Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc.

760 S.W.2d 298, 1988 Tex. App. LEXIS 2441, 1988 WL 96932
CourtCourt of Appeals of Texas
DecidedSeptember 13, 1988
Docket9617
StatusPublished
Cited by24 cases

This text of 760 S.W.2d 298 (Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc., 760 S.W.2d 298, 1988 Tex. App. LEXIS 2441, 1988 WL 96932 (Tex. Ct. App. 1988).

Opinion

GRANT, Justice.

Cranetex, Inc. (hereinafter referred to as Cranetex) brings a limited appeal complaining only of the trial court’s discharge of Northwest Acceptance Corporation (hereinafter referred to as Northwest) from liability. A suit was brought by Cranetex for repairs made to a crane belonging to Precision Crane & Rigging of Houston, Inc. (hereinafter referred to as Precision Crane) and mortgaged to Northwest.

Cranetex contends that the trial court erred (1) in holding that a letter agreement among the parties did not bind Northwest contractually to pay insurance proceeds to Cranetex; (2) in making erroneous conclusions of law which were contrary to its findings of fact; and (3) in finding no liability on the part of Northwest when there were no proper conclusions of law to support this outcome.

Northwest raises three cross-points contending that the trial court erred (1) in making a conclusion of law and finding of fact that Cranetex sold the crane at public auction in substantial compliance with the Property Code; (2) in reaching a conclusion of law that the debt owing to Cranetex accrued as of June 20, 1984; and (3) in failing to make a finding that repairs to the crane were not completed by Cranetex to the satisfaction of both Precision Crane and Northwest pursuant to the January 17, 1984, letter agreement.

Cranetex argues that Northwest is precluded from bringing these cross-points because of the limited appeal. To the extent, however, that these cross-points tend to support Northwest’s position that the trial court properly entered a take-nothing judgment against them, the cross-points will be considered on appeal. Whataburger, Inc. v. Rutherford, 642 S.W.2d 30 (Tex.App.—Dallas 1982, no writ); Smith v. Texas Improvement Co., 570 S.W.2d 90 (Tex.Civ.App.—Dallas 1978, no writ).

A crane owned by Precision Crane and subject to a purchase-finance lien held by Northwest, was damaged in an accident. Precision Crane carried accident insurance, and the insurance carrier paid Northwest $86,386.84 to hold in escrow as compensation for the damage. Cranetex submitted a bid to repair the crane for $100,520.05, which was accepted. On January 17, 1984, Bill Hall, vice-president and regional manager of Northwest, wrote a letter to Precision Crane and stated the following:

This letter acknowledges the receipt of a insurance draft in the amount of $86,-386.84 to be employed in the repair of One (1) P & H model T-750 75 ton hydraulic crane, s/n 44243 complete. Northwest Acceptance Corporation agrees that upon collection of those funds and completion of said repairs to the satisfaction of Northwest Acceptance Corporation and Precision Crane and Rigging of Houston, Inc., that the sum of $86,386.84 will be paid directly to Cranetex, Inc., the party that will be performing those repairs. Precision Crane and Rigging of Houston, Inc. agrees to remit certified funds to Crane-tex, Inc., for any repairs or charges in excess of the insurance draft, prior to taking possession of the crane.

At the bottom of the letter under the terms “AGREED TO AND ACCEPTED BY” agents for Precision Crane and Crane-tex signed on behalf of those parties.

Cranetex repaired the damage and submitted a bill of $105,330.05. (This included some work in addition to the work covered *301 by the original bid.) Precision Crane claimed that the repairs were not performed adequately and refused to authorize payment of the insurance proceeds.

Crane Service and Certification, Inc. inspected and certified the crane on July 23, 1984. A more detailed report was completed by that company on July 24, 1984.

Cranetex sold the crane at public auction for $55,000. Cranetex then brought suit for the unpaid remainder of its repair bill. In a trial before the court, Cranetex took judgment against Precision Crane for a $47,500 deficiency, and Northwest was discharged.

Cranetex contends that the trial court erred in making the following conclusion of law:

The Letter Agreement dated January 17, 1984, attached hereto as Exhibit “B” did not bind Northwest to pay insurance proceeds to Cranetex.

If this conclusion of law means that Northwest had no contractual obligation to pay the insurance proceeds when Cranetex performed, it appears to conflict with the following findings of fact by the trial court:

CRANETEX, PRECISION CRANE, and NORTHWEST entered into a letter agreement for repairs of the crane and payment therefore (sic) dated January 17, 1984, which was admitted into evidence at trial as Plaintiffs Exhibit 1. NORTHWEST agreed to hold insurance proceeds in the sum of $86,386.84 for the benefit of CRANETEX and PRECISION CRANE which sum would be paid on the repair costs to CRANETEX upon satisfactory completion of repairs to the crane.

Findings of fact control over conflicting conclusions of law. Gary Safe Co. v. A.C. Andrews Co., 568 S.W.2d 166, 168 (Tex.Civ.App.—Dallas 1978, writ ref’d n.r.e.). Northwest contends that it was not bound by the letter agreement because there was no consideration for the agreement.

The trial court did not address consideration in its findings of fact. Northwest held an equitable ownership right in the crane; therefore, it was to Northwest’s benefit that the crane be repaired. Cranetex agreed to make the repairs on the condition that all insurance proceeds would be available to pay a portion of the cost of repairs. Cranetex’s agreement to make the repairs was sufficient consideration to bind Northwest to pay insurance proceeds to Cranetex as specified in the letter agreement. Mutual reciprocal obligations are sufficient to constitute a binding contract. Texas Gas Utilities Co. v. Barrett, 460 S.W.2d 409 (Tex.1970).

The trial court entered two conclusions of law that also conflict with the conclusion that the letter agreement did not bind Northwest to pay the insurance proceeds to Cranetex:

The letter agreement between CRANE-TEX, PRECISION CRANE, and NORTHWEST, which was admitted into evidence as Plaintiffs Exhibit 1 constituted a contract for the payment of the repairs to the crane made the basis of this lawsuit. (Emphasis added)
By entering into the contract admitted into evidence as Plaintiffs Exhibit 1, NORTHWEST agreed to hold the insurance proceeds in the sum of $86,386.84 in escrow to be paid over to CRANETEX upon completion of the repairs satisfactory to PRECISION CRANE and NORTHWEST ACCEPTANCE. (Emphasis added)

Both of these conclusions of law indicate that the letter agreement was a contract to which Northwest was bound; therefore, the trial court erred in entering a conclusion to the contrary.

The remaining two points of error urge that the trial court erred in discharging Northwest from liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chappell Hill Bank v. Lane Bank Equipment Co.
38 S.W.3d 237 (Court of Appeals of Texas, 2001)
Dob's Tire & Auto Center v. Safeway Insurance Agency
923 S.W.2d 715 (Court of Appeals of Texas, 1996)
Lynx Exploration and Production Co. v. 4-Sight Operating Co.
891 S.W.2d 785 (Court of Appeals of Texas, 1995)
Sassen v. Tanglegrove Townhouse Condominium Ass'n
877 S.W.2d 489 (Court of Appeals of Texas, 1994)
Watkins v. Williamson
869 S.W.2d 383 (Court of Appeals of Texas, 1993)
Amfac, Inc. v. Waikiki Beachcomber Investment Co.
839 P.2d 10 (Hawaii Supreme Court, 1992)
Anderson v. Vinson Exploration, Inc.
832 S.W.2d 657 (Court of Appeals of Texas, 1992)
Hutton v. Monograms Plus, Inc.
604 N.E.2d 200 (Ohio Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
760 S.W.2d 298, 1988 Tex. App. LEXIS 2441, 1988 WL 96932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cranetex-inc-v-precision-crane-rigging-of-houston-inc-texapp-1988.