Mannix v. Wilson

123 P. 981, 18 Cal. App. 595, 1912 Cal. App. LEXIS 401
CourtCalifornia Court of Appeal
DecidedApril 1, 1912
DocketCiv. No. 933.
StatusPublished
Cited by6 cases

This text of 123 P. 981 (Mannix v. Wilson) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mannix v. Wilson, 123 P. 981, 18 Cal. App. 595, 1912 Cal. App. LEXIS 401 (Cal. Ct. App. 1912).

Opinion

BURNETT, J.

The original complaint, as stated by respondent, set forth a cause of action for the foreclosure of a mechanic’s lien upon the property therein described, for plastering the building thereon, under a contract between respondent and the original contractor, one J. W. Mitchell, and also against the owner, appellant Wilson, personally, on a “stop notice” served upon him pursuant to section 1184 of the Code of Civil Procedure. By a subsequent amendment another cause of action for the same debt is alleged against appellant, on a written guaranty which appellant gave re *597 spondent for the payment by said Mitchell of the contract price of said plastering. No question is raised, nor indeed could be, as to the sufficiency of the complaint, and the only issue presented by the answer which can be considered here is found in the averment that “plaintiff hindered and delayed the said work, and did not prosecute the same with reasonable or any diligence, but unreasonably and without any valid excuse therefor did so negligently and slothfully perform the same and so neglected the performance of and hindered and delayed the same, that the same was not completed by him until sixty days subsequent to the time when the same should have been completed by him and when the same would have been completed by him had he not delayed the work as aforesaid and had he prosecuted the same with reasonable diligence,” and that thereby appellant was damaged by loss of rents to the extent of $2,840. The finding of the court directly negatives these allegations in the answer and, outside of a single ruling upon offered evidence, to be hereafter noticed, it is apparent, from the record, that the only matter for adjudication here is as to the sufficiency of the evidence to support said finding.

As to this there can be no serious controversy. Indeed, it is strange that the question should be raised at all. It may be said that the testimony for appellant in this respect is so equivocal and uncertain as to hardly create even a conflict. The contract involved herein was executed September 2, 1908. It is apparent that the lathing and plastering could not be done until the building was made ready for it. It does not appear definitely when the building was ready for respondent’s work. Appellant testified that he thought that a month before respondent started to work he notified the latter that the building was ready for him, but furthermore he testified: “He didn’t start his work before away back in September. ... I could safely say he delayed in starting work after I had notified him that it was ready for him for thirty days! It was at least two or three weeks. It was fully a month. ... I notified him to commence work the beginning of July, I think it was ... ; he commenced to make his mortar two or three weeks afterward. . . . He commenced plastering about August 13th. No, I don’t think he commenced plastering until about September 1st. ... I think he started in to *598 plaster between the 1st and 15th of September—no, between the 15th of September and the 1st of October.” His other witness, the architect, also testified: "I don’t remember the date when Mannix commenced the work. I should judge some time during the month of September.” Furthermore, he said: ‘‘A plastering contractor mixes his mortar first, which takes some time. Then that mortar must lay for ten or twelve days so it will become aged.” As to this asserted delay of thirty days in beginning the work it is therefore apparent that the question was at least left in doubt by the testimony of appellant’s witnesses.

Turning, however, for support of the challenged finding, to the evidence, which under the established rule requires of us full credit, we may adopt the epitome furnished by respondent, as follows: Mannix says that when Wilson notified him to commence work he went to the building and found it was not ready for plastering, but he commenced to mix his mortar on the street and was stopped by a policeman, which occasioned a delay of about two days. There was not room to mix it in the basement, because it was full of rubbish and carpenter stuff and they had men there getting it ready to plaster. When the architect called on him to commence plastering the building was not ready. Neither the front nor back stairway was up; the electric wires had not been inspected and his work went over them; the carpenters’ work on the first floor was improperly done and Wilson made him do it over afterward. "I proceeded just as soon as the work was ready and continued it as quick as it could be done.” One Ziegler did the lathing, and ‘‘I started him as soon as he could get to work and followed it up with the plastering. ’ ’ Furthermore, plaintiff testified that he talked with appellant at different times and that the latter said, "Of course he had to pay the bill; he knew he had to pay the bill; he knew he had to pay it, and he did not complain about the character of the work or about any delays, and he said that he was ready to pay as soon as the affair could be settled up.” The testimony of plaintiff as to the progress of the work is also corroborated by two of the lathers, who made clear the fact that any unwarranted delay in the plastering was not at all the fault of respondent. It seems idle to pursue the subject any further or to argue—what certainly will not be disputed— *599 that respondent was not responsible for delays caused by those over whom he had no control and with whom he sustained no contractual relations.

The only ruling which is assailed is exhibited in the transcript as follows: “The defendant thereupon offered in evidence the original plans and specifications and contract between A. W. Wilson and J. W. Mitchell. . . . Counsel for defendant Wilson stated that said contract was offered in evidence to show that Mitchell was required by it to complete the building within one hundred working days after June 22, 1908, and that in case of his failure so to do that he should be liable to the owner for all loss and damage arising by reason of such delay, to which introduction of said evidence the plaintiff objected, upon the ground that the same was immaterial, irrelevant and incompetent, and was a contract between Mitchell and Wilson and not binding upon Mannix except so far as it was made so by his agreement.” The objection was sustained.

. The question may be considered from several viewpoints, and from each we shall discover that the said ruling was either justifiable or innocuous. One of these is set forth perspicuously by Mr. Justice Henshaw in the case of Hampton v. Christensen, 148 Cal. 729, [84 Pac. 200]. Therein it is said: “It is a perfectly legal contract which makes time of completion of its essence, and provides that the contractor, for a failure to perform in time, shall make good to the owner such loss as the latter may sustain thereby. More than this, it is a deduction or offset which, but for the lien law, the owner would have the unquestioned right to claim from the amount found due the contractor under the contract. . . . But the right of materialmen, artisans and laborers of every class is to have a lien upon the property upon which they have bestowed their labor or furnished their material for the full value of the same, and this right is one solemnly guaranteed them by the constitution of the state. (Art. XX, sec. 15.) The legislature is enjoined to pass laws for the speedy and efficient enforcement of these liens. ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard Oil Co. of California v. Houser
225 P.2d 539 (California Court of Appeal, 1950)
Banducci v. Frank T. Hickey, Inc.
209 P.2d 398 (California Court of Appeal, 1949)
Atowich v. Zimmer
25 P.2d 6 (California Supreme Court, 1933)
Leaf v. Reynolds
203 P. 458 (Idaho Supreme Court, 1921)
Summers v. L. F. S. Syndicate
189 P. 286 (California Court of Appeal, 1920)
Stephens v. Weyl-Zuckerman & Co.
165 P.2d 975 (California Court of Appeal, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
123 P. 981, 18 Cal. App. 595, 1912 Cal. App. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mannix-v-wilson-calctapp-1912.