Seville Flexpack Corporation v. Bob Leathers, D/B/A R & L Steel Erectors
This text of Seville Flexpack Corporation v. Bob Leathers, D/B/A R & L Steel Erectors (Seville Flexpack Corporation v. Bob Leathers, D/B/A R & L Steel Erectors) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NO. 10-89-290-CV
IN THE
COURT OF APPEALS
FOR THE
TENTH DISTRICT OF TEXAS
AT WACO
* * * * * * * * * * * * *
          SEVILLE FLEXPACK CORPORATION,
                                                                                            Appellant
          v.
          BOB LEATHERS, D/B/A R & L STEEL
          ERECTORS,
                                                                                            Appellee
From 19th Judicial District Court
McLennan County, Texas
Trial Court # 88-1460-1
O P I N I O N
* * * * * * *
          This appeal arose from a suit brought by Bob Leathers, doing business as R & L Steel Erectors (Leathers), against Seville Flexpack Corporation (Seville) in April 1989, seeking damages for breach of a construction contract and, alternatively, asserting a right to recover on the basis of quantum meruit for the reasonable value of labor and equipment used in erecting a steel structure as part of Seville's manufacturing plant. The primary complaints on appeal are that the trial court abused its discretion in submitting a charge on substantial performance when only full performance had been pleaded and in awarding Leathers the full contract price even though the jury found "zero" to be the cost of remedying any defects or omissions. Seville also complains of the admission into evidence of a letter which it maintains constituted settlement negotiations. Finally, Seville appeals the judgment in favor of Leathers for attorney's fees because there was no evidence to support such an award. The judgment will be affirmed.
          The judgment awarded Leathers damages against Seville totaling $9,939, plus pre-judgment and post-judgment interest. The court expressly stated in the judgment that Leathers was awarded attorney's fees based on a stipulation that the prevailing party was to be awarded $3500 in attorney's fees as a part of the judgment. The court entered a take-nothing judgment against Seville on its counterclaim.
          Seville contracted to pay Leathers for services rendered at an agreed rate per ton of steel, the contract price totaling $57,850. Leathers could periodically request payment based upon the approval and certification of the work by Drennon & Associates, the architectural firm who designed the building and inspected Leathers' work prior to payment by Seville. Although the first three "draws" Leathers submitted to Seville were paid in full, Seville refused to pay the fourth and final draw in the amount of $9,939, plus $800 allegedly due for extra work. This refusal resulted in Leathers filing suit. Seville counterclaimed, alleging violations of the Texas Deceptive Trade Practices Act (DTPA). Both parties sought to recover their attorney's fees.
          The jury found that Leathers had substantially performed under the contract and that the cost of remedying any defects or omissions to make the structure conform to the contract was "zero." The jury failed to find that Leathers had done "extra welding" on the building at Seville's request or that Leathers had committed any DTPA violations. No questions concerning recovery of attorney's fees incurred by either party were submitted in the charge.
          In points one through seven, Seville argues that the court abused its discretion in submitting the questions on substantial performance and the cost to remedy defects in the construction when Leathers had only pleaded full performance. Seville also argues that the court erred in entering judgment on the jury's finding of "zero" as the cost to repair any defects because Leathers failed to plead and prove such costs and because the answer of "zero" constituted no finding on the requisite element of cost to repair, thus rendering the jury's finding of substantial performance immaterial. Seville further contends that the court erred in entering a judgment for Leathers because, as a matter of law, Leathers' substantial performance cannot support a judgment for the entire contract price.
          Whether the questions submitted in the charge control the disposition of the case as raised by the pleadings and the evidence and properly submit the disputed issues for the jury's determination are generally matters left to the discretion of the trial court. Baker Marine Corp. v. Moseley, 645 S.W.2d 486, 489 (Tex. App.--Corpus Christi 1982, writ ref'd n.r.e.). However, whether the charge has submitted the controlling theories of recovery or defense and whether particular questions submitted were supported by the pleadings are questions of law to be reviewed de novo. See Continental Casualty Co. v. Street, 379 S.W.2d 648, 651 (Tex. 1964).
          The theory of substantial performance permits a contractor to recover the full performance price on the contract less the cost of remedying the defects that can be fixed. Vance v. My Apartment Steak House, Inc., 677 S.W.2d 480, 481 (Tex. 1984). A pleading of full performance of the contract will support submission of a question to the jury on substantial performance in a suit on a construction contract. Uhlir v. Golden Triangle Development Corp., 763 S.W.2d 512, 514-15 (Tex. App.--Fort Worth 1988, writ den'd); Shaddock v. Storm King Window Co., 696 S.W.2d 271, 273 (Tex. App. -- Fort Worth 1985, writ ref'd n.r.e.).      Substantial performance was defined in the charge as "performance in all essential and important particulars, so that the building is suitable for the purpose intended, or may be made so with relatively minor corrective work." Seville introduced the majority of the evidence on what it claimed to be defects in the construction as well as on the cost to repair them. These alleged defects included five-hundred feet of parapet which had to be removed and replaced, removal and replacement of improperly welded steel bars which were removed in conjunction with the repair to the parapet, problems with steel lintels above and below windows, as well as the correction of a roof angle to allow window and brick installation. The record indicates that all of Leathers' work was inspected by the consulting structural engineer on the project and was approved by him or by Drennon & Associates and that Leathers adhered to the shop drawings drafted by Davis Iron Works from the project plans and specifications.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Seville Flexpack Corporation v. Bob Leathers, D/B/A R & L Steel Erectors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seville-flexpack-corporation-v-bob-leathers-dba-r-l-steel-erectors-texapp-1991.