Crest Construction, Inc. v. Murray

888 S.W.2d 931, 1994 WL 684677
CourtCourt of Appeals of Texas
DecidedJanuary 17, 1995
Docket09-93-225 CV
StatusPublished
Cited by10 cases

This text of 888 S.W.2d 931 (Crest Construction, Inc. v. Murray) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crest Construction, Inc. v. Murray, 888 S.W.2d 931, 1994 WL 684677 (Tex. Ct. App. 1995).

Opinion

OPINION

BROOKSHIRE, Justice.

An appeal by Crest Construction, Incorporated (Crest) from an adverse judgment. The appeal involves certain sub-contracts on three different construction projects. These three projects were referred to during the trial and in the briefs as the “Borden Job”, the “Cooper Job”, and the “Beaumont Job”. On these three construction jobs, Jim Murray acted as a concrete sub-contractor under Crest. Murray’s performance or lack of completion thereon triggered this litigation. At this ..point in our opinion we visit no moral or ethical wrongdoing on Murray’s part.

Crest initiated this litigation when, it was alleged, that Judy Murray ignored and violated a waiver of all rights to lien claims 1 that had been signed by her husband, Jim Murray, during his lifetime. Crest contended that Judy, individually and as Independent Executrix, had filed a groundless and waived, and forbidden lien claim affidavit on the “Beaumont Job”, thus preventing Crest from being paid by CCI, the general contractor on the “Beaumont Job”. CCI then filed pleadings in the nature of an interpleader. CCI was the general contractor for the Southeast Texas Rehabilitation Hospital Project in Beaumont, Texas. This was the “Beaumont Job”. Crest was a sub-contractor under CCI and Jim Murray was a subcontractor under Crest. Murray was to perform the concrete and cement work. CCI pleaded that a dispute arose between Crest and Murray as to the amount of money owed to Murray on the “Beaumont Job”. CCI tendered $71,509.51 into court.

CCI averred that it was informed that Murray had agreed to accept a certain, unse *936 cured promissory note in the amount of $36,-'000 payable from Crest to Murray in full and final settlement of all disputes, issues, and contentions on the “Beaumont Job”. But other separate, distinct disputes arose between Crest and Murray on two other, unrelated jobs where Murray was a sub-contractor to Crest. These two other jobs were the “Cooper Job” and the “Borden Job”. CCI had no relationship to the “Cooper Job” or the “Borden Job”. CCI by proper pleadings advised the court that Judy Murray, individually and as Independent Executrix, was making a lien claim against Crest on the “Beaumont Job”. Crest maintained that a full, final, and all-inclusive settlement agreement had been consummated between Crest and Jim Murray. The agreement provided only for the $36,000 note and affirmatively forbade the making or filing of any type of lien claim on the “Beaumont Job”.

Thus CCI was exposed to conflicting claims exposing CCI to multiple liability. CCI was a party to the “Beaumont Job”— but no other. Thereupon, CCI tendered into the registry of the district court the retained amount of $71,509.51 on the “Beaumont Job”. This amount was the entire retainage. CCI pleaded for relief seeking a declaration that all liens and all other claims of the subcontractors (Crest and Murray) asserted against the Beaumont property involved, that was the subject of the project on the “Beaumont Job”, shall be judicially deemed satisfied, paid, and released. The CCI inter-pleader was disposed of by the bench according to ‘an agreed judgment fully approved by CCI, Crest, and Judy.

The Jury Trial on the Merits Between Crest and Murray (Judy)

A number of questions were posed to the jury. The jury found, in substance, that by filing of record and sending a copy of the Mechanic’s and Materialmen’s Lien Affidavit dated April 8, 1991, 2 to CCI, Judy Murray was not guilty of intentionally interfering with the right of Crest to receive timely, final payments under its contract with CCI on the “Beaumont Job”. The jury’s answer was favorable to Judy Murray in her two capacities.

In answer to Jury Question No. 2, the jury was asked was Murray justified in filing the lien for approximately $62,000 plus on the “Beaumont Job”, even though the settlement called for Crest to execute a $36,000 unsecured promissory note containing strict provisions as to when the note matured and became due. The jury answered, “Yes” — in effect Judy was justified. The jury found that Murray was justified in interfering with Crest’s contractual rights with CCI if such action was done in a good faith assertion of legal rights. We, under this record, totally disagree on these jury questions and an *937 swers. We conclude that Judy’s positions on the filed liens are insupportable.

Neither Jim nor Judy had a right to file a Mechanic’s and Materialmen’s Lien claim or other type of lien or claim on the “Beaumont Job”. Unquestionably, neither had the right to file a $62,000 plus lien nor did either of them have a right to send copies to CCI. Under the rule of integrated, final, complete settlement agreements neither had a right to file even a $36,000 hen. Both parties had to adhere to ah of the provisions of the Beaumont settlement agreement. Appellee, in this record, admitted that a complete and final compromised settlement agreement was reached on all issues and disputes relevant to the “Beaumont Job”. The “Beaumont Job” settlement was separate, distinct, and independent of any problems or disputes on the “Borden” or “Cooper Jobs”. Under restrictive predicates, a certain number of jury questions were not answered.

The jury also found that James E. Murray did not breach his sub-contracts by failing to provide and pay for all of the labor and materials on the “Borden” and “Cooper Jobs”. The jury was instructed in connection with this question that lack of performance may be excused where the same contract had been previously materially breached by the other contracting party. This special answer was favorable to James E. Murray and his Independent Executrix.

Question No. 10 read: “Did Crest Construction, Inc. fail to receive all of the consideration it was to receive in return for execution of the $36,000.00 note on the Beaumont Job?” The jury answered, “No.” Thus Crest received all consideration given for the $36,000 note under the jury’s answer. We disagree. The jury in four separate answers denied any attorney’s fees whatsoever for the services of Crest’s lawyers.

Jury Question No. 13 read: “Did Crest and Jim Murray agree that Murray would be entitled to receive weekly payments from Crest on the Borden and Cooper Jobs?” The jury answered, ‘Yes.” To Jury Question No. 14 which read: “Did Crest fail to comply with the agreement, if any, by failing to make weekly payments on the Borden and Cooper Jobs prior to November 7, 1990?” The jury answered, ‘Yes.”

The jury also found that there was no sum of money that would (or should) be awarded to fairly or reasonably compensate Murray for damages, if any, that resulted from such failure of Crest to perform weekly payroll advances on the “Borden” and “Cooper Jobs”. Thus, the Murrays were entitled to nothing on the “Borden” and “Cooper Jobs”.

But to Jury Question No. 16 the jury did find that Crest failed to comply with the agreement of January 14,1991 on the “Beaumont Job”, by refusing to pay the $36,000 note in toto without claiming offsets. The jury answered, ‘Yes.”

The jury awarded $36,000 to Murray for the damages resulting from the failure of Crest to comply with the Beaumont settlement agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vicky McKenna v. Baylor College of Medicine
Court of Appeals of Texas, 2015
Lee Edward Morris v. State
Court of Appeals of Texas, 2010
Walker & Associates Surveying, Inc. v. Roberts
306 S.W.3d 839 (Court of Appeals of Texas, 2010)
Raymond Lopez v. Jesse D. Ramirez
Court of Appeals of Texas, 2005
Robert L. Crill, Inc. v. Bond
76 S.W.3d 411 (Court of Appeals of Texas, 2001)
Copeland v. Alsobrook
3 S.W.3d 598 (Court of Appeals of Texas, 1999)
Billy M. Copeland v. Tammy Alsobrooks
Court of Appeals of Texas, 1999
Murray v. Crest Construction, Inc.
900 S.W.2d 342 (Texas Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
888 S.W.2d 931, 1994 WL 684677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crest-construction-inc-v-murray-texapp-1995.