Jost Jost v. Kurtz Kurtz

82 Pa. Super. 205, 1923 Pa. Super. LEXIS 276
CourtSuperior Court of Pennsylvania
DecidedOctober 8, 1923
DocketAppeal, 160
StatusPublished

This text of 82 Pa. Super. 205 (Jost Jost v. Kurtz Kurtz) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jost Jost v. Kurtz Kurtz, 82 Pa. Super. 205, 1923 Pa. Super. LEXIS 276 (Pa. Ct. App. 1923).

Opinion

Opinion by

Gawthrop, J.,

Plaintiffs brought an action of assumpsit to recover an alleged balance due on a written contract for the fur *207 nishing and installation of a vapor heating system in defendants’ building, and also to recover the value of labor and material furnished under an oral contract. the statement of claim averred performance by plaintiffs and acceptance by defendants. the affidavit of defense denied both performance and acceptance. the written contract provided that when the beating plant was completed plaintiffs should test it in the presence of the architect and prove it tight under a steain pressure of fifteen pounds. It provided further that all work should be executed “to the entire satisfaction and written acceptance of the architect.” When the case came on for trial, plaintiffs offered evidence tending to establish that when the work was completed under the written contract, and they were ready to make the.test of the plant, the architect failed to appear and one of the defendants suggested that the test be made in the absence of the architect; that the result of the test was perfect satisfaction on the part of defendants. the court below ruled that there could be no recovery under the written contract because plaintiffs failed to produce a certificate of the architect and acceptance thereunder. We do not agree that it was necessary for plaintiffs to produce a certificate from the architect showing that the beating plant bad been completed to the satisfaction of the defendants before there can be a recovery on this branch of the case under the circumstances. This is not a case in which a certificate of the architect is made a condition precedent to the making of the final or any other payment by the owner. Under the contract, the last payment was due upon completion and test of the beating system. There was evidence that the system was completed and that the test was satisfactory. If the beating system was completed by plaintiffs, defendants could waive their right to insist upon the certificate. If they expressed satisfaction with the plant and chose to accept it on their own responsibility, it was for the jury to say whether or not they bad waived their right to insist *208 upon the certificate. This is so firmly established that it must be accepted as the settled law of this State. See Hunn v. Penn. Inst, for the Blind, 221 Pa. 403.

Since the case must be retried, we deem it our duty to state that in our opinion the book which was offered as one of original entry was, on its face, inadmissible and, therefore, properly excluded, because it contained lump charges. See Miller’s Est., 188 Pa. 214. Without being supplemented by the testimony of one who knew that the lumping charges were composed of items furnished, it would have been error to admit the book: Nichols v. Haynes, 78 Pa. 174.

The judgment is reversed and a venire facias de novo is awarded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nichols v. Haynes
78 Pa. 174 (Supreme Court of Pennsylvania, 1875)
In re Estate of Miller
41 A. 532 (Supreme Court of Pennsylvania, 1898)
Hunn v. Pennsylvania Institution for the Instruction of the Blind
70 A. 812 (Supreme Court of Pennsylvania, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
82 Pa. Super. 205, 1923 Pa. Super. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jost-jost-v-kurtz-kurtz-pasuperct-1923.