M.S. Foundations, Inc. v. Perma-Crete Building Systems, Inc.

666 S.W.2d 568, 1984 Tex. App. LEXIS 4908
CourtCourt of Appeals of Texas
DecidedJanuary 19, 1984
DocketB14-83-053CV
StatusPublished
Cited by2 cases

This text of 666 S.W.2d 568 (M.S. Foundations, Inc. v. Perma-Crete Building Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.S. Foundations, Inc. v. Perma-Crete Building Systems, Inc., 666 S.W.2d 568, 1984 Tex. App. LEXIS 4908 (Tex. Ct. App. 1984).

Opinion

OPINION

ROBERTSON, Justice.

This is an appeal from a take nothing judgment rendered on motions for directed verdict. At issue in this appeal is the propriety of such action by the trial court. We affirm.

Badger, Emmanouil, and McDaniel, hereinafter referred to as “owners,” contracted with Perma-Crete to construct a building on owners’s property. The financing agent was Texas Commerce Bank — Lakeside, hereinafter referred to as “bank.” M.S. Foundations, hereinafter referred to as appellant, a subcontractor of Perma-Crete, entered into two contracts with Perma-Crete to do certain concrete work. Work under the first contract was completed and appellant was paid. The second contract, totalling some $28,000, was for concrete paving around the building. Appellant was not paid under this contract, and that is the basis of this suit. In 1980, prior to the trial against the owners and the bank in 1982, an agreed interlocutory judgment was entered in favor of appellant and against Perma-Crete. Appellant proceeded to trial on its sixth amended petition alleging: (1) liability of the owners in quantum meruit; (2) estoppel by owners to assert limitations on their liability; (3) foreclosure of statutory and constitutional materialman’s lien; (4) “civil conspiracy and interference” with contract between appellant and Perma-Crete; and (5) “breach of contract by [bank] ... and civil conspiracy between [bank] and owners to deny rights of [appellant].”

In ten of appellant’s eleven points of error, it asserts there was sufficient evidence to support its cause of action, and therefore, the action of the court in granting a directed verdict in favor of appellees was error. Appellant correctly recognizes that “for the trial court’s ruling to be correct, as to each theory of recovery asserted by [appellant], there must be at least one fact proposition, constituting a component element ... as to which the plaintiff’s evidence is so meagre ... that reasonable men could not differ as to the conclusion that such proposition is not established,” citing Mumphord v. First Victoria National Bank, 605 S.W.2d 701 (Tex.Civ.App. —Corpus Christi 1980, no writ). Appellant also correctly recognizes the rule this court must follow in reviewing the propriety of the trial court action, i.e. we must “view the evidence in the light most favorable to appellant, the losing party in the trial court, to indulge against the judgment every inference that can be possibly drawn from the evidence, and to disregard all evidence and inferences adverse to Appellant,” citing Rogers v. Searle, 533 S.W.2d 433 (Tex.Civ.App. — Corpus Christi), rev’d on other grounds, 554 S.W.2d 114 (Tex. 1976). Finally, in addressing appellant’s evidentiary points, it is appropriate to recognize the general rule that “if the probative force of evidence be so weak that it raises only a surmise or suspicion of the existence of the fact sought to be established, that evidence in legal contemplation is no evidence at all and will not support a finding which comprehends the existence of a disputed fact.” Hamilton v. Newbury, 412 S.W.2d 801 (Tex.Civ.App. — Dallas 1967, writ ref’d n.r.e.).

In its first point, appellant contends the trial court erred in granting a directed verdict because there was ample evidence to support the cause of action alleged that the owners are liable to M.S. Foundations, Inc., under the Mechanics and Materialman’s lien statutes. In argument under this point, it appears to be appellant’s conten *571 tion on appeal that it was entitled to a lien against the owners’ property for its pro-rata share of the lien claimant’s fund of ten percent (10%) of the contract price which is required to be retained by the owners in accordance with TEX.REV.CIV.STAT. ANN. art. 5469 (Vernon Supp. 1982-1983). So far as we are able to determine from the record, this issue was never presented to the trial court. Appellant’s petition sought only to establish and foreclose on the lien in the total amount of $28,310, and it did not plead alternatively for the amount of $19,014.60 which was 10% of the total contract price.

In the owners’ second amended answer, they specifically pled they had “met all their obligations under their contract with Perma-Crete Building Systems, Inc. particularly with regard to setting aside or holding back the proper amount of retain-age with regard to sub-contractors,” and asserted “any recovery due Plaintiff as relating to defendants is limited to the said retainage, and the amount of Plaintiff’s lien filed pursuant to said foundational work.” We agree that if appellant had made the proper proof, it would have been entitled to recover from appellee owners a portion of the money owed it by the general contractor (Perma-Crete), limited by 10% of the contract price or its pro-rata portion thereof. McKalip v. Smith Building & Masonry Supply, Inc., 599 S.W.2d 884 (Tex.Civ.App. — Waco 1980, writ ref’d n.r. e.). However, since this issue was not raised in the trial court, appellant is not in position to now complain for the first time on appeal. Greater Fort Worth and Tarrant County Community Action Agency v. Mims, 627 S.W.2d 149 (Tex.1982). While it is true the judgment contains the following finding:

Plaintiff introduced no evidence to raise any issue that Defendants Warren Badger, A.Z. Emmanouil and W.W. McDaniel are liable to the Plaintiff for any sum of money other than the statutory percentage held by them as retainage to satisfy liens (emphasis ours)

and in appellant’s response to defendant’s motion for judgment, it objected because the judgment made “no provision for judgment or execution” for the amount of re-tainage, we hold this does not preserve the matter for our review. The point is one of evidence, and there was no evidence before the court upon which appellant’s pro rata share of the retainage could be determined. We hold that in the absence of proof by the lien claimant of the amount of the retain-age to which it was entitled, the court could not make provision for its recovery from such retainage fund. Its first point of error is overruled.

In its second point, appellant contends it was error for the trial court to grant the instructed verdict because there was ample evidence to support its cause of action against the owners in quantum me-ruit. Other than citing authority establishing the four component elements of quantum meruit, appellant cites no authority supporting its argument that it, as a subcontractor with no privity of contract with the owners, is entitled to recover the total of its contract price on such theory. We agree with the appellees (owners) that appellant is precluded by TEX.REV.CIV. STAT.ANN. arts. 5463(2), 5469 (Vernon Supp.1982-1983) from recovering “in the manner and amount” sought by appellant. McKalip v. Smith Building & Masonry Supply, Inc., supra. The same reasoning under the first point of error is likewise applicable here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ambassador Development Corp. v. Valdez
791 S.W.2d 612 (Court of Appeals of Texas, 1990)
University Christian Church v. City of Austin
724 S.W.2d 94 (Court of Appeals of Texas, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
666 S.W.2d 568, 1984 Tex. App. LEXIS 4908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ms-foundations-inc-v-perma-crete-building-systems-inc-texapp-1984.