of the tower and pumps in controversy and their replacement with different equipment. To insure that this requirement will be met South Texas has deposited with FHA the sum of $6,000.00.

Among the various provisions of the contract between Ideal and South Texas, those most pertinent to this controversy follow:

“2. The materials to be furnished and work to be done by Subcontractor hereunder are:

“A COMPLETE HEATING, VENTILATING AND AIR CONDITIONING SYSTEM IN ACCORDANCE WITH PLANS AND SPECIFICATIONS. ANY DEVIATION FROM PLANS AND SPECIFICATIONS MUST BE ACCEPTABLE TO F. H. A., ARCHITECT, ENGINEER AND OWNER.
“NOTE: INDEMNITY BOND FOR $64,000.00 REQUIRED.”

“4. A Carroll Broadnax, Architect & Associates will have general supervision of the work and will have authority to stop the work if necessary to insure its proper execution. The Afchitect will pass on all matters pertaining to progress, compliance and completion, including but not limited to the certification of the date of final completion of the project, for all purposes set forth herein-

“6. It is specifically understood and agreed that no payment or draw shall be due under this Contract until and unless the work has theretofore satisfactorily met all inspections that may be required .by the Architect, the F.H.A., the City or other governmental agency, and if any of such work shall fail to pass such inspections, Subcontractor shall remedy the defects at his expense and pay all other damages occasioned Contractor by reason thereof, including all reinspection fees; and in the event or recurring defects or delay by Subcontractor in making defects good, Contractor may correct defects without Subcontractor’s assistance and charge the expense thereof to Subcontractor and Contractor may in such case cancel this entire contract.

“12. Subcontractor guarantees a good workmanlike job according to the plans and specifications, the Architect or Owner’s Superintendent, and according to F.H.A. and City specifications and requirements. Any departure from standard practices or any failure of Subcontractor to meet the Architect’s requirements or any failure by Subcontractor to meet requirements of the plans and specifications, or any failure of Subcontractor to have a full crew and equipment on the job when needed, or any default by Subcontractor under the provisions of this Contract, shall give contractor the option to cancel this Contract and retain all unpaid portions thereof as liquidated damages and to recover from Subcontractor such additional damages as Contractor may suffer, and to employ others to do the work and collect therefor from Subcontractor and charge the cost thereof to the money due Subcontractor under this Contract, or any of said remedies, and Contractor shall also have all other remedies allowed in law or equity. It is especially understood and agreed that all work done hereunder shall be done with the utmost speed and that Contractor shall have perference over any and all other jobs which Subcontractor may have or hereafter take; and any failure of Subcontractor for any reason to have a full crew available when needed shall be reason for cancellation regardless of the reason for such delay.”

Appellant, South Texas, contends that the trial court erred in granting judgment in that (1) there is “no indication in this record of full or substantial compliance with or performance under the terms of the contract by Ideal Engineering, Inc.”; and [295]*295(2) “it affirmatively appears that Ideal Engineering, Inc. breached such contract when it failed to secure FHA approval of deviation from contractual plans and specifications.”

While it is not clear whether the original plans and specifications were amended in writing, the trial court could have found that such an amendment was made with the consent of the contractor. Since it is stipulated that the work was completed in accordance with the plans and specifications (as modified with the approval of the owner prior to the execution of the sub-contract), with the exception of the connection of the water tower, a finding by the trial court that Ideal had fully performed the contract will be implied unless such a conclusion is prevented by the stipulation that FHA required that the tower and pumps be removed and substituted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baldwin v. Smith
586 S.W.2d 624 (Court of Appeals of Texas, 1979)
Godde v. Wood
509 S.W.2d 435 (Court of Appeals of Texas, 1974)
Ryan v. Thurmond
481 S.W.2d 199 (Court of Appeals of Texas, 1972)
Tenneco Oil Company v. Padre Drilling Company
453 S.W.2d 814 (Texas Supreme Court, 1970)
Griffin v. Holiday Inns of America
452 S.W.2d 517 (Court of Appeals of Texas, 1970)
Seal v. Rogers
448 S.W.2d 722 (Court of Appeals of Texas, 1969)
Shivers v. Feuhs
438 S.W.2d 585 (Court of Appeals of Texas, 1969)
Boaz Well Service, Inc. v. Carter
437 S.W.2d 38 (Court of Appeals of Texas, 1969)
Maloney v. Strain
410 S.W.2d 650 (Court of Appeals of Texas, 1966)
South Texas Building Co. v. Ideal Engineering, Inc.
402 S.W.2d 292 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
402 S.W.2d 292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-texas-building-co-v-ideal-engineering-inc-texapp-1966.