Carr v. Norstok Building Systems, Inc.

767 S.W.2d 936, 1989 Tex. App. LEXIS 1057, 1989 WL 40575
CourtCourt of Appeals of Texas
DecidedMarch 23, 1989
Docket09-87-168 CV
StatusPublished
Cited by13 cases

This text of 767 S.W.2d 936 (Carr v. Norstok Building Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carr v. Norstok Building Systems, Inc., 767 S.W.2d 936, 1989 Tex. App. LEXIS 1057, 1989 WL 40575 (Tex. Ct. App. 1989).

Opinions

OPINION

BROOKSHIRE, Justice.

An appeal involving the disputed performance and completion of a building contract. The original plaintiff Norstok Building Systems, Inc. (also spelled Norstock), was the prime contractor. Norstok sued Jim Carr d/b/a Jim Carr Motors (Carr) as owner basically for breach of contract in that Norstok alleged that Carr had failed to pay the balance due on the building construction contract. Norstok pleaded that the balance due was $29,597.49 together with legal interest and in addition, a reasonable attorney’s fees of not less than $5,000.00.

Carr by an amended pleading became a cross-plaintiff and pleaded that the construction contract specified that the price for the construction of the new automobile dealership and shop facility was $259,-192.00 and that the final payment on that contract shall be due provided the contract be then fully performed....” Carr further pleaded that Norstok, under the contract, had to re-execute any work that failed to conform with the requirements of the contract and had to remedy any defects due to faulty materials or workmanship which shall appear within a period of one year from the date of the alleged completion of the contract, pleading further that this provision of the construction contract may apply to the work done by the subcontractors as well as to the work done by direct employees of the prime contractor. Carr pleaded that Nor-stok had materially breached the contract in 19 or 20 specific defects, or breaches or failures to properly perform the work. Additionally, Carr said that Norstok had failed to comply with its expressed warranties and implied warranties in the construction of the building because of the serious [939]*939and numerous defects and failures m the construction of the building and, thereafter, Norstok’s failure to cure and correct the same.

Carr also pleaded that Norstok had violated the Texas Deceptive Trade Practices Act, stating that many of the defects and breaches were so serious that Norstok was unable to properly effectuate an acceptable cure. Norstok sued over and against a number of the subcontractors in its third party action naming Armco, Inc., Walter Long d/b/a A & B Plumbing and Construction, DeWitt Heating and Air-Conditioning Company, and Don Russell d/b/a Universal Company.

At a bench trial the judgment was rendered in favor of Norstok to recover money damages from Carr. Carr obtained certain significant offsets. At the conclusion of the bench trial and after a motion for new trial had been overruled by operation of law, the trial court entered its findings of fact and conclusions of law. The judgment in the case, dated May 5, 1987, provided that Norstok recover of and from Carr $21,564.49 plus pre-judgment interest in the amount of $8,736.56, totalling $30,-301.05. Norstok also recovered $6,900.00 from Armco, Inc. Only Carr appeals.

Norstok unequivocably pleaded that it had fully complied with the agreement for the construction and completion of the building. Norstok affirmatively pleaded that it had completed all of the work provided for in the said construction contract in a good and workmanlike manner and that Carr had defaulted in failing to pay for the building as contracted for. From the thrust of the Appellant’s brief, we conclude that the major complaints of Carr, inter alia, were: (1) a substantial sway in the top roof ridgeline wherein the ridgeline had a deflection bowing down from each of the ends of the ridgeline toward the center; (2) an improperly joined rafter column whereby a two-piece metal shim was inserted in the joint at the peak of the roofline; (3) in the construction of an adjoining canopy using materials that were not of Armco design and manufacture; (4) installation of a non-conforming HVAC system of duct-work and non-conforming insulation; and (5) arguing that the most egregious defects were an overwhelming and excessive number of unacceptable defective welds in the structural beams. Carr pleaded, briefed and argued a number of other defects.

Norstok adamantly took the position upon the trial that it had performed 100% of all of the work and that it performed 100% of all the work in all the documents that comprised the construction contract. Norstok did not plead substantial performance or substantial completion of the construction contract. From the pleadings standpoint, Norstok endeavored to recover solely on the basis of complete, 100% performance and never pleaded the equitable theory of recovery by way of substantial performance or substantial compliance with the contract. The trial court’s significant findings of fact, however, found that Norstok merely substantially performed and substantially completed the written agreement. The trial judge failed and declined to make a finding of complete performance for Norstok.

A breach of contract does not occur until one of the contracting parties to the agreement fails to perform an act or a thing that he or she or it has expressly or impliedly promised to do. Crutcher-Rolfs-Cummings, Inc. v. Ballard, 540 S.W.2d 380 (Tex.Civ.App.—Corpus Christi 1976, writ ref’d n.r.e.), cert. denied 433 U.S. 910, 97 S.Ct. 2978, 53 L.Ed.2d 1095 (1977); Foster v. Wagner, 343 S.W.2d 914 (Tex.Civ.App.—El Paso 1961, writ ref’d n.r.e.). The general rule — and the same is well established — is that a party to a contract cannot enforce it or recover damages for its breach unless that party shows that he or she or it has performed the obligations imposed upon him or that he or she has offered to perform them and was able to do so or unless the party shows some valid excuse for failure to perform. Acme Pest Control Co. v. Youngman, 216 S.W.2d 259 (Tex.Civ.App.—Waco 1948, no writ). Nor-stok simply failed and refused to plead the equitable theory of a recovery by way of a substantial performance. There are simply no findings of fact of complete perform-[940]*940anee, the trial court declining to do so. Hence, error occurs since, under this record, Norstok failed to plead substantial performance nor did Norstok prove the elements of substantial performance. The reason the error is reversible is because the trial court judgment is based solely upon the trial court’s finding of substantial performance by Norstok. It is interesting and important to note that the court has a separate finding of fact establishing that 28 or 29 important structural welds needed to be replaced or be repaired and that the reasonable and necessary cost to rectify such defective weld would amount to $200. There are no pleadings of Norstok to sustain the judgment below in its behalf. The judgment must conform to the pleadings.

Appellee invests major reliance on the case of Del Monte Corp. v. Martin, 574 S.W.2d 597 (Tex.Civ.App.—San Antonio 1978, no writ). The reliance is upon the language that a pleading of full performance will support the submission to the jury of the issues of substantial performance. But Del Monte is distinguishable and different. In Del Monte, the court held that the contract required the plaintiff, Martin, to grow a certain type of “fancy grade” spinach which would have been impossible for farmer Martin to grow.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark Young v. Bella Palma, LLC
Court of Appeals of Texas, 2022
Limestone Group, Inc. v. Sai Thong, L.L.C.
107 S.W.3d 793 (Court of Appeals of Texas, 2003)
Moody v. EMC Services, Inc.
828 S.W.2d 237 (Court of Appeals of Texas, 1992)
Nikole, Inc. v. Klinger
603 A.2d 587 (Superior Court of Pennsylvania, 1992)
Escamilla v. Estate of Escamilla
805 S.W.2d 886 (Court of Appeals of Texas, 1991)
Garcia v. Kastner Farms, Inc.
789 S.W.2d 656 (Court of Appeals of Texas, 1990)
Carr v. Norstok Building Systems, Inc.
767 S.W.2d 936 (Court of Appeals of Texas, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
767 S.W.2d 936, 1989 Tex. App. LEXIS 1057, 1989 WL 40575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carr-v-norstok-building-systems-inc-texapp-1989.