Griffin v. Holiday Inns of America

452 S.W.2d 517, 1970 Tex. App. LEXIS 2375
CourtCourt of Appeals of Texas
DecidedMarch 25, 1970
Docket11746
StatusPublished
Cited by7 cases

This text of 452 S.W.2d 517 (Griffin v. Holiday Inns of America) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffin v. Holiday Inns of America, 452 S.W.2d 517, 1970 Tex. App. LEXIS 2375 (Tex. Ct. App. 1970).

Opinion

HUGHES, Justice.

Appellant, Leon Griffin, sued Holiday Inns of America, called “Contractor” and San Marcos Motel Company, called “Owner,” the first named being a foreign and the latter named being a domestic corporation, upon a contract between appellant called “subcontractor” and contractor wherein appellant obligated himself to do certain paving adjacent to the Holiday Inn of San Marcos, Texas, appellant alleging that he had fully performed such contract but that Contractor had failed and refused to pay a balance of $6,538.61 due under its terms. Appellant sought recovery of this amount, attorney’s fees and foreclosure of a materialmen’s and mechanic’s lien on the Motel, the property of Owner.

Appellees filed an answer and cross-action. The answer consisted of special exceptions, a general denial and a further answer alleging that appellant had not performed the contract, listing eighteen specific violations of the contract. Appellees prayed that appellant take nothing by liis suit, that the cloud cast by the lien be removed and that they recover $6,812.27 which they had paid on the contract.

Appellees’ cross-action alleged that in order to correct the deficiencies in the performance of the paving contract by appellant an expenditure of $18,073.20 by them *519 would be required, and they prayed for judgment in this amount.

There is no allegation in any of the pleadings that appellant intentionally or in bad faith failed to perform the contract according to its terms.

Trial was to the court without a jury. The Trial Court rendered a formal take nothing judgment against appellant on his suit and similarly against appellees on their cross-action, removed the cloud on the title to the Motel cast by the asserted lien and divided the costs one half to appellant and one half to appellees.

No findings of fact or conclusions of law were requested of or filed by the Trial Court.

Appellees excepted to the judgment, gave notice of appeal but did not file an appeal bond or make a deposit in lieu of bond. They have filed a cross point in their brief.

Appellant does not suggest, and his pleadings would not support any right of recovery based on quantum meruit.

Appellant has three points the substance of which is that there is no evidence or insufficient evidence to support the judgment against him.

We have appraised these points under the rules stated in King v. King, 150 Tex. 662, 244 S.W.2d 660 (1951).

We overrule all three points.

The essence of the contract between the parties to it is contained in Sec. 2, which we quote:

“Section 2. The Subcontractor and the Contractor agree that the materials to be furnished and work to be done by the Subcontractor are furnishing all labor, material, and equipment to install six inch base to be layed in 2, 3" layers compacted by power compacters, plus 1%" hot-mix asphalt. Prior to installing base material, all fill and ground work must be compacted to 95% density. The dirt work includes the inner court yard around swimming pool and under canopy, and all areas covered by asphalt. Including driveways out to Loop 82, and installing drainage tile furnished by prime contractor. Over the prepared stabilized aggregate base cover, install an asphaltic primer at the rate of .6 gallons per sq. yd. Binder topping shall conform to the state highway department specifications for parking areas and driveways in locality of project. Furnish certifications of compliance. Base and topping shall be so installed without depressions where water may collect. The subcontractor shall clean the job of any debris caused by his phase of work, and nothing but a first class job will be accepted. Any thing not mentioned in this contract will be covered according to these specifications.”

The date of the contract was February 29, 1968. While not so specified in the contract, appellant agreed that the job would be completed by March 28, 1968. The reason for the time agreement was that the Motel had a convention scheduled on that date and the opening of Hemisfair was near.

The contract price was $13,000 for 7,000 or less sq. yds. of paving and $1.72 per sq. yd. additional above this amount. Appellant claimed 204 additional sq. yds. The cost o.f materials for this job, $6,812.27, was paid by appellees directly to suppliers and is not involved here. Appellant sought recovery of $6,538.61 plus attorney’s fees.

The evidence shows that the materials delivered to the job site were adequate to comply with the requirements of the contract for a six inch base and a one and one half inch layer of asphalt topping.

There is no evidence that any of this material was diverted from this job.

Raymond Canion, a graduate engineer, who was highly qualified as an expert in paving work, testified for appellant. Mr. Canion examined the parking lot in suit on June 29, 1969. He testified that the pav *520 ing was “as satisfactory as any in this town,” that the job was not perfect and that there were depressions on the surface but it had “no more depressions than an average parking lot around a college campus here or in Austin under the same type of circumstances.” Mr. Canion observed considerable settling or uplift in the curbing around the parking area which was not laid by appellant and the cracking of brick in a sign and that this indicated to him that the parking area was on “an expansive clay or some type of plastic material.” Under these conditions, Mr. Canion expressed surprise that the paving was in as good condition as it was after more than a year of use. Mr. Canion said that the depressions or ponding in the pavement should not cause worry although, “there are some places that are going to need some maintenance in the future like any other parking lot.” He reiterated, “ * * * I would say again after a year’s time the fact that it is there in substantial condition is a fairly good rule of thumb or mark showing that it was a satisfactory job. * * * ”

Mr. D. E. Jacobs, an employe of Engineering Testing Laboratories, Inc., also a highly qualified witness, testified for appellant. On April 10, 1969, Mr. Jacobs conducted tests of the paving at the request of appellant. He made three test holes located, he said, in areas so as to be representative of the entire lot. The result of these tests may be summarized as follows:

“First Sample: Base 7 inches, asphalt 1¾ inches
Second Sample: Base 5¾ inches, asphalt 1⅛ inches
Third Sample: Base 5½ inches, asphalt 1 ¾ inches
Average: Base Six and a fraction inches: Asphalt One and one-half plus a fraction inches”

The record shows that in March 1968 Trinity Testing Laboratory of Austin at the request of appellees tested the sub-base on the parking lot. The results of these tests were testified to by Mr. Alvis Vandy-griff, Jr., a witness for appellees as follows :

“Q So as a result of those tests, the density at that particular time, which is March 15, was 97.8 and 96.2, was it not?
A Correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosas v. Bursey
724 S.W.2d 402 (Court of Appeals of Texas, 1986)
Griffin v. Holiday Inns of America
496 S.W.2d 535 (Texas Supreme Court, 1973)
Monarch Life Insurance Co. v. Trinity Industries, Inc.
495 S.W.2d 41 (Court of Appeals of Texas, 1973)
Griffin v. Holiday Inns of America
480 S.W.2d 506 (Court of Appeals of Texas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
452 S.W.2d 517, 1970 Tex. App. LEXIS 2375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffin-v-holiday-inns-of-america-texapp-1970.