Hostetter v. City of Pittsburgh

107 Pa. 419, 1885 Pa. LEXIS 578
CourtSupreme Court of Pennsylvania
DecidedOctober 23, 1884
DocketNo. 183
StatusPublished
Cited by29 cases

This text of 107 Pa. 419 (Hostetter v. City of Pittsburgh) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hostetter v. City of Pittsburgh, 107 Pa. 419, 1885 Pa. LEXIS 578 (Pa. 1884).

Opinion

Chief Justice Mercur

delivered the opinion of the court, January 5th, 1885.

This judgment was recovered against the plaintiff in error on his bonds as surety of Hartupee. The latter had contracted to build for the city of Pittsburgh, certain graduating plunger pumping engines, according to the terms of two contracts between them. Each bond was conditioned that Hartupee should “ well and truly keep and perform all the terms and conditions of the said contract on his part to be kept and performed.”

The contracts and specifications designated the quality and strength of the iron to be used, and provided that the whole machinery should be constructed in a neat, substantial and workmanlike manner, and be put in successful operation to the satisfaction and acceptance of the board of water commissioners by a day specified. It was further agreed that the city might deduct and retain out of the moneys which may be due or become due to said Hartupee under the agreement, the sum of one hundred dollars per day, as liquidated damages for each and every day the work might be uncompleted beyond the time stipulated for its completion.

Monthly estimates should be made for all iron and composition work completed, and eighty per cent, thereof be paid monthly, and the residue be paid on the completion of the contract. The agreement further stipulated that in case of a failure to perform the conditions and obligations of the contract, and due notice thereof by the mechanical engineer, the contract might be declared null and void; and further, in [431]*431case of such failure to perform the contract, the said Hartupee should become liable for any damages caused the said city by reason of said non-performance, and besides, under any circumstances, should forfeit to the city the twenty per cent, retained out of the monthly estimates, or of any other moneys held in reserve bv the city. It was expressly agreed “in case any question or dispute between the parties shall arise under this contract, or touching the quantity, quality, or value of any work done thereunder, the same shall be referred to the mechanical engineer whose decision shall be final and conclusive. And tbe said party of tbe second part hereby waives and releases all right of action and suit at law, under or by virtue of this contract.”

When the work was partially completed tbe city complained that the iron and materials used were not of good quality nor of the strength stipulated in the contract: that they were of such defective materials as to have resulted in numerous breakages, thereby causing great loss and damage to the city; also that the workmanship was inferior and defective, and not according to the agreement.

It further alleged that the work was unreasonably delayed, and was not completed at the expiration of several years after the time stipulated for its completion. After due notice to tho contractor, and demand of possession, under claim of forfeiture, the city took possession of the works in an unfinished condition, refused to pay for them and claimed damages. The contractor denied the claims and allegations of the city; and claimed there were large sums due him on the contract and for extra work. The contentions were submitted to tbe mechanical engineer, who after a full bearing and consideration of the testimony, and of all tbe claims on each side, decided and reported that there was nothing dire to the contractor, that he had been fully paid for all work done and materials furnished, and above this he owed and was indebted to the city on each contract in a certain sum which be named, by reason of his breach of the contract in furnishing inferior and improper iron and in making defective castings, neither of which was in accordance with the terms of the contract, and said referee therefore adjudged that said Hartupee owed and should pay said sum to the city of Pittsburgh. This suit was for the recovery of the sums thus awarded.

It is contended by the plaintiff in error that this submission is not authorized by the language of the agreement.

Tbe clear and comprehensive words therein answers this question. They are 1st, “any question or -dispute ” between the parties that “ shall arise under this contract ” shall be so referred. This language is very broad. It is not restricted [432]*432to questions of disputed fact, nor to questions of disputed law, arising on the contract, but includes both. 2d. It proceeds, disjunctively, “or any question or dispute that shall arise touching tbe quantity, quality or value of any work done thereunder ” shall be referred to the same person. The reasonable and manifest meaning and sense of “ under,” in the connection in which it is used, is “the subject of” or “ covered by ” the contract. This is not only the plain and palpable import of “ under,” but it corresponds with the meaning of the word as given by both Worcester and Webster. As further indicating an intention that all questions of dispute that might arise connected with the subject matters of the contract should be so submitted, Hartupee waived and released all right of action and suit at law “ under or by virtue of this contract; ” that is, arising from or based upon its force, power and effect. The language clearly proves an agreement that all questions of dispute between the parties, which should arise on the contract, should be referred to the mechanical engineer, and that his decision should be final.

2. Is such an agreement valid, so that an award made under it shall be of binding force?

In Monongahela Navigation Company v. Fenlon, 4 W. & S. 205, it was held, when the parties to an executory contract stipulate that any dispute which shall arise between them on the subject of the contract shall be determined by an individual named, whose decision shall be final, no action will lie for a breach of the agreement by one against the other : but they must resort to the tribunal appointed by themselves, from whose award there is no appeal. In that case as in the present case the agreement was that the decision of the engineer should be conclusive. The agreement was held valid although the engineer was interested as a stockholder of the company. The binding effect of a similar agreement to refer to a person named all questions which may arise on an executory contract is affirmed in McGheehen v. Duffield, 5 Barr 497; Reynolds v. Caldwell, 1 P. F. Smith 298; O’Reilly v. Kerns, 2 Id. 214 ; Howard v. Allegheny Valley Railroad Co., 19 Id. 489; Connor v. Simpson, 8 Out. 440. This last case arose on an agreement to grade a portion of a railroad bed. It contained a clause appointing the chief engineer of the railway company a common arbiter to whom all and every question of 'difference between the parties growing out of the contract should be referred, and whose decision should be final and binding on both parties. The contractor entered on the work, and for some reason abandoned it in an unfinished condition, whereby the company claimed damages. It [433]*433was held, although the submission was prospective, yet it was special and to the arbitrament of a person designated, and was binding on the parties. In Hartupee v. City of Pittsburgh,

Out. 107, we considered the very contract now before us. We then held, as to all questions covered by the agreement, neither party could maintain a common law action without a previous arbitrament of the engineer, or an offer by one and a refusal by the other to so refer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bole v. Nationwide Insurance
352 A.2d 472 (Superior Court of Pennsylvania, 1975)
Allstate Insurance v. Fioravanti
299 A.2d 585 (Supreme Court of Pennsylvania, 1973)
Wilson v. Pennsylvania Railroad
219 A.2d 666 (Supreme Court of Pennsylvania, 1966)
Britex Waste Co. v. Nathan Schwab & Sons, Inc.
12 A.2d 473 (Superior Court of Pennsylvania, 1939)
Patriotic Order Sons of America Hall Ass'n v. Hartford Fire Insurance
157 A. 259 (Supreme Court of Pennsylvania, 1931)
Lackawanna Iron & Steel Co. v. Lackawanna & Wyoming Valley R. R.
149 A. 702 (Supreme Court of Pennsylvania, 1930)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)
Marine Ins. v. McLanahan
5 F.2d 773 (Fourth Circuit, 1925)
Pyron v. Brownfield
269 S.W. 202 (Court of Appeals of Texas, 1925)
Bizet v. Smith
115 A. 868 (Supreme Court of Pennsylvania, 1922)
Witmer v. Royal Insurance
68 Pa. Super. 12 (Superior Court of Pennsylvania, 1917)
Commercial Union Assur. Co. v. Dalzell
210 F. 605 (Third Circuit, 1914)
Kann v. Bennett
82 A. 1111 (Supreme Court of Pennsylvania, 1912)
Thaler Bros. v. Greisser Construction Co.
79 A. 147 (Supreme Court of Pennsylvania, 1911)
Duvall v. Sulzner
155 F. 910 (U.S. Circuit Court for the District of Western Pennsylvania, 1907)
McNally v. Montour Railroad
33 Pa. Super. 51 (Superior Court of Pennsylvania, 1907)
Seibel v. Firemen's Insurance
24 Pa. Super. 154 (Superior Court of Pennsylvania, 1904)
Borough v. Ott
56 A. 1079 (Supreme Court of Pennsylvania, 1904)
Chandley Bros. v. Cambridge Springs Borough
49 A. 772 (Supreme Court of Pennsylvania, 1901)
Klingensmith v. West Leechburg Steel & Tin Plate Co.
17 Pa. Super. 210 (Superior Court of Pennsylvania, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
107 Pa. 419, 1885 Pa. LEXIS 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hostetter-v-city-of-pittsburgh-pa-1884.