Widmer v. Stamps

663 S.W.2d 875, 1984 Tex. App. LEXIS 4901
CourtCourt of Appeals of Texas
DecidedJanuary 12, 1984
DocketC14-82-429CV
StatusPublished
Cited by16 cases

This text of 663 S.W.2d 875 (Widmer v. Stamps) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Widmer v. Stamps, 663 S.W.2d 875, 1984 Tex. App. LEXIS 4901 (Tex. Ct. App. 1984).

Opinions

OPINION

ROBERTSON, Justice.

This appeal is from a judgment entered in favor of appellee in a suit concerning the construction of a home. While the issues themselves are not especially complex, this case has been made complex by the large number of pleadings, the extent of testimony (in excess of 900 pages), the number of special issues (38) and the 28 points of error on appeal. Basically, appellants’ contentions concern (1) the amount they were entitled to as an offset against the contract price; (2) the state of the evidence; (3) failure to submit special issues; (4) conflicts in jury answers; (5) error in awarding rental value of home as an element of damages; [878]*878(6) the award of attorney’s fees and prejudgment interest, and (7) the failure to award treble damages. We reform the judgment to delete the award of reasonable rental value of the home, but otherwise affirm.

The pertinent facts indicate that on October 9, 1976 the parties signed a contract providing that appellee would build a home for appellants for which he would be paid his actual costs plus the lesser of 15% or $7,500. The estimated cost of construction was $62,500 and the estimated time for completing construction was six months. The interim construction loan was closed on November 18, 1976. Construction commenced the following month and in July of 1977 appellants moved into the house. They complained to appellee about work not yet completed. Appellants were approved for a permanent loan and a closing was initially set for August of 1977, then rescheduled for the following month. This litigation ensued and the parties did not come to a final agreement until December 31, 1977 when closing on the permanent loan commitment was finally held.

In order to properly address appellants’ points of error, we note that the jury:

1) found the actual cost to construct the house according to contract and agreement of parties would have been $70,000;
2) found the reasonable profit in construction of house would be $7,500;
3) found appellee made an express warranty for all work under the contract for one year;
4) found the house had a defect in workmanship;
5) found appellee failed to correct the defect;
6) found such failure was a proximate cause of damages to appellants;
7) failed to find such failure to correct the defect adversely affected appellants;
8) found the reasonable cost to repair and correct defect would be $2,500;
9)failed to find appellants’ home was not constructed in good and workmanlike manner;
10) failed to find appellee failed to complete the home within a reasonable time;
11) found appellants did not lose money on the sale of their other home; did not spend additional funds for additional loan and did not lose money representing rental on value of home being built;
12) found five of six specific acts or practices inquired about, to have occurred but none to have been false, misleading or deceptive;
13) found appellee did not misrepresent materials or services;
14) failed to find that any of the acts and practices constituted an unconscionable action or course of action;
15) found reasonable attorney’s fees for appellants’ attorney;
16) found the reasonable rental value of the house from time appellants moved in until closing was $4,200;
17) found appellee substantially performed the contract;
18) found that by taking home in July appellants accepted contract work performed by appellee;
19) found the bar between kitchen and den was not constructed in a good and workmanlike manner;
20) failed to find the oven and utility room wall were not constructed in good and workmanlike manner;
21) found the kitchen cabinets containing stove were not constructed in a good and workmanlike manner;
22) failed to find appellee was not given a reasonable opportunity to cure defects in construction;
23) failed to find appellee had no written notice of complaint of mislocation of utility room wall and oven area;
24) found appellee had no written notice of complaint about kitchen cabinets containing stove;
[879]*87925) found appellee had no written notice of complaint about bar between kitchen and den;
26) found appellants have owed money to appellee since date of closing;
27) found reasonable attorney’s fees for appellee.

In points of error one through five, grouped for discussion, the issue presented is the amount to which appellants are entitled as an offset against the contract price. Appellants argue the trial court erred in failing to enter a take nothing judgment against appellee because “he failed to furnish evidence to properly measure the deductions and omissions to be subtracted from the contract price.” This issue is not properly preserved for our consideration because it was never presented to the trial court. If it were properly before us, we note that while it is true that where the issue is substantial performance by the contractor, the contractor has the burden “to furnish the evidence to properly measure the deductions allowable necessary to remedy the defects,” Atkinson v. Jackson Bros., 270 S.W. 848 (Tex.Comm’n App.1931, holding approved), we do not see how this fact can benefit appellants. Appellants presented extensive testimony concerning the “deductions and omissions to be subtracted from the contract price.” Only one monetary damage issue was submitted to the jury asking for the sum of money that was reasonable as a “cost to repair and correct the defect in workmanship.” There were no objections to the issue and the jury answered $2,500. Appellants complaint in this regard is without merit.

Appellants further argue it was error to award appellee the full contract price offset only by the damages found by the jury for what they contend was a breach of express warranty. What we have said above applies equally to this contention. Evidence was offered; the issue was submitted to the jury; the jury answered the issue, and the court entered judgment. The argument is without merit.

As further argument on this issue appellants contend they were entitled to an offset from the full contract price for the value of the work they performed including their supervision, cost to complete and cost to correct. No special issues were request ed for these offsets; therefore, appellants cannot complain for the first time on appeal. Points of error one through five are overruled.

The next group of points of error complain of the state of the evidence. In numbers six and seven appellants complain of the sufficiency of the evidence to support the jury answer of $7,500 to compensate appellee for his profit. The contract expressly provided for a profit of the lesser of 15% or $7,500.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petties v. Petties
129 S.W.3d 901 (Missouri Court of Appeals, 2004)
Murphy v. Canion
797 S.W.2d 944 (Court of Appeals of Texas, 1990)
Cissne v. Robertson
782 S.W.2d 912 (Court of Appeals of Texas, 1989)
Davis v. Sheerin
754 S.W.2d 375 (Court of Appeals of Texas, 1988)
Champion v. Wright
740 S.W.2d 848 (Court of Appeals of Texas, 1987)
Moore v. Rotello
719 S.W.2d 372 (Court of Appeals of Texas, 1986)
Marcus v. Jefferson Investment Corp.
797 F.2d 227 (Fifth Circuit, 1986)
Griffith v. Geffen & Jacobsen, P.C.
693 S.W.2d 724 (Court of Appeals of Texas, 1985)
Argos Resources, Inc. v. May Petroleum Inc.
693 S.W.2d 663 (Court of Appeals of Texas, 1985)
McKinley v. Drozd
685 S.W.2d 7 (Texas Supreme Court, 1985)
Building Concepts, Inc. v. Duncan
667 S.W.2d 897 (Court of Appeals of Texas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
663 S.W.2d 875, 1984 Tex. App. LEXIS 4901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/widmer-v-stamps-texapp-1984.