George v. Hall

371 S.W.2d 874
CourtTexas Supreme Court
DecidedNovember 6, 1963
DocketA-9358
StatusPublished
Cited by7 cases

This text of 371 S.W.2d 874 (George v. Hall) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George v. Hall, 371 S.W.2d 874 (Tex. 1963).

Opinion

SMITH, Justice.

Petitioner’s motion for rehearing is granted; the Court’s opinion delivered on July 24, 1963, is withdrawn and the following is substituted therefor.

On October 7, 1960, the respondents, W» T. Hall, Jr., and W. T. Hall, III d/b/a, W. T. Hall, contractor and builder, brought this suit against Jesse A. George and Mona George, husband and wife, petitioners, and the Marshall Savings & Loan Association, Marshall, Texas, a corporation. The petitioners shall hereinafter be referred to as the Georges, the respondents as Hall and the Loan Association as the Association.

Hall alleged that he agreed to construct for the Georges a one-story brick veneer-dwelling on premises owned by the Georges, according to certain plans and specifications signed by Hall and the Georges for a total consideration of $24,900.00; that the Georges paid the sum of $5,900.00 in cash and executed a promissory note for $19,000.00; that Hall and the Georges, thereafter, on September 17, 1959, executed a mechanic’s and materialmen’s lien contract to secure said note; that on the date of its execution Hall assigned and conveyed the note together with the mechanic’s and material-men’s lien to the Association, and that at the time of the filing of this suit there remained unpaid the sum of $9,052.00.

Hall alleged that he complied with the terms of the contract and that the Georges approved the work and accepted the premises by taking possession thereof on or about September 7, 1960; that having accepted the premises, the Georges are bound by the terms of the mechanic’s and materialmen’s lien contract wherein it was stipulated and agreed that:

“ * * * the taking of possession * * * of the improvements * * * either before or after same has been completed shall constitute a full and *876 complete acceptance of same * * * and the lien herein created shall he a valid and enforceable lien for the full amount of the * * * note, and the parties of the first part [the Georges] by taking such possession shall waive all defenses, offsets, and counterclaims to such indebtedness and the lien securing same, and the same shall become valid and enforceable

Answers were filed by the Georges asserting that Hall was not entitled to any of the funds remaining unpaid for the reason that Hall had failed to perform in accordance with the terms of the contract. The Georges also filed a plea in abatement to Hall’s suit, alleging that Hall was not entitled to a money judgment against them. This plea was sustained and the Georges were dismissed as defendants. However, the Georges filed a cross action alleging that Hall had failed to construct the residence in accordance with the terms of the contract, and that they were entitled to the remaining funds in the hands of the Association to be used towards the completion of the building.

Thereafter, Hall filed a motion for summary judgment against the Georges. This motion, so far as the Georges were concerned, contained the same allegations relative to the building contract as the allegations contained in Hall’s petition, and the Georges’ affidavits in opposition to the motion contained the same allegations as those contained in their cross action against Hall.

Hall filed amended pleadings wherein it was alleged that he had contracted with certain sub-contractors and such subcontractors had furnished material and services in the construction of the building and that such sub-contractors should receive out of the funds in the hands of the Association the sum actually due each of them, and that the remainder should be paid to Hall. The materialmen and contractors, hereinafter named, intervened claiming they had furnished material and services under their agreement with Hall, and that certain sums were due for material furnished and labor performed in connection with the construction of the George residence. However, these contractors did not file a motion for summary judgment. Clearly the claims of the sub-contractors affected Hall and not the Georges. There existed no privity of contract between these claimants and the Georges.

On October 28, 1960, Hall, the Georges and the Association entered into a stipulation wherein it was agreed that the sum of $9,052.00 was the subject matter of this litigation ; that such sum was the balance due on the Hall-George contract; that the Georges and Hall had made demand for the money, and that such demands were stated in the pleadings of the parties; that the Association had no interest in the subject of the litigation, other than to pay the sum of money in its hands to the parties found by the court to be entitled thereto. It was stipulated that the Association “ * * * shall keep and retain the said funds pending the final termination of this litigation affecting the said sum and will pay the said funds to the parties hereto according to the terms of the final judgment entered in this cause provided, however, no cost shall be assessed against the Association.”

The trial court, without the aid of a jury, sustained the Georges’ plea in abatement and dismissed them as parties defendant. The judgment of the court recites a finding to the effect that the Georges accepted the premises by taking possession thereof on September 7, 1960, and that, therefore, there was no genuine issue of fact as between Hall and the Georges, and that Hall was entitled to judgment as a matter of law. The judgment further relieved Marshall Federal of all liability and established the validity of its lien on the property, denied all relief not expressly granted, and taxed all costs against the Georges.

The judgment awarded the Association the sum of $500.00 as its reasonable attorney’s fees, and ordered the clerk to pay such *877 sum to the Association. In addition thereto the judgment ordered the remaining funds distributed as follows: “D. L. War-britton, $1529.24; W. A. Jeter, $1032.00; W. A. George, $2331.50; Martex Glass Company, $239.69; W. D. Myrick, $300.00; Logan & Whaley Hardware Co., $420.39; Marshall Hardware & Supply Co., $24.50 .and C. M. Pennington, the sum of $325.00, .aggregating the sum of $6,702.32. The •court ordered that the remaining $2,349.68 he paid to W. T. Hall, Jr., and W. T. Hall, III, after the clerk had paid all other sums •above mentioned.” Since, quite clearly, the •Georges and the Halls, by consent, and the trial court, by its action, converted this suit from one by Hall against the Georges and Association to recover the sum of $9,052.00 remaining in the hands of the Association to one for a proper disposition of the funds .accordingly as the issues in the case were ■determined by final judgment, we approach a solution of the question before us just as though the trial court had entered judgment •in favor of Hall for $9,052.00 rather than .the sum of $2,349.68.

Only the Georges appealed from the judgment of the trial court. In the Court of Civil Appeals the Georges attacked that ■part of the trial court’s judgment which •denied them relief on their cross action and .awarded a recovery to Hall and the subcontractors. The Court of Civil Appeals in an unpublished opinion, severed the •cross action, and as to the cause of action there asserted reversed the judgment of •.the trial court and remanded for a trial on the merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Conway v. Saudi Arabian Oil Co.
867 F. Supp. 539 (S.D. Texas, 1994)
Carr v. Norstok Building Systems, Inc.
767 S.W.2d 936 (Court of Appeals of Texas, 1989)
Black Lake Pipe Line Co. v. Union Construction Co.
538 S.W.2d 80 (Texas Supreme Court, 1976)
B & C CONSTRUCTION CO. v. Grain Handling Corp.
521 S.W.2d 98 (Court of Appeals of Texas, 1975)
Guldberg v. Greenfield
146 N.W.2d 298 (Supreme Court of Iowa, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
371 S.W.2d 874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-v-hall-tex-1963.