Ambassador Development Corp. v. Valdez

791 S.W.2d 612, 1990 Tex. App. LEXIS 1733, 1990 WL 98740
CourtCourt of Appeals of Texas
DecidedJune 14, 1990
Docket2-88-009-CV
StatusPublished
Cited by16 cases

This text of 791 S.W.2d 612 (Ambassador Development Corp. v. Valdez) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ambassador Development Corp. v. Valdez, 791 S.W.2d 612, 1990 Tex. App. LEXIS 1733, 1990 WL 98740 (Tex. Ct. App. 1990).

Opinion

OPINION

MEYERS, Justice.

Appellee and appellant Ambassador Development Corporation (“Ambassador”) entered into two written contracts whereby appellee, as subcontractor, agreed to perform work for Ambassador, the general contractor of a real estate construction project, on behalf of appellant Opus I, Ltd. (“Opus”), the owner of the Lewisville Business and Self-Storage Park. In the first contract, dated December 18, 1985, the parties contracted for “Excavation of site work and construction of building pads in accordance with plans and specifications” to be provided by appellee for the sum of $94,000. Soon thereafter, on February 6, 1986, the parties contracted for “completion of all concrete foundations, concrete paving, retaining walls, and tilt wall, including forms and rebar” for the amount of $594,850. Additionally, it is undisputed that appellants subsequently requested ap-pellee to perform extra work which was not included in the concrete contract. When appellee was not paid in full for this additional work, he filed suit against Ambassador asserting a claim for the unpaid amount. Appellee also sought judicial foreclosure of a mechanic’s and material-man’s lien filed against the real property owned by Opus. Ambassador counterclaimed for defective and incomplete concrete work, and defective earthwork. Opus counterclaimed for cancellation of the asserted lien.

The jury found that appellee substantially performed his obligations for concrete work, he did not fail to perform all earthwork under his contract in a good and workmanlike manner, and appellants did not incur any costs in repairing or remedying appellee’s concrete work. The jury further responded that appellee’s concrete contract price plus authorized “extras” was $698,193.49, and that appellants had paid appellee and his suppliers $613,333.62. The court entered judgment on the verdict in favor of appellee against Ambassador in the amount of $85,859.87, 1 plus $5,151.59 prejudgment interest, and entered judgment against Opus for foreclosure of appel-lee’s mechanic’s and materialman’s lien in the amount of $91,011.46.

We affirm that portion of the trial court’s judgment which awards appellee $91,011.46 in damages against Ambassador. We modify that portion of the judgment which imposes, and orders foreclosure on, a statutory mechanic’s and ma-terialman’s lien on the property of Opus, so as to delete the $5,151.59 award of prejudgment interest from the amount of the lien. Lastly, we remand the cause to the trial court on the sole issue of the amount, if any, Opus is entitled to recover as attorney’s fees attributable to defending appel-lee’s claim that prejudgment interest should be included in the amount of the statutory lien. As modified, the remainder of the judgment is affirmed.

APPELLANTS’ CONTENTIONS

Appellants have raised twenty points of error contending: the jury’s findings of “none” for costs of completion and correction cannot support a judgment for substantial performance; the jury’s findings of substantial performance and zero costs of *615 completion and correction are in fatal conflict; there was no evidence, or alternatively insufficient evidence, to support the jury’s findings of substantial performance, the zero costs of completion, the zero costs of correction, the amount of any trapped funds, and the amount of any statutory retainage share; the evidence established as a matter of law that $632,885.28 (as opposed to the jury’s finding of $613,-333.62) was the total amount previously paid to appellee; appellee failed to perform all earthwork in a good and workmanlike manner, or alternatively the jury’s findings to the contrary were against the great weight and preponderance of the evidence; evidence concerning an alleged oral modification of the concrete subcontract was erroneously admitted; and any lien claim of appellee’s cannot exceed the amount of any trapped funds plus any statutory retainage share.

Substantial Performance

In their first and second points of error, appellants contend the trial court erred in entering judgment for appellee and for lien foreclosure, claiming: the jury’s findings of “none” for costs of completion and correction cannot support the judgment on a substantial performance claim; and the finding of substantial performance is in fatal conflict with the findings of zero costs of completion and correction. Basically, appellants assert that appellee’s failure to secure jury findings of specific monetary amounts regarding the costs of correction and completion, constitutes a failure of proof of the substantial performance claim and appellee should take nothing with respect to such claim. The charge instructed the jury that “ ‘substantial performance’ means performance of the essential elements of a contract, provided that the defects in performance do not prevent the parties from accomplishing the purpose of the contract.”

Appellee maintains he met his burden of proof under his substantial performance cause of action, and the jury’s zero answers to costs of completion and correction of defects are not in conflict with the jury’s finding of substantial performance by ap-pellee. Appellee’s theory is that any costs allegedly incurred by appellants in completing or correcting the work in question were: (a) not attributable to appellee’s work; (b) so trivial as to require no additional expenses; and (c) not true costs under appellee’s subcontract, and the jury rightfully did not charge these costs to appellee.

Appellants place primary reliance upon Vance v. My Apartment Steak House, Etc., 677 S.W.2d 480 (Tex.1984). In that case the Texas Supreme Court restated the well-established Texas rules concerning the measure of damages in a building contract dispute: (1) When a contractor has substantially performed a building contract, he is entitled to recover the full contract price less the cost of remedying those defects that are remediable; (2) the measure of damages for an owner when a contractor is alleged to be in breach of a construction contract is the cost of completing the job or of remedying those defects that are remediable; and (3) if only part of the contract price has been paid to the contractor, the amount of the owner’s damages is credited against the balance of his payments still unpaid. Id. at 481-82. The court further discussed the doctrine of substantial performance, stating:

The Atkinson [Atkinson v. Jackson Bros., 270 S.W. 848, 850 (Tex.Comm’n App.1925, holding approved)] court correctly stated that the doctrine of substantial performance is merely an equitable doctrine that was adopted to allow a contractor who has substantially completed a construction contract to sue on the contract rather than being relegated to his cause of action for quantum meruit. The doctrine does not, however, permit the contractor to recover the full consideration provided for in the contract. By definition, this doctrine recognizes that the contractor has not totally fulfilled his bargain under the contract — he is in breach. Nonetheless, he is allowed to sue on the contract, but his recovery is decreased by the cost of remedying those defects for which he is responsible. “To allow full recovery without deductions for defects is to *616 award compensation for something [the contractor has] not done.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
791 S.W.2d 612, 1990 Tex. App. LEXIS 1733, 1990 WL 98740, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ambassador-development-corp-v-valdez-texapp-1990.