Stephens v. Weyl-Zuckerman & Co.

165 P.2d 975, 165 P. 975, 33 Cal. App. 566, 1917 Cal. App. LEXIS 263
CourtCalifornia Court of Appeal
DecidedMay 2, 1917
DocketCiv. No. 1559.
StatusPublished
Cited by3 cases

This text of 165 P.2d 975 (Stephens v. Weyl-Zuckerman & Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephens v. Weyl-Zuckerman & Co., 165 P.2d 975, 165 P. 975, 33 Cal. App. 566, 1917 Cal. App. LEXIS 263 (Cal. Ct. App. 1917).

Opinion

BURNETT, J.

The action is for the balance due for the construction by plaintiffs of a gasoline launch under an ex *567 press contract requiring the payment by defendant of the sum of $1,550 and providing that the launch should be completed on June 1, 1914. The boat was not ready on time but was accepted by defendant, which claimed, however, that it was entitled to a rebate or recoupment in consequence of the damage caused by the delay. It was, though, found by the court that there was a waiver of any such claim and the real controversy revolves around this consideration. The basis for the court’s conclusion is found in these facts: “Defendant, with knowledge of the fact that said launch would not be completed in the time specified by said contract, did not insist upon any penalty from plaintiffs but urged them to rush said launch to completion. That plaintiffs did rush said launch to completion. During the period prior to August 8, 1914, in which payments were made as hereinafter set forth, defendant did not at any time threaten plaintiffs for any penalty for their failure to deliver the boat on time, but rather urged plaintiffs to complete the boat as soon as possible ; that plaintiffs did complete the boat as soon as possible ; that prior to August 8, 1914, defendant raised no objection as to the failure of plaintiffs to complete the same on June 1, 1914.”

We think, however, that the learned trial judge failed to distinguish between the right to rescind or abandon the contract and the right to insist upon compensation for the damage caused by the delay. The former was undoubtedly waived, but the other legal privilege was unaffected by the acts detailed in said finding. The distinction between the two methods of redress as to waiver is quite clearly shown by the authorities.

In Crocker-Wheeler Co. v. Varick Realty Co., 43 Misc. Rep. 645, [88 N. Y. Supp. 412], the subject of litigation was a contract to furnish and install two elevators.' The trial judge held that the conduct of defendant “in urging plaintiff to continue and hurry completion of the work, and finally accepting the same when performed and paying therefor a large part of the stipulated price thereof,” was a waiver of damages for the failure to complete the work within the prescribed time. It was determined, however, by the appellate division that the defendant waived simply any right it might have asserted to plead the delay as a defense to an action for the agreed price, the court saying as to the other question:

*568 “It did not, however, thereby waive its right to counterclaim for any actual damage it might have suffered by reason of the delay. . . . The error into which the court below fell was in treating defendant’s acquiescence in the completion of the contract as a waiver of damages for nonfulfillment, instead of only a waiver of any defense to a claim for the contract price. ’ ’

In Howard v. Thompson Lumber Co., 106 Ky. 566, [50 S. W. 1092], appellant agreed to build a tramway and haul logs for appellee. Compensation was to be paid as the work progressed, but a certain percentage thereof was to be retained and appellants’ rights thereto forfeited if they did not perform as agreed. In an action by appellants, the defense of tardy performance was pleaded and appellee responded by alleging a waiver. In the course of the opinion it was stated that after the failure to furnish the logs within the time agreed upon, appellee “continued to receive and pay for the logs delivered and urged defendants to go on with their contract.” The court, after quoting from Lawson on Contracts, declared: ’“Appellee, in accepting the logs, actually delivered, and paying therefor, and in urging and ' encouraging appellants to go ahead with the work, waived its right to claim the forfeiture of the ten per cent on monthly settlements and the seventy-five cents per thousand feet for failure to complete the tramway, and appellants are entitled to maintain this action to recover the amount due them under the contract for logs actually delivered; but appellee is entitled to recoup by way of setoff or counterclaim damages sustained on account of the failure of appellants to beep their contract, unless such failure was occasioned by the fault of appellee.”

The supreme court of this state declared the same principle in Bryson v. McCone, 121 Cal. 153, [53 Pac. 637], as follows: “But consent on the part of plaintiff that defendant might continue the work after the stipulated time was not a waiver of damages or of the breach. Upon the breach plaintiff, not being himself in default, had the right to rescind or permit the defendant to complete the work and sue for damages occasioned by the default.”

It was similarly held by the supreme court of Michigan in Buick Motor Co. v. Reid Mfg. Co., 150 Mich. 118, [113 N. W. 591], wherein the defendant urgently insisted upon the de *569 livery of the goods contracted for after the stipulated time had expired; by the supreme court of the United States in Phillips etc. Const. Co. v. Seymour, 91 U. S. 646, [23 L. Ed. 341], wherein it was stated that upon a contract for the sale of personal property to be delivered upon a certain day it might be received afterward and the vendor could recover for it, but that the vendee might recoup by setting up a cross-demand for damages for the delay; by the supreme court of Michigan in Pittsburgh & O. Min. Co. v. Scully, 145 Mich. 229, [108 N. W. 503], wherein it was held that defendant, by receiving and paying for coal that was not promptly shipped, did not waive the claim for damages because the coal was not promptly delivered. Many other cases to the same effect are cited by appellant, and they seem to recognize the rule as of general acceptance.

The justice of this view is affirmed in. Page on Contracts, volume 3, page 2320, upon the ground that “the party not in default is often constrained by his necessities to take what he can get under his contract when he can get it. Such conduct does not and should not operate as a waiver of the right of action for damages.”

We can perceive no just ground for holding that any of the facts recited by the court, or all combined, should operate as a waiver of the right to claim whatever damages accrued to appellant by reason of the failure on the part of respondents to keep their engagement. Assuredly, the failure to demand a penalty, or to use threatening or acrimonious language, is no evidence of a relinquishment of this right. The effort to induce respondents to complete the work as speedily as possible and the payment of the several installments as they were due were entirely consistent with the purpose of claiming whatever might be due defendant under the contract. It was the duty of appellant to make the payments as called for, and its urgency as to the completion was evidence of good faith and a desire to save respondents as well as appellant from unnecessary loss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Banducci v. Frank T. Hickey, Inc.
209 P.2d 398 (California Court of Appeal, 1949)
Robberson Steel Co. v. Harrell
177 F.2d 12 (Tenth Circuit, 1949)
Orr v. Forde
282 P. 429 (California Court of Appeal, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
165 P.2d 975, 165 P. 975, 33 Cal. App. 566, 1917 Cal. App. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephens-v-weyl-zuckerman-co-calctapp-1917.