Black Lake Pipe Line Co. v. Union Construction Co.

538 S.W.2d 80, 19 Tex. Sup. Ct. J. 318, 1976 Tex. LEXIS 221
CourtTexas Supreme Court
DecidedMay 19, 1976
DocketB-5285
StatusPublished
Cited by315 cases

This text of 538 S.W.2d 80 (Black Lake Pipe Line Co. v. Union Construction Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black Lake Pipe Line Co. v. Union Construction Co., 538 S.W.2d 80, 19 Tex. Sup. Ct. J. 318, 1976 Tex. LEXIS 221 (Tex. 1976).

Opinion

*83 SAM D. JOHNSON, Justice.

Union Construction Company, Inc., Mobile Pipe Constructors, Inc., and Dillingham Corporation brought this action against Black Lake Pipe Line Company to recover for extra work performed during the construction of a pipeline for Black Lake. The trial court rendered judgment on a jury verdict for Union Construction Company in the principal amount of $160,096.61, and for Mobile Pipe Constructors, Inc. and Dilling-ham Corporation in the principal amount of $95,428.50. The court of civil appeals affirmed, holding that the plaintiffs were entitled to recover upon the theory of quantum meruit. 520 S.W.2d 486. We reverse and render in part and reverse and remand in part.

On January 4,1967 Mobile Pipe Constructors, Inc. and Dillingham Corporation, joint venturers known as Mobile Pipe-Dillingham (MPD), and Black Lake executed a prime contract that provided for the construction of a 125-mile pipeline 8⅝⅞ inches in diameter beginning in Natchitoches Parish, Louisiana and extending to a point in Hardin County, Texas. The agreement contemplated that a new device known as a mobile pipe mill, owned by Mobile Pipe Constructors, Inc., would be employed to lay the pipe. The pipe mill was a large vehicle on caterpillar treads that moved slowly down the right-of-way fabricating pipe in 1,000- to 1,500-foot lengths from rolls of flat steel. If the mobile pipe mill performed on schedule, the completion date of the pipeline as determined by the contract was April 15, 1967. If the pipe mill did not perform properly, however, MPD was allowed a “reasonable period of time, but no later than June 15, 1967,” to complete construction of the pipeline utilizing commercial mill pipe and conventional pipeline construction techniques. Contemporaneously with the execution of the prime contract, MPD subcontracted to McCathern, Inc. substantially all of the work under the prime contract with the exception of the operation of the pipe mill and the fabrication of the pipe. Subsequent to the execution of these contracts, work thereunder was begun.

Due to mechanical problems with the pipe mill and impediments created by the swamps and timberland through which the pipeline right-of-way passed, MPD failed to complete the project by April 15, 1967. Pursuant to the agreement, the completion date was then extended to June 15, 1967. In May 1967 the use of the pipe mill was discontinued. Shortly thereafter a dispute arose between MPD and McCathern, Inc. causing McCathern to withdraw from the job. Black Lake then notified MPD that it would terminate the agreement and employ another contractor unless MPD engaged a new subcontractor to proceed with the pipeline construction. Black Lake further offered to extend the completion date of the pipeline to August 1, 1967 if MPD engaged a new subcontractor.

On June 19, 1967 MPD entered into an agreement with Union Construction Company that provided for the construction by August 1, 1967 of a 67-mile stretch of the pipeline. The agreement between MPD and Union incorporated most of the provisions of the prime contract, and Union was responsible for all phases of construction on the 67-mile stretch of the pipeline. Meanwhile, MPD continued working toward completion of the remainder of the pipeline with its own crew. After Union began work on the project additional delays were encountered. MPD then sought and obtained from Black Lake an agreement extending the completion date from August 1, 1967 to August 15, 1967 plus a reasonable time for right-of-way cleanup work. It was not until November 28,1967 that the cleanup work was finally completed to Black Lake’s satisfaction.

The parties agree that Union and MPD have completed and have been paid for the work called for by the terms, plans, and specifications of their contracts. This lawsuit stems from a dispute among the parties regarding extra work.

MPD officially notified Black Lake as early as October 23,1967 of its intent to file extra work claims. Both MPD and Union presented their claims to Black Lake in March of 1968. Black Lake rejected the *84 claims and this litigation ensued. Union, seeking a total recovery of $298,255.99, filed suit against Black Lake and MPD alleging that it was required to perform a considerable amount of additional or extra work in order to obtain approval and acceptance of its work by Black Lake Pipe Line Company. MPD answered and filed a cross claim against Black Lake alleging that Black Lake required them to perform work in excess of that required by the contract and claiming damages in the amount of $346,-966.56.

The items of extra work complained of by Union and the respective jury awards for such items were as follows:

1. Excessive work performed in uncovering, for additional inspection, pipe which had already been placed in the pipeline ditch with the approval of Black Lake, $3,120.31;
2. Additional costs resulting from the requirements by Black Lake that inside air clamps rather than conventional outside clamps be employed in the pipe alignment operation, $3,547.95;
3. Additional costs resulting from the requirements made during the course of the work that Union add a second spread of men and equipment, $109,415.50;
4. Additional costs resulting from the firing by Black Lake of a welder-employee of Union (no award was made for this item of extra work because the jury failed to find that the firing of the welder caused an increase in Union’s cost of performing the work);
5. Excessive work performed in moving and returning equipment and personnel to and from construction locations caused by the failure of Black Lake to keep available the line pipe that it was obligated to furnish, $6,388.85;
6. Excessive work performed in the removal of stumps, brush, tree limbs, and other debris from off-right-of-way areas, $12,862.94;
7. Excessive work performed in reworking the crown over portions of the pipeline ditch, $6,833.75;
8. Excessive work performed in the cleanup operations on the right-of-way, $10,722.40;
9. Excessive work performed in the construction of terraces across the pipeline ditch to direct the flow of water into natural drainage courses, $5,893.51;
10. Excessive work performed in disking pastureland, $1,311.40.

The items of extra work complained of by MPD and the respective jury awards for such items were as follows:

11. Excessive work performed in the cleanup operations on the right-of-way, $32,244.75;
12. Excessive work performed in the construction of terraces across the pipeline right-of-way to direct the flow of water into natural drainage courses, $39,410.25;
13. Excessive work performed in the removal of stumps, brush, tree limbs, and other debris from off-right-of-way areas, $22,200.50;
14. Excessive dredging at the tailrace of the Toledo Bend Dam, $1,573.00;
15.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Concept General Contracting, Inc. v. Asbestos Maintenance Services, Inc.
346 S.W.3d 172 (Court of Appeals of Texas, 2011)
Bluelinx Corp. v. Texas Construction Systems, Inc.
363 S.W.3d 623 (Court of Appeals of Texas, 2011)
Tribble & Stephens Co. v. RGM Constructors, L.P.
154 S.W.3d 639 (Court of Appeals of Texas, 2005)
Kerr-McGee Corp. v. Helton
134 S.W.3d 204 (Court of Appeals of Texas, 2002)
Rogers v. Cigna Healthcare of Texas, Inc.
227 F. Supp. 2d 652 (W.D. Texas, 2001)
Jensen Construction Co. v. Dallas County
920 S.W.2d 761 (Court of Appeals of Texas, 1996)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
Arthur Andersen & Co. v. Perry Equipment Corp..
898 S.W.2d 914 (Court of Appeals of Texas, 1995)
Lynx Exploration and Production Co. v. 4-Sight Operating Co.
891 S.W.2d 785 (Court of Appeals of Texas, 1995)
Crest Construction, Inc. v. Murray
888 S.W.2d 931 (Court of Appeals of Texas, 1995)
Sassen v. Tanglegrove Townhouse Condominium Ass'n
877 S.W.2d 489 (Court of Appeals of Texas, 1994)
Galveston County Fair & Rodeo, Inc. v. Glover
880 S.W.2d 112 (Court of Appeals of Texas, 1994)
Martinez v. Hardy
864 S.W.2d 767 (Court of Appeals of Texas, 1993)
Central Savings & Loan Ass'n v. Stemmons Northwest Bank, N.A.
848 S.W.2d 232 (Court of Appeals of Texas, 1992)
Coker v. Burghardt
833 S.W.2d 306 (Court of Appeals of Texas, 1992)
Pic Realty Corp. v. Southfield Farms, Inc.
832 S.W.2d 610 (Court of Appeals of Texas, 1992)
Welder v. Welder
794 S.W.2d 420 (Court of Appeals of Texas, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
538 S.W.2d 80, 19 Tex. Sup. Ct. J. 318, 1976 Tex. LEXIS 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-lake-pipe-line-co-v-union-construction-co-tex-1976.