Ryan v. Thurmond

481 S.W.2d 199, 1972 Tex. App. LEXIS 2458
CourtCourt of Appeals of Texas
DecidedApril 27, 1972
Docket632
StatusPublished
Cited by32 cases

This text of 481 S.W.2d 199 (Ryan v. Thurmond) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryan v. Thurmond, 481 S.W.2d 199, 1972 Tex. App. LEXIS 2458 (Tex. Ct. App. 1972).

Opinion

OPINION

NYE, Chief Justice.

This is a suit to recover the balance due on a written building contract for work done in connection with the construction of a building in Kingsville, Texas. The owner of the building, John W. Ryan, filed a cross-action to recover damages for delay on the part of the contractor in completing the building. The case was tried to a jury and, based on answers to special issues, judgment was rendered for the contractor. All relief was denied to the owner on his cross-action. The owner has perfected his appeal from the judgment of the trial court.

On August 23, 1967, Jimmie Thurmond, 1 d/b/a Jimmie Thurmond Construction Company, entered into a written agreement with *202 John W. Ryan to construct a building for Ryan for the sum of $294,000.00. The contract provided that the work shall commence immediately and shall be substantially completed by January 10, 1968. The completed building was to be turned over to the owner not later than February 10, 1968. Part of the work was done by the contractor pursuant to this agreement and part of the work was performed pursuant to several oral agreements entered into as additions to the work specified in the written agreement. The building was not substantially completed until May 28, 1968, at which time the tenant moved in and occupied the building. As the construction of the building progressed, the owner paid the contractor $274,600.00. Later certain disputes arose between the contractor and the owner.

The contractor brought this suit to recover the balance due on the contract (plus additions, and less certain deletions agreed to by the parties). The owner’s cross-action against the contractor was predicated on the delay by the contractor in completion of the contract. Ryan (called the owner hereafter) sought damages for loss of the rental value to the building and for the interest he paid on money borrowed to complete and finance the building.

The owner complains of the judgment of the trial court in 479 points of error, summarized at the suggestion of this Court in his fifth brief to 33 contentions. We have reviewed the entire voluminous record and considered all the points of error, the appellant’s contentions, as well as the contractor’s two cross-points. For the purpose of disposition of this appeal, we consider in detail three basic points of error, two of which require a reversal of this case. While isolation of three of the asserted errors might seem to be a cursory treatment of the points on appeal, they nevertheless form the only crux for reversal of the instant appeal.

First the owner contends in a series of points of error, that the contractor’s suit was tried on the wrong theory and therefore the judgment is erroneous. The contractor sought payment for the balance due on the contract. His suit was based on the fact that he had fully completed the construction contract and the balance of the money under the contract was due and owing. The pleadings and proof were predicated on this theory. The contract, on the other hand, stated that (Art. 5) :

“Final payment shall be due Thirty days after (1) Substantial Completion of the work provided the work be then (2) fully completed and the contract (3) fully performed.” (Emphasis supplied)

This provision of the contract (in three parts) requires, first of all, that: The work must be substantially completed. Then after thirty days, final payment will be due. Provided, and only if, the two following conditions take place: (1) That the work be fully completed, and (2) the contract fully performed. The owner contends that the latter provision has never taken place; therefore, the contractor is not entitled to the balance due under the contract. We agree.

Mrs. Thurmond filed this suit to recover everything left due and owing under the contract, i. e.: $24,224.17. She plead full performance of the contract and complete construction of the building. In the alternative, she plead a full recovery based on quantum meruit. It was undisputed that the building was substantially completed on May 28, 1968, the date the tenant started its occupancy. However, the evidence is virtually undisputed that the contractor never did fully perform all of the terms and conditions of the contract.

We recognize the rule that a strict and literal performance of a building and construction contract is not absolutely essential to entitle a contractor to recover on his contract. If the contractor has substantially performed, he may recover the contract price less the reasonable costs of remedying trivial defects and omissions so *203 as to make the structure comply with the contract terms. Atkinson v. Jackson Bros., 270 S.W. 848 (Tex.Com.App.1925, holding approved); Graham Construction Co. v. Walker Process Equipment, Inc., 422 S.W. 2d 478 (Tex.Civ.App.—Corpus Christi 1967, ref’d n. r. e.); Graves v. Albert & Fuess, 104 Tex. 614, 142 S.W. 869 (1912); Christy v. Williams, 292 S.W.2d 348 (Tex.Civ.App.—Galveston 1956) and 156 Tex. 555, 298 S.W.2d 565 (1957); South Texas Building Co. v. Ideal Engineering, Inc., 402 S.W.2d 292 (Tex.Civ.App.—Houston 1966, ref’d n. r. e.).

Here, however, the contractor did not plead or prove the requisites of substantial performance. The contractor’s entire suit was predicated on the fact that he had fully completed the contract and was therefore entitled to full recovery of all monies due under the contract. There were no issues submitted as to the costs to complete the contract according to its complete terms, nor were there issues submitted as to the damages caused the owner by the contractor’s failure to complete the contract.

The contract, in Art. 1, entitled “Scope of the Work”, provided that the contractor “. . . shall do everything required by this Agreement, the General Conditions of the Contract, the Specifications and the Drawings.” The evidence clearly reflects undisputed instances where the contractor did not comply with all of the terms of the contract. At the time the suit was filed on December 9, 1968, the following items were alleged definitely to be instances where the contractor had not complied with the contract terms:

(1) The emergency lighting system had not been installed ;
(2) The contractor still owed bills on the job amounting to $9,952.47;
(3) A certain lien was still unpaid and a mechanic’s lien was filed and unreleased;
(4) Thurmond’s own mechanic’s lien was still on file and had never been released;
(5) Certain warranties and guarantees required by the contract had not been furnished;
(6) The contractor had not submitted satisfactory evidence that all bills for all of the labor and material had been paid.

After the suit was filed, a number of the contract deficiencies were satisfied by the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brent Timmerman D/B/A Timmerman Custom Builders v. Richard Dale, J.
397 S.W.3d 327 (Court of Appeals of Texas, 2013)
Bluebonnet Savings Bank, F.S.B. v. Grayridge Apartment Homes, Inc.
907 S.W.2d 904 (Court of Appeals of Texas, 1995)
Advance Tank & Construction Co. v. City of DeSoto
737 F. Supp. 383 (N.D. Texas, 1990)
C.S.R., Inc. v. Industrial Mechanical, Inc.
698 S.W.2d 213 (Court of Appeals of Texas, 1985)
Intermedics, Inc. v. Grady
683 S.W.2d 842 (Court of Appeals of Texas, 1984)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Marshall v. Karl F. Schultz, Inc.
438 So. 2d 533 (District Court of Appeal of Florida, 1983)
Powers v. Walsh Engineering, Inc.
657 S.W.2d 12 (Court of Appeals of Texas, 1983)
Irrigation Construction Co. v. Motheral Contractors, Inc.
599 S.W.2d 336 (Court of Appeals of Texas, 1980)
Wood v. Texas Farmers Insurance Co.
593 S.W.2d 777 (Court of Appeals of Texas, 1979)
Seismic & Digital Concepts, Inc. v. Digital Resources Corp.
590 S.W.2d 718 (Court of Appeals of Texas, 1979)
Taylor v. Rigby
574 S.W.2d 833 (Court of Appeals of Texas, 1978)
Woodard v. Marathon Letourneau Co.
570 S.W.2d 552 (Court of Appeals of Texas, 1978)
Warren v. Denison
563 S.W.2d 299 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
481 S.W.2d 199, 1972 Tex. App. LEXIS 2458, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryan-v-thurmond-texapp-1972.