Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin

CourtCourt of Appeals of Texas
DecidedNovember 2, 2011
Docket10-10-00417-CV
StatusPublished

This text of Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin (Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin, (Tex. Ct. App. 2011).

Opinion

IN THE TENTH COURT OF APPEALS

No. 10-10-00417-CV

CAMP ROOFING LTD, D/B/A CAMP CONSTRUCTION SERVICES, Appellants v.

PARK SIDE VILLAS I, LLC AND KAREN IRWIN, Appellees

From the 85th District Court Brazos County, Texas Trial Court No. 07-001984-CV-85

MEMORANDUM OPINION

Camp Roofing Ltd d/b/a Camp Construction Services appeals from an adverse

judgment rendered after a jury trial on its breach of contract claim and in favor of Park

Side Villas I, LLC and Karen Irwin1 on their breach of contract claim. We affirm in part

and reverse in part.

1 These two parties filed a brief together and will be referred to as the single entity, Park Side. FACTUAL BACKGROUND

Charles Szabuniewicz formed a single-asset entity, Park Side Villas I, LLC, and

bought an apartment complex in late 2006. After rejecting a ‚total renovation‛ estimate

of $941,383, Park Side contracted with Camp in early 2007 to do some limited

renovations on the property for a contract price of $204,000 which included replacing

the ‚Hardie‛ board on some exterior portions of the property, renovating the office

building for the property, and painting and repairing sheetrock in at least 35 apartment

units. According to Park Side, all the renovations were verbally agreed to be completed

within 6-8 weeks. Camp’s progress on the project was not satisfactory to Park Side.

Park Side paid two draws for $35,000 each to Camp for work-in-progress. When Camp

wanted more of its money, Park Side refused due to what it considered was poor

workmanship on what had been completed and the failure of Camp to timely renovate

the 35 apartment units. Because friction had already been present in their

communications, Camp anticipated this action and had filed a mechanic’s lien. Camp

then sued Park Side for breach of contract. Park Side filed a counterclaim for breach of

contract. After a jury trial, Park Side was awarded a judgment against Camp for

$25,488 for breach of contract plus $39,092.51 in attorney’s fees.

Camp brings four issues on appeal. Because it has some bearing on the

disposition to Camp’s first issue, we dispose of Camp’s third issue first.

Camp Roofing v. Park Side Page 2 INADEQUATE BRIEFING

In its third issue, Camp asserts that the evidence established Park Side breached

the contract with Camp as a matter of law or, in the alternative, the jury’s refusal to find

that Park Side breached the contract was against the great weight and preponderance of

the evidence. The jury was asked in Question 1 of the jury charge, ‚Did Park Side Villas

I, LLC or Camp Construction fail to comply with any agreement or agreements between

them?‛ The jury answered ‚No‛ as to Park Side and ‚Yes‛ as to Camp. Camp’s entire

argument in its third issue consists of two short paragraphs. No case authority is

included in those paragraphs. To present an issue for review, a brief must contain

appropriate citations to authorities. TEX. R. APP. P. 38.1(i). Accordingly, this issue is

inadequately briefed and presents nothing for review. See id. Camp’s third issue is

overruled.

SUBSTANTIAL PERFORMANCE

In its first issue, Camp contends the doctrine of substantial performance was

established as a matter of law. By Question 4 of the jury charge, the jury was asked,

‚Do you find that Camp Construction substantially performed its obligations under the

agreement, if any?‛ The answer was ‚No.‛

To prove an action for breach of contract, a plaintiff must establish it performed,

tendered performance of, or was excused from performing its contractual obligations.

Carr v. Norstok Bldg Sys., Inc., 767 S.W.2d 936, 939 (Tex. App.—Beaumont 1989, no writ);

Camp Roofing v. Park Side Page 3 Acme Pest Control Co. v. Youngman, 216 S.W.2d 259, 263 (Tex. Civ. App.—Waco 1948, no

writ). "Substantial performance" is the legal equivalent to full performance and means

that the essential elements or provisions of a contract have been performed. Anderson v.

Vinson Exploration, 832 S.W.2d 657, 666 (Tex. App.—El Paso 1992, writ denied);

CraneTex, Inc. v. Precision Crane & Rigging of Houston, Inc., 760 S.W.2d 298 (Tex. App.—

Texarkana 1988, writ denied). This is not the same as being excused from performing

under the contract. When one party to a contract commits a material breach of that

contract, the other party is discharged or excused from further performance. Mustang

Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004).

The doctrine of substantial performance only excuses contractual deviations or

deficiencies which do not severely impair the purpose underlying the contractual

provision. Burtch v. Burtch, 972 S.W.2d 882, 889 (Tex. App.—Austin 1998, no pet.). For

example, the doctrine allows a contractor who substantially performed a contract to sue

on the contract rather than being limited to a cause of action for quantum meruit. Vance

v. My Apartment Steak House, Inc., 677 S.W.2d 480, 482 (Tex. 1984). When a contractor

substantially performs a building contract, he is entitled to recover the full contract

price less the cost of remedying those defects that are remediable. Vance, 677 S.W.2d at

481; Atkinson v. Jackson Bros., 270 S.W. 848, 850 (Tex. Comm'n App. 1925, holding

approved); Dietz Memorial Co. v. Texas Steel Bldg. Co., 578 S.W.2d 872, 875 (Tex. Civ.

App.—Waco 1979, writ ref'd n.r.e.). Thus, when a breaching contractor brings suit to

Camp Roofing v. Park Side Page 4 recover for his substantial performance and the owner alleges remediable defects in the

construction, the contractor is required to prove 1) that he did substantially perform, 2)

the consideration due him under the contract, and 3) the cost of remedying the defects

due to his errors or omissions. Vance v. My Apartment Steak House, Inc., 677 S.W.2d 480,

483 (Tex. 1984).

Camp contends that the evidence and the verdict establish substantial

performance as a matter of law. It was Camp’s burden to prove that it substantially

performed under the contract. That is, Camp had to prove that it performed the

essential provisions of its contract with Park Side. It was undisputed, and Camp even

stresses that fact in its brief, that Camp did not complete the interior work of at least 35

units in the apartment complex. Park Side claimed that Camp was to perform the

interior work on 37 apartment units. The evidence shows that Camp did not start that

part of the renovation project, and had not even hired anyone to begin the work, before

it ceased work under the contract because of a payment dispute.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
DiGiuseppe v. Lawler
269 S.W.3d 588 (Texas Supreme Court, 2008)
Holland v. Lesesne
350 S.W.2d 859 (Court of Appeals of Texas, 1961)
Dietz Memorial Co. v. Texas Steel Building Co.
578 S.W.2d 872 (Court of Appeals of Texas, 1979)
Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc.
760 S.W.2d 298 (Court of Appeals of Texas, 1988)
Anderson v. Vinson Exploration, Inc.
832 S.W.2d 657 (Court of Appeals of Texas, 1992)
Bradford v. Arhelger
340 S.W.2d 772 (Texas Supreme Court, 1960)
Burtch v. Burtch
972 S.W.2d 882 (Court of Appeals of Texas, 1998)
Carr v. Norstok Building Systems, Inc.
767 S.W.2d 936 (Court of Appeals of Texas, 1989)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Acme Pest Control Co. v. Youngman
216 S.W.2d 259 (Court of Appeals of Texas, 1948)
Little Rock Furniture Manufacturing Co. v. Dunn
222 S.W.2d 985 (Texas Supreme Court, 1949)
Atkinson v. Jackson Bros.
270 S.W. 848 (Texas Commission of Appeals, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
Camp Roofing LTD, D/B/A Camp Construction Services v. Park Side Villas I, LLC and Karen Irwin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camp-roofing-ltd-dba-camp-construction-services-v--texapp-2011.