Dietz Memorial Co. v. Texas Steel Building Co.

578 S.W.2d 872, 1979 Tex. App. LEXIS 3316
CourtCourt of Appeals of Texas
DecidedMarch 8, 1979
Docket5943
StatusPublished
Cited by9 cases

This text of 578 S.W.2d 872 (Dietz Memorial Co. v. Texas Steel Building Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dietz Memorial Co. v. Texas Steel Building Co., 578 S.W.2d 872, 1979 Tex. App. LEXIS 3316 (Tex. Ct. App. 1979).

Opinion

HALL, Justice.

Plaintiff-appellee Texas Steel Building Company and defendant-appellant Dietz Memorial Company entered into a written contract under which plaintiff agreed to provide the material and labor and make certain repairs and improvements to defendant’s metal building. Plaintiff was required among other duties to “furnish and install white acoustical spray insulation to the entire roof, walls, and all red iron, except crane beams, rails and columns, of [defendant’s] plant building to a minimum thickness of ½-inch throughout the job” and to “clean and wash down all plastic panel skylights in building.” The total contract price was $14,266.00. Plaintiff performed under the contract. Defendant paid $2,926.00, but refused to make further payment. Plaintiff brought this suit for the balance of $11,340.00, alleging it had performed its obligations under the contract. Plaintiff also pleaded for reasonable attorneys’ fees.

Defendant answered with a general denial, a special denial, and a counterclaim, alleging that plaintiff had subcontracted the insulation work and the skylight cleaning job to E. O. Wood Company; that the work performed by the subcontractor was not done in a good and workmanlike manner and was defective; that the installed insulation deviated from the contract in many pleaded particulars including that it was loosely applied and did not adhere firmly enough to the building to prevent it from falling off the roof, walls, and red iron, and from being knocked off upon any reasonable contact; and that the skylights were not cleaned and washed down in accordance with the contract. Defendant alleged that proper correction of the deficiencies and defects in the work performed by plaintiff and its subcontractor would necessitate removal of the existing insulation, cleaning of the surfaces, application of a base coat of adhesive, and then reapplication of the insulation; and that the cost of such work would be $18,886.62. Defendant prayed for the recovery of $7,546.62 (the difference between the cost of the asserted remedial work and the balance due on the contract), and for reasonable attorneys’ fees.

Plaintiff answered defendant’s counterclaim with a general denial. Plaintiff also impleaded its subcontractor E. O. Wood Company and, alleging an indemnity agreement between them, prayed for judgment against the subcontractor for any recovery by defendant against plaintiff.

The case was tried to a jury. Defendant conceded during the trial it was not complaining about the cleaning of the skylights. Excepting proof on attorneys’ fees, the single issue developed on the trial was whether the insulation work was properly performed by plaintiff’s subcontractor. Plaintiff’s witnesses testified that the work was done *874 in a good and workmanlike manner; defendant’s witnesses testified that it was not.

During the trial plaintiff asked two of its witnesses whether the contract was “substantially completed.” Defendant objected to the question on both occasions on the ground that evidence of substantial performance was not supported by the pleadings because plaintiff had alleged and sued only on a completed contract. The objections were overruled, and both witnesses answered the questions favorably to plaintiff. After the parties had rested their proof, but before the case went to the jury, plaintiff was permitted over defendant’s objection to file a trial amendment pleading substantial performance.

Related to this appeal, the jury made the following answers to the special issues:

No.l: Failed to find that plaintiff “fully performed its obligations under the contract in question in a good and workmanlike manner.”
No. 2: Found that plaintiff “substantially performed its obligations under the contract.”
No. 5: Found that “the reasonable cost of remedying [the] defects or omissions in [plaintiff’s] material and workmanship in performing [the] contract” was “NONE.”

Judgment was rendered on the verdict awarding plaintiff $11,340.00 (the unpaid balance on the full contract price), and prejudgment interest on that amount. Apparently upon a stipulation not of record, plaintiff was also awarded attorneys’ fees.

Defendant appeals. We affirm the judgment.

Defendant’s two grounds for reversal are (1) that the court erred in permitting plaintiff to file the trial amendment, pleading substantial performance, on the last day of the trial; and (2) that the court erred “in awarding judgment for plaintiff for the full balance due on the contract, when the jury found that the contract had only been substantially performed.”

A party suing upon a completed building or construction contract may recover upon proof of only substantial performance of the contract. Linch v. Paris Lumber & Grain Elevator Co., 80 Tex. 23, 15 S.W. 208, 213 (1891); Atkinson v. Jackson Bros., 270 S.W. 848, 851 (Tex.Com.App. 1925, holding approved); Pacific Coast Engineering Co. v. Trinity Const. Co., 410 S.W.2d 797, 799 (Tex.Civ.App.—Waco 1967, writ ref’d n. r. e.); 10 Tex.Jur.2d 25, Building Contracts § 21. It follows, therefore, that the court did not err in permitting plaintiff to expressly plead substantial performance by trial amendment after the proof had ended. The pleading was unnecessary and no harm could have been caused defendant by it. See, especially, Pacific Coast Engineering Co. v. Trinity Const. Co., supra.

Additionally, the allowance or not of a trial amendment is addressed to the sound discretion of the trial court; and the question of whether the court’s ruling was an abuse of discretion must be determined from a review of the entire record of the case. Vermillion v. Haynes, 147 Tex. 359, 215 S.W.2d 605, 609 (1948); Aubin v. Hunsucker, 481 S.W.2d 952, 955 (Tex.Civ.App.—Austin 1972, writ ref’d n. r. e.). In our case, it was plaintiff’s position before the jury that the insulation work was fully performed in a proper and workmanlike manner. It was defendant’s position that the work was poorly done; and that the insulation applied by plaintiff’s subcontractor would have to be completely removed and new insulation installed at the cost of $18,-887.62. When the parties ended their proof, they had established in great detail their respective assertions of what had been done and what had not been done by the subcontractor on the insulation job. Excluding the previously mentioned answers to plaintiff’s witnesses permitted over defendant’s objection, the evidence adduced by the parties would have supported findings of (1) full and proper performance of the insulation work or (2) wholly improper performance; and (3) stages of completion between those extremes, including substantial performance. With the record in that state, *875 we hold the court did not abuse its discretion in permitting the trial amendment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chappell Hill Bank v. Lane Bank Equipment Co.
38 S.W.3d 237 (Court of Appeals of Texas, 2001)
Weitzul Construction, Inc. v. Outdoor Environs
849 S.W.2d 359 (Court of Appeals of Texas, 1993)
Ambassador Development Corp. v. Valdez
791 S.W.2d 612 (Court of Appeals of Texas, 1990)
Skaggs v. Guerra
704 S.W.2d 51 (Court of Appeals of Texas, 1985)
Transworld Drilling Co. v. Levingston Shipbuilding Co.
693 S.W.2d 19 (Court of Appeals of Texas, 1985)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
578 S.W.2d 872, 1979 Tex. App. LEXIS 3316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dietz-memorial-co-v-texas-steel-building-co-texapp-1979.