Pollock v. Pennsylvania Iron Works Co.

34 N.Y.S. 129, 13 Misc. 194, 68 N.Y. St. Rep. 215
CourtNew York Court of Common Pleas
DecidedJune 3, 1895
StatusPublished
Cited by3 cases

This text of 34 N.Y.S. 129 (Pollock v. Pennsylvania Iron Works Co.) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pollock v. Pennsylvania Iron Works Co., 34 N.Y.S. 129, 13 Misc. 194, 68 N.Y. St. Rep. 215 (N.Y. Super. Ct. 1895).

Opinion

BOOKSTAVER, J.

This action was brought to recover for extra work done by respondent for the appellant. The plaintiff contracted with the defendant to do certain work in the Broadway cable power house in this city, under written specifications. This work consisted of the furnishing and erecting of all pipes, valves, fittings, and materials necessary for the operations of the boilers, engines, heaters, and pumps in the power house. The alleged extra work consisted in furnishing certain tees, elbows, and crosses of special design, drawings for which were furnished by defendant’s engineer in charge of the work. The specifications called for two kinds of fittings, viz. heavy cast-iron tees for one part of the work, and in another part for fittings provided with “extra heavy flanges of a design to be submitted and approved, with bolt bosses extending their full depth.” Plaintiff furnished the fittings with the extra heavy flanges, and, under the specification for heavy cast-iron tees, furnished the standard or commercial heavy cast-iron tees, as the jury have found. These, however, were rejected by defendant’s engineer, Mr. Moore, and thereafter lie furnished a special design for these tees; and for the difference in cost between these special fittings and the commercial fitings, namely, $425.96, and interest, this action is brought. The difference in the cost of the two styles of fittings was not [130]*130disputed, and the case was sent to the jury on the question whether the fittings first furnished by the plaintiff were those required by the contract. The whole controversy turns upon the interpretation to be given to this part of the contract between the parties. The appellant contends that Mr. Moore, defendant’s engineer, in charge of the work, and Mr. Grist, the general manager of appellant, had, under the provisions of the contract, exclusive right to determine the construction and meaning of the specifications, as well as the steamfitting drawings; that, by the terms of the contract, these questions were all referred for conclusive determination to these men; and that plaintiff could not withdraw the decision of such questions from them, and refer them to the determination of a court,—citing Smith v. Brady, 17 N. Y. 176. The provisions of the contract upon which this contention rests are as follows:

“Finally, it is furthermore expressly understood that these specifications and drawings are not to be used to the exclusion of the instructions and directions of the engineer of the Pennsylvania Iron Works Company in charge, but jointly with them. * * * The work, when finished, shall be subject to the acceptance of the general manager of the Pennsylvania Iron Works Company and the chief engineer of the Broadway and Seventh Avenue Railroad Company, * * * whose acceptance will be the final acceptance of the Pennsylvania Iron Works Company.
“Note: The interpretation and the full intent of the herein mentioned steamfitting drawings, etc., shall be given by the engineer of the Pennsylvania Iron Works Company in charge, and his decision pertaining to any question which may arise shall be conclusive.”

The first criticism on these provisions is that, by the terms of the contract, the conclusiveness of the interpretation of the engineer extends only to the “steam-fitting drawings,” etc., and not to the “specifications,” as is apparent from the sequence of the various clauses quoted and their punctuation. And the next criticism is that the stipulation in the contract is a very rigid and dangerous one; it puts a power in the hands of one party, which may be wielded very harshly and severely against the other; and we ought not to construe it with any unnecessary liberality in favor of one who possesses it. McKenzie v. Decker, 94 N. Y. 650.

In regard to the interpretation of such contracts, the court of appeals has said:

“Where there is doubt or uncertainty as to the meaning of words or phrases used in a contract, in seeking for the intent of the parties as evidenced by the words used, the fact that a construction contended for would make the contract unreasonable, and place one of the parties entirely at the mercy of the other, may properly be taken into consideration.” Russell v. Allerton, 108 N. Y. 288, 15 N. E. 391.

Again, these provisions are only another form of the usual clause in building contracts to- the effect that the work shall be done to the satisfaction of the architect, and shall be subject to his acceptance. This court has held that the “satisfaction” is a legal satisfaction, and that an architect cannot capriciously and willfully refuse to be satisfied; that, if the work has been performed substantially in accordance with the contract, the architect ought to be satisfied, and the law will hold that he is satisfied. Hopper v. Cutting (Com. Pl. N. Y.) 13 N. Y. Supp. 820; Byron v. Bell (Com. [131]*131Pl. N. Y.) 10 N. Y. Supp. 693; Highton v. Dessau (Com. Pl. N. Y.) 19 N. Y. Supp. 395; McCarthy v. Gallagher, 4 Misc. Rep. 188, 23 N. Y. Supp. 884; Boiler Co. v. Garden, 101 N. Y. 387, 4 N. E. 749; Nolan v. Whitnev, 88 N. Y. 648; Bowery Nat. Bank v. Mayor, etc., 63 N. Y. 336; Doll v. Noble, 116 N. Y. 230, 22 N. E. 406. In the case under consideration the contract did not require the plaintiff to procure a certificate as a condition precedent, and hence there was no necessity of pleading an excuse for its nonproduction.

The appellant, however, contends that, notwithstanding the law-on the subject, the question at issue in this case had been voluntarily submitted to the arbitration of defendant’s general manager, Mr. Grist, and Mr. McNulty, the engineer of the Broadway & Seventh Avenue Railroad Company. We think, however, that it is clear from the testimony, and the jury rightly found, there was no vol untary submission to arbitration, but there was a demand that these engineers should declare themselves satisfied, and accept what plaintiff claimed was the fulfillment of the requirements of the contract.

Appellant also contends that the engineer was the sole arbitrator as to what was required by the specifications. But such a contention is fully answered by the authorities we have cited, and the contract itself refutes the claim, for it declares that the determination of the engineer is conclusive only when a question arises over the interpretation of the “steam-fitting drawings,” etc. As to the specifications, the provision is that they shall not be used to the exclusion of the instructions of the engineer. The authorities cited by the appellant in support of its contention are not in point. In Butler v. Tucker, 24 Wend. 449, the question was solely one of pleading; and in Wiberly v. Matthews, 91 N. Y. 648, it relates to voluntary submission to arbitrators, while in Zimmerman v. Lutheran Church, 11 Misc. Rep. 49, 31 N. Y. Supp. 845, the architect’s certificate had been given, and the owner claimed that it was erroneous, but did not charge a mistake or bad faith. If appellant’s contention were well founded, the engineer could as well have demanded a 20-inch pipe where a 14-inch pipe was called for, with correspond- • ing fittings, throughout the whole plant, and thus have enabled him to double or treble the cost of the work. It cannot be possible that such a right was intended by the parties to be given to the engineer, but that the true interpretation of it is that the powers granted to him were for the purpose of requiring a compliance with the terms of the contract, and not to enable him to alter those terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cranetex, Inc. v. Precision Crane & Rigging of Houston, Inc.
760 S.W.2d 298 (Court of Appeals of Texas, 1988)
Raw Silk Trading Co. v. Katz
201 A.D. 713 (Appellate Division of the Supreme Court of New York, 1922)
Pollock v. Pennsylvania Ironworks Co.
35 N.Y.S. 1115 (New York Court of Common Pleas, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
34 N.Y.S. 129, 13 Misc. 194, 68 N.Y. St. Rep. 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pollock-v-pennsylvania-iron-works-co-nyctcompl-1895.