Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin

Court of Appeals of Texas·Decided November 2, 2011·No. 10-10-00417-CV·Published

Opinion

IN THE

TENTH COURT OF APPEALS

No. 10-10-00417-CV

CAMP ROOFING LTD, D/B/A CAMP CONSTRUCTION SERVICES, Appellants

v.

PARK SIDE VILLAS I, LLC AND KAREN IRWIN, Appellees

From the 85th District Court Brazos County, Texas

Trial Court No. 07-001984-CV-85

MEMORANDUM OPINION

Camp Roofing Ltd d/b/a Camp Construction Services appeals from an adverse judgment rendered after a jury trial on its breach of contract claim and in favor of Park Side Villas I, LLC and Karen Irwin1 on their breach of contract claim. We affirm in part and reverse in part.

1 These two parties filed a brief together and will be referred to as the single entity, Park Side.

FACTUAL BACKGROUND

Charles Szabuniewicz formed a single-asset entity, Park Side Villas I, LLC, and bought an apartment complex in late 2006. After rejecting a ‚total renovation‛ estimate of $941,383, Park Side contracted with Camp in early 2007 to do some limited renovations on the property for a contract price of $204,000 which included replacing the ‚Hardie‛ board on some exterior portions of the property, renovating the office building for the property, and painting and repairing sheetrock in at least 35 apartment units. According to Park Side, all the renovations were verbally agreed to be completed within 6-8 weeks. Camp’s progress on the project was not satisfactory to Park Side. Park Side paid two draws for $35,000 each to Camp for work-in-progress. When Camp wanted more of its money, Park Side refused due to what it considered was poor workmanship on what had been completed and the failure of Camp to timely renovate the 35 apartment units. Because friction had already been present in their communications, Camp anticipated this action and had filed a mechanic’s lien. Camp then sued Park Side for breach of contract. Park Side filed a counterclaim for breach of contract. After a jury trial, Park Side was awarded a judgment against Camp for $25,488 for breach of contract plus $39,092.51 in attorney’s fees.

Camp brings four issues on appeal. Because it has some bearing on the disposition to Camp’s first issue, we dispose of Camp’s third issue first.

INADEQUATE BRIEFING

In its third issue, Camp asserts that the evidence established Park Side breached the contract with Camp as a matter of law or, in the alternative, the jury’s refusal to find that Park Side breached the contract was against the great weight and preponderance of the evidence. The jury was asked in Question 1 of the jury charge, ‚Did Park Side Villas I, LLC or Camp Construction fail to comply with any agreement or agreements between them?‛ The jury answered ‚No‛ as to Park Side and ‚Yes‛ as to Camp. Camp’s entire argument in its third issue consists of two short paragraphs. No case authority is included in those paragraphs. To present an issue for review, a brief must contain appropriate citations to authorities. TEX. R. APP. P. 38.1(i). Accordingly, this issue is inadequately briefed and presents nothing for review. See id. Camp’s third issue is overruled.

SUBSTANTIAL PERFORMANCE

In its first issue, Camp contends the doctrine of substantial performance was established as a matter of law. By Question 4 of the jury charge, the jury was asked, ‚Do you find that Camp Construction substantially performed its obligations under the agreement, if any?‛ The answer was ‚No.‛ To prove an action for breach of contract, a plaintiff must establish it performed, tendered performance of, or was excused from performing its contractual obligations. Carr v. Norstok Bldg Sys., Inc., 767 S.W.2d 936, 939 (Tex. App.—Beaumont 1989, no writ);

Camp Roofing v. Park Side Page 3

Acme Pest Control Co. v. Youngman, 216 S.W.2d 259, 263 (Tex. Civ. App.—Waco 1948, no writ). "Substantial performance" is the legal equivalent to full performance and means that the essential elements or provisions of a contract have been performed. Anderson v. Vinson Exploration, 832 S.W.2d 657, 666 (Tex. App.—El Paso 1992, writ denied); CraneTex, Inc. v. Precision Crane & Rigging of Houston, Inc., 760 S.W.2d 298 (Tex. App.— Texarkana 1988, writ denied). This is not the same as being excused from performing under the contract. When one party to a contract commits a material breach of that contract, the other party is discharged or excused from further performance. Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004).

The doctrine of substantial performance only excuses contractual deviations or deficiencies which do not severely impair the purpose underlying the contractual provision. Burtch v. Burtch, 972 S.W.2d 882, 889 (Tex. App.—Austin 1998, no pet.). For example, the doctrine allows a contractor who substantially performed a contract to sue on the contract rather than being limited to a cause of action for quantum meruit. Vance v. My Apartment Steak House, Inc., 677 S.W.2d 480, 482 (Tex. 1984). When a contractor substantially performs a building contract, he is entitled to recover the full contract price less the cost of remedying those defects that are remediable. Vance, 677 S.W.2d at 481; Atkinson v. Jackson Bros., 270 S.W. 848, 850 (Tex. Comm'n App. 1925, holding approved); Dietz Memorial Co. v. Texas Steel Bldg. Co., 578 S.W.2d 872, 875 (Tex. Civ. App.—Waco 1979, writ ref'd n.r.e.). Thus, when a breaching contractor brings suit to recover for his substantial performance and the owner alleges remediable defects in the construction, the contractor is required to prove 1) that he did substantially perform, 2) the consideration due him under the contract, and 3) the cost of remedying the defects due to his errors or omissions. Vance v. My Apartment Steak House, Inc., 677 S.W.2d 480, 483 (Tex. 1984).

Camp contends that the evidence and the verdict establish substantial performance as a matter of law. It was Camp’s burden to prove that it substantially performed under the contract. That is, Camp had to prove that it performed the essential provisions of its contract with Park Side. It was undisputed, and Camp even stresses that fact in its brief, that Camp did not complete the interior work of at least 35 units in the apartment complex. Park Side claimed that Camp was to perform the interior work on 37 apartment units. The evidence shows that Camp did not start that part of the renovation project, and had not even hired anyone to begin the work, before it ceased work under the contract because of a payment dispute.2 Whether renovation of the interior of those units was an essential provision of the contract between Camp and Park Side was, for purposes of the trial of the issue of substantial performance, a disputed issue. Park Side presented evidence that it wanted the 35-37 units to have sheetrock repaired and to be painted before the peak renting

2 Park Side’s failure to pay as Camp believed was required was the crux of Camp’s breach of contract claim against Park Side. Camp might have been excused from performing under the contract because of Park Side’s failure to pay, if that failure was a material breach of the contract. However, the jury did not find that Park Side breached the contract.

Camp Roofing v. Park Side Page 5 cycle for the fall semester at Texas A&M University. Camp did not perform that part of the contract. Whether performance of that part of the contract was an essential provision of the contract was for the jury to decide. Accordingly, Camp did not establish as a matter of law the first element-that it performed the essential provisions of its contract-to recover under the doctrine of substantial performance. Camp’s first issue is overruled.

CONFLICTING FINDINGS

Free access — add to your briefcase to read the full text and ask questions with AI

Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin, (Tex. Ct. App. 2011).

Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin (Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
DiGiuseppe v. Lawler
269 S.W.3d 588 (Texas Supreme Court, 2008)
Holland v. Lesesne
350 S.W.2d 859 (Court of Appeals of Texas, 1961)
Dietz Memorial Co. v. Texas Steel Building Co.
578 S.W.2d 872 (Court of Appeals of Texas, 1979)
Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc.
760 S.W.2d 298 (Court of Appeals of Texas, 1988)
Anderson v. Vinson Exploration, Inc.
832 S.W.2d 657 (Court of Appeals of Texas, 1992)
Bradford v. Arhelger
340 S.W.2d 772 (Texas Supreme Court, 1960)
Burtch v. Burtch
972 S.W.2d 882 (Court of Appeals of Texas, 1998)
Carr v. Norstok Building Systems, Inc.
767 S.W.2d 936 (Court of Appeals of Texas, 1989)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Acme Pest Control Co. v. Youngman
216 S.W.2d 259 (Court of Appeals of Texas, 1948)
Little Rock Furniture Manufacturing Co. v. Dunn
222 S.W.2d 985 (Texas Supreme Court, 1949)
Atkinson v. Jackson Bros.
270 S.W. 848 (Texas Commission of Appeals, 1925)