Miller & Sons Co. v. Homeopathic Medical & Surgical Hospital & Dispensary

90 A. 394, 243 Pa. 502, 1914 Pa. LEXIS 653
Supreme Court of Pennsylvania·Decided January 5, 1914·No. Appeal, No. 246·Published·Cited by 8 cases

Opinion

Opinion by

Mr. Justice Mesteezat,

The facts of the case with two or three omissions have been clearly stated by the learned judge of the court below, and will be found in the reporter’s notes. They need not be restated here.

This is an action by the contractor against the owner to recover the- cost of tearing down and rebuilding the damaged part of a building being erected by the former for the latter. The amount is not in dispute. The finding of the jury was in favor of the plaintiff and under the charge the verdict established that the alleged defect in the plans and specifications did not cause the sinking of the building; that the plaintiff used all practical precautions to prevent water getting into the foundation; and that the wall fell because the soil on the defendant’s lot when excavated to the width and depth required by the contract was not sufficient to sustain the building to be placed upon it. The single question here is whether the contractor or owner is responsible for the loss resulting from the sinking of the east wing of the foundation wall caused by the insufficiency of the soil to support the building. The learned court below held the contractor responsible, and entered judgment non obstante veredicto for the defendant. The plaintiff company, the contractor, took this appeal.

The learned court below in reaching its conclusion applied the rule of absolute obligation on the part of a contractor, and held that the contract was entire and indivisible, that the contractor was required to finish and deliver a completed building to the owner, that the [512] defect in the soil which caused the wall to fall did not excuse the contractor from the performance of the eon- ■ tract, and that therefore the latter could not recover the cost of reconstructing the damaged building. It is undoubtedly a well established rule in many jurisdictions that if one undertakes by an entire contract to erect a building for another without stipulating against unforeseen contingencies he must perform his contract and complete the building, unless performance is rendered impossible by the act of God, the law or the other party. There is no implied warranty, it is held, of the practicability or sufficiency of the plans or of the sufficiency of the soil to support the building to be erected thereon. The contractor assumes the risk in both instances, and if an injury results to the building by the happening of either contingency during the progress of the work, the contractor must sustain the resulting loss. Whether the rule in question is the law of this State we need not inquire or determine, as we are of opinion it is not applicable to the facts of this case.

The agreement between the parties to this litigation does not provide simply that the contractor shall furnish certain materials and do certain work in the construction of the hospital on a certain lot of ground in accordance with definite plans and specifications. He was not permitted to furnish such materials or do such work as he deemed a compliance with the contract for the erection of the building nor could he deviate from the plans and specifications if he found them defective or insufficient to support the building on the designated lot of ground so as to complete the building in accordance with the agreement. In other words, while he was required to furnish all materials and perform all the work for the erection of the building as shown on the drawings and described in the specifications, the materials were to be furnished and the work was to be done under the supervision and direction of the architect who was to determine the true construction of the drawings [513] and specifications and was authorized to make such changes in the work as he might consider desirable. In addition to these stipulations, the contract provides that such additional drawings as might be necessary should be furnished by the architect and the contractor should conform to them; no alterations should be made in the work except upon the written order of the architect; the contractor should take down all work condemned by the architect ; should the contractor refuse to properly perform the work the owners, on certificate of the architect, might dispense with the contractor and complete the work at his expense; the building would not be accepted unless a final certificate was given by the architect; the workmen should be satisfactory to the architect; anything not expressly set forth in the drawings or specifications but reasonably implied to make a complete job should be furnished and performed by the contractor, but should any error appear in either of them or the work done, affecting the work included in the specifications, the contractor was required to notify the architect or make good the damages; no work should be altered without a written order of the architect; and if required by the architect the contractor was to erect a platform to make soil tests.

Free access — add to your briefcase to read the full text and ask questions with AI

Miller & Sons Co. v. Homeopathic Medical & Surgical Hospital & Dispensary, 90 A. 394, 243 Pa. 502, 1914 Pa. LEXIS 653 (Pa. 1914).

90 A. 394 (Miller & Sons Co. v. Homeopathic Medical & Surgical Hospital & Dispensary) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pickens v. Cunningham
22 Pa. D. & C.3d 40 (Mercer County Court of Common Pleas, 1981)
Commonwealth v. W. P. Dickerson & Son, Inc.
400 A.2d 930 (Commonwealth Court of Pennsylvania, 1979)
Luria Engineering Co. v. Aetna Casualty & Surety Co.
213 A.2d 151 (Superior Court of Pennsylvania, 1965)
Canuso v. Philadelphia
192 A. 133 (Supreme Court of Pennsylvania, 1937)
Atowich v. Zimmer
25 P.2d 6 (California Supreme Court, 1933)
Raab Et Ux. v. Beatty
96 Pa. Super. 574 (Superior Court of Pennsylvania, 1929)
Portable Elevator Manufacturing Co. v. Dutton
224 Ill. App. 123 (Appellate Court of Illinois, 1922)
Cramp & Co. v. Central Realty Corp.
110 A. 763 (Supreme Court of Pennsylvania, 1920)