Vecellio v. Bopst

6 S.E.2d 708, 121 W. Va. 562, 1939 W. Va. LEXIS 94
CourtWest Virginia Supreme Court
DecidedOctober 31, 1939
Docket8909
StatusPublished
Cited by7 cases

This text of 6 S.E.2d 708 (Vecellio v. Bopst) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vecellio v. Bopst, 6 S.E.2d 708, 121 W. Va. 562, 1939 W. Va. LEXIS 94 (W. Va. 1939).

Opinion

Kenna, Judge:

This is an action in assumpsit brought in the Circuit Court of Mercer County by Oscar Vecellio against John *563 H. Bopst, Jr., trading and doing business as Industrial Piping & Engineering Company, the amount sued for being forty-five thousand dollars. Defendant being a resident of Baltimore, Maryland, an attachment was issued with which we are not here concerned. The declaration contains the common counts and in addition thereto a special count based upon a written contract set forth in extenso. The defendant filed a special plea setting up the plaintiff’s abandonment of his contract, which resulted in damaging the defendant in the amount of $38,573.07, amended by increasing the damages claimed to $38,945.03, for which he asked judgment against the plaintiff and filed in addition a statement of his grounds of defense based substantially upon the same averment. The plaintiff filed a statutory replication, issue was joined, and upon being submitted to a jury, a verdict for $26,196.00 was returned for the plaintiff. This writ was granted upon application of the defendant below.

The first question to be disposed of is one of pleading, the plaintiff in error contending that the verdict is necessarily based in part at least upon the quantum meruit, and that this fact necessarily involves an inconsistency since, as stated, the declaration contains both the common counts and a special count, which involve two different causes of action, one based upon the written contract and the other involving its abandonment. Without conceding the soundness of this theory, in our opinion, it is unnecessary to consider it here, due to the fact that it was not raised in the trial court. Neither by demurrer, special plea nor motion was this question presented to the trial judge and passed upon by him. This Court need not consider questions not acted upon by the court below. Davis v. Davis Trust Co., 113 W. Va. 43, 166 S. E. 690; Cameron v. Cameron, 105 W. Va. 621, 143 S. E. 349; State v. Sanney, 91 W. Va. 477, 113 S. E. 762. This applies particularly to what has resulted in no apparent prejudice.

The trial lasted for six days and the plaintiff’s proof involved a mass of documentary evidence the detail of which was not contested; In passing we wish to call at *564 tention to Code, 56-7-10, which provides for what may be. termed an order of reference in law actions for the purpose of taking an account between the parties. We are under the impression that the hearing of this case might have been simplified by following that practice.

The following, we think, is an accurate statement of the essential facts shown by this record, a detailed statement of which cannot be attempted, the record consisting of more than ten hundred and fifty printed pages:

The defendant, on July 3, 1936, entered into a contract with the plaintiff to partially construct that part of a sewage disposal plant located at South Bluefield, Taze-well County, Virginia, which the defendant had contracted to construct by a previous contract entered into with the City of Bluefield, West Virginia. The construction of the sewage disposal plant was a Public Works Administration project of some magnitude so that the plans and specifications were divided into three parts, apparently the work being classified according to its nature and time for performance. “Contract No. 3” was awarded to Bopst and he employed Vecellio to perform a large part of the construction work allotted to him, such as excavating, concrete foundation, structure work, etc. Vecellio also entered directly into “Contract No. 1,” so that he became both a principal and a sub-contractor. Apparently the only complication that was created by this dual relationship was due to the fact that Vecellio did not separate the credit extended to him for materials and equipment, but permitted that under the two contracts to become commingled, which fact, perhaps, involved the expenditure of receipts upon his sub-contract to discharge liabilities based upon his “Contract No. 1.” However, there does not seem to have been any mala fides involved in this rather awkward status, and surely the complication could not have been developed without the implied consent of the defendant, who, by the exercise of mediocre diligence, could have prevented it from arising. Vecellio was not required to enter into a performance bond and the only effort shown in this record *565 to have him use his receipts from Contract No. 3 to meet his obligations arising from its performance was a notation placed by Bopst upon a check for $21,525.56 given Vecellio on November 21st to cover October estimates requiring its proceeds to be so used, otherwise, the check to be “void”. Obviously, nothing was accomplished.

Vecellio began work July 15, 1936, and carried on until December 17, 1936, when his equipment, machinery, and materials were taken into the possession of the principal contractor, who retained some of his employees as well. We are under the impression that the principal part of the questions raised in this case turn upon the answer to the query as to whether this was justified as being predicated upon a voluntary abandonment or default on the part of Vecellio, or whether it constituted a breach of the contract on the part of Bopst, in which event the recovery by Vecellio is justified. From the record, it seems obvious that the construction cost of the part of the work covered by Vecellio’s sub-contract exceeded the contract price named in that contract.

Apparently Vecellio did very satisfactory work, keeping up with the schedule both as to quantity and kind of his work until late in November. Sometime before December first, forms were removed from a concrete “pour” intended for the pumping station wall. The concrete was found perforated and admittedly not in compliance with the specifications. The City of Bluefield, acting through Knowles and Company, declined to accept it or include it in the amount estimated to be payable to the contractor for the month of November. The engineer representing the city did agree that the original pour should be “gunited”, but insisted that that should be done by persons having had at least two years experience as operators. This led to the engineer’s not permitting a Fairmont firm that Vecellio arranged for to proceed with the work, which was not finally done until after Vecellio had ceased performance on December 17, 1936.

There is irreconcilable conflict in the testimony as to what occurred after the defective concrete was discovered, *566 Vecellio’s version being that the supervising engineer was at fault (Jupenlaz) and that he looked to the principal contractor to enforce his rights under the principal contract and subrogate him in turn; that he carried on with the contract to the extent that weather conditions would permit until it was breached by the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowers v. Wurzburg
528 S.E.2d 475 (West Virginia Supreme Court, 2000)
Aetna Casualty & Surety Co. v. Federal Insurance Co. of New York
133 S.E.2d 770 (West Virginia Supreme Court, 1963)
Sands v. Security Trust Company
102 S.E.2d 733 (West Virginia Supreme Court, 1958)
Copen v. Hix
43 S.E.2d 382 (West Virginia Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
6 S.E.2d 708, 121 W. Va. 562, 1939 W. Va. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vecellio-v-bopst-wva-1939.