Atowich v. Zimmer

25 P.2d 6, 218 Cal. 763, 1933 Cal. LEXIS 578
CourtCalifornia Supreme Court
DecidedSeptember 13, 1933
DocketDocket No. L.A. 12785.
StatusPublished
Cited by8 cases

This text of 25 P.2d 6 (Atowich v. Zimmer) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atowich v. Zimmer, 25 P.2d 6, 218 Cal. 763, 1933 Cal. LEXIS 578 (Cal. 1933).

Opinion

WASTE, C. J.

The appellants, husband and wife (plaintiffs below), entered into a contract with respondent Max Zimmer (one of the defendants below), hereinafter referred to as the contractor, wherein and whereby the latter agreed to erect and construct for plaintiffs a certain building and to remove and remodel another structure situated on the same premises, for the agreed sum of $23,400. The respondent Fidelity & Deposit Company of Maryland executed a bond in favor of plaintiffs containing the usual guaranties that all things incumbent upon the contractor would be done and performed in accordance with the contract, plans and specifications. The contractor did not construct the *765 building entirely according to the plans and specifications. On completion of the building, however, plaintiffs took possession and accepted it from the contractor. Some time after its acceptance and occupancy by the plaintiffs, it was discovered that the walls of the building had settled, and that there was a noticeable deflection in the floor of the second story. Plaintiffs brought this action against the contractor and his surety to recover damages caused by reason of the omission of certain features called for by the plans and specifications, the cost of making necessary repairs to the walls and floor of the second story, and depreciation in value of the property by reason of the alleged faulty construction. Incidentally, also, relief was sought against other parties in relation to certain payments made by plaintiffs to the contractor on account of the contract. Judgment was rendered for the defendants.

The trial court has made lengthy and explicit findings, including therein, in some instances, practically a recital of the testimony educed at the trial. The first and general contention of appellants is that the findings are not supported by and are contrary to the evidence, and that the evidence is insufficient to support the judgment. A reading of the record of the evidence and an examination of the contentions of both appellants and respondents lead us to the belief that the contention is not borne out by the record. So far as the record is concerned, the evidence material to the issues presents, rather, a question of the weight to be given to the testimony of the various witnesses. For that reason, we deem it unnecessary to enter into a discussion of the testimony in the case.

An objection to the sufficiency of the findings of fact and conclusions of law urged by the appellants relates to the second finding of the trial court, the effect of which is that the plans and specifications for the work to be performed by the contractor were, in fact, prepared at the instance and request of the plaintiffs. We are of the view that the evidence as a whole supports the trial court, and that its conclusions in that regard were correct.

It appears from the findings that after the plans and specifications were submitted to the owners, and after bids had been received by them for the doing of the work, certain changes had to be made to meet the objections of the *766 building inspector of the city of Glendale. That matter being settled, the contractor entered upon the performance of his contract, and proceeded with the work. After part of the work had been performed, the plaintiffs secured the services of Elmer Elliott, a man of experience, as an inspector or foreman, to supervise for them the erection and construction of the building from that point to its completion. The work was completed, and the plaintiffs accepted the building and took possession on or about the eleventh day of December, 1928. Between that time and the date of the trial of the action, it was discovered that a portion of the brick walls on the northerly and westerly sides of the building had settled. The finding of the trial court on this matter is that the walls “settled as a result of the soil or dirt under said walls not being of sufficient strength or texture to sustain the weight thereof upon a foundation of the width supporting said walls, and in this respect the court finds that the foundation under said walls was of the width and thickness as provided by the plans and specifications, and that said defendant Max Zimmer in the erection and construction of said brick walls and the foundation thereunder fully complied with said plans and specifications and that . . . the settlement occurring in said walls and foundation was not the result of a failure on the part of said defendant Max Zimmer to comply with said plans and specifications.” Evidence supporting this finding is that the contractor who performed the brick work in the construction and erection of the building and his foreman plumbed the outside brick walls after the walls had been erected to the second story, and after the second story walls had been finished, and again upon the completion of the building, on which occasions they found the walls to be perpendicular; on which evidence the court finds “that upon the completion of the erection and construction of the building the brick walls were plumb and perpendicular and that none of said walls were out of plumb or leaning”.

Some time after the plaintiffs took possession of and accepted the building, a deflection or settlement occurred in the floor of the second story. As to this matter the court finds that there was no such deflection or settlement at the time the plaintiffs took possession and accepted the building, but that such deflection when it did occur was “due to the *767 failure to use a sufficient number of joists and timbers to support or maintain the second floor and that said joists and timbers were not placed close enough together”; but that in this respect the joists and timbers used and installed “were of the size as provided for in the plans and specifications and the same were spaced at the distance provided for in the plans”. From these facts the court further finds that the deflection or settlement in the floor of the second story of the building “was not due to the failure of the defendant Max Zimmer to install said joists or timbers or to erect and construct the second story or any part of the building in accordance with the plans and specifications”, but that in the erection and construction of the second floor and the use of joists, timbers, flooring and other lumber the defendant fully complied with the plans and specifications under which the building was erected and constructed.

The contractor did not construct the building in exact accordance with the plans and specifications in that four telephones leading from apartments to the lobby entrance were omitted, one electric door opener was omitted, certain storerooms and garages were omitted, and certain work was done in a manner and form slightly different from that called for in the plans and specifications. In this behalf the court finds that before making any changes and before performing work in a manner and form different from that called for in the plans and specifications, the contractor conferred with and consulted Elliott, the agent and superintendent of the plaintiffs, and the changes, alterations and omissions were made with the consent and approval of the plaintiffs given by and through their agent Elliott. There is a further finding that in the erection and construction of the building “there was a substantial compliance with the contract, plans and specifications by the defendant Max Zimmer”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wm. R. Clarke Corp. v. Safeco Insurance of America
938 P.2d 372 (California Supreme Court, 1997)
United States Leasing Corp. v. duPont
444 P.2d 65 (California Supreme Court, 1968)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Pacific Allied v. Century Steel Products, Inc.
327 P.2d 547 (California Court of Appeal, 1958)
Bloom v. Bender
313 P.2d 568 (California Supreme Court, 1957)
Banducci v. Frank T. Hickey, Inc.
209 P.2d 398 (California Court of Appeal, 1949)
In Re Kinney Aluminum Co.
78 F. Supp. 565 (S.D. California, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
25 P.2d 6, 218 Cal. 763, 1933 Cal. LEXIS 578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atowich-v-zimmer-cal-1933.