Merrill v. Ithaca & Owego Rail Road

16 Wend. 586
CourtNew York Supreme Court
DecidedJanuary 15, 1837
StatusPublished
Cited by81 cases

This text of 16 Wend. 586 (Merrill v. Ithaca & Owego Rail Road) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merrill v. Ithaca & Owego Rail Road, 16 Wend. 586 (N.Y. Super. Ct. 1837).

Opinion

By the Court, Cowen, J.

After such an exact tacit adherence, on the side of the plaintiffs, as appears from the evidence in this case, to the written terms of the contracts, without one word that they intended to alter their rates of charge, it would be a fraud upon the company were they allowed to change their ground. It is not denied that they may resort to the general counts. Both parties having assented that the work should go forward after the day, that may be so. It is clearly so as to line C. and section 4, if [589]*589they are not touched by the general provisions of the contract in respect to section 3 ; yet the rule is well settled, that though there be a deviation, yet the special contract shall be pursued as far as it can be traced and made to apply. Here all the powers of the engineer in chief, with the measures and estimates, may be retained and applied to the whole work, with very little exception. For a plain excess beyond what the parties may have treated as within the articles, there could of course be no objection to allow on the basis of a quantum meruit. I am here speaking particularly of the work done on sections 3 and 4. As to section 8, there is no doubt that all the substantial provisions of the written contract should be applied. The prices and estimates of the engineer in chief would still be conclusive, though we should allow the action of indebitatus assumpsit. It is a mere change of remedy. It would be gross injustice to allow any substantial departure from stipulations, in reference to which the parties all along acted. No matter for the delay, and no matter which party was so unfortunate as to be the innocent occasion of it. It was the business of either to speak out, if a change of terms was in contemplation. Silence was equivalent to skying, “I go on upon the old terms.” It is like a tenant holding over in silence. He shall pay his last year’s rent. If one party, by his conduct or silence, leads "another to believe that he is at work for him on certain wages, he is estopped and shall not add to his demand. I forbear, however, to pursue this branch of the inquiry. I have said so much merely by way of protest against the notion that, because the law is favorable to a remedy in some form, though the covenant may not have been literally fulfilled, it is yet not sedulous to save all the terms of the written contract as far as possible; measures, proportions, prices, bases of estimate, quality of the work, every thing fair and honest.

I have so far supposed all delay and embarrassment to have been the result of misfortune ; of oversight, miscalculation, or want of fore cast in one party or the other, or both; want of skill, if you please, in the conduct of business, and I care not on which side. But there is another view of [590]*590the case which is decisive in favor of a departure from the original principles and mode of estimate, at the election of the plaintiffs. [Mr. Justice Co wen here reviewed the testimonv which had been given in reference to embarrassments to the completion of the job, alleged to have been thrown in the way of the plaintiffs by the defendants, and then proceeds.] I do not say the referees were bound to believe that here was a project by the defendants to abuse the great power confided to them, or to their engineer, by turning it into a means of ruinous delay. It is only necessary to see from the testimony, both direct and circumstantial, as it comes from many witnesses, that they were justified in such a conclusion. There was certainly a conflict of evidence upon the question ; but that belonged to the referees. Coming to that conclusion, whose fault is it that this contract was not fulfilled by the 15th of July? Whose fault is it that these plaintiffs passed their summer in a state of tantalizing suspense, and were driven with this large concern on their hands into the ensuing winter ? Whose fault is it that a contract, which the engineer thinks performed with adequate skill, would have been profitable on the original estimates, has nearly doubled in the expense of performance ? Thus hoodwinked, and led into a train of additional expense which would exhaust two ordinary fortunes; pursuing a pilgrimage of toil in the service of these defendants, which, with an honest and hearty concurrence on their part might have been finished before the inclement season came, the parties stand clear of the covenant in all its features ; and the plaintiffs are entitled to an indemnity upon the principles adopted by the referees. They might have stopped, and sued the defendants for a breach of their covenant. But going on under the circumstances disclosed, there is nothing of the primary principles of estimate which could have been justly applied.

I apprehend, however, that the cause must go back to the referees and be re-heard, for an error committed by'them in the admission of the kind of evidence by which they appear to have governed themselves in fixing the amount of labor. Finding that the estimates of the engineer in chief had be[591]*591come entirely inapplicable and positively unjust, by the baffling of the defendants and delays of the work till the very worst season, it became necessary for the plaintiffs to communicate to the referees, by some other evidence, the amount of labor ; and they chose to adopt, as they had a right to do, the number of days in team and other work. For the purpose of ascertaining the days of work performed as between themselves and their laborers, their superintendents were directed to keep what were called check-rolls, and which appear to have been books marked A, B, C, dec. devoted to each section, in which the laborer’s name was placed in the left margin; and in a column opposite, and under the day of the week at the top of that column, was written in figures the time he worked on that day. At evening when the laborers came in, the superintendents of the particular section being generally together, the roll of names were called, and the amount of labor reported and marked by some one. The particular superintendent of each squadron of laborers heard the names, and generally either wrote the time or saw it set down, and was capable of deciding to his own satisfaction whether the item was correct. I say generally. These persons, as far as they were called to prove the rolls, did not pretend that the superintendents were always together, that they always wrote or saw written the accounts of their particular squadron, or always heard the names. Some of them were absent for days and even months ; and a considerable portion of these entries must have been made without their actual or potential knowledge. One says he was sick a part of the time, and could not be out with his hands. He, however, saw or superintended the entries at his quarters in the evening. It does not appear that all the superintendents were sworn before the books were offered, much less all those persons who acted as clerks, and those who were engaged 'as substitutes during the absence or sickness of the general superintendents. Nor were all the clerks or superintendents, or their substitutes named in evidence and absences accounted for. Indeed, the contrary appears, or is plainly inferrible from the 'case as made out by the affidavit of the attorney [592]*592for the plaintiffs, into which I have so far looked, because it was adopted as containing the more correct statement of the oral evidence, the case not having been referred to and settled the referees. The books, of course, continued in the hands or under the control of the plaintiffs. The superintendents sworn expressed a strong general belief of the áccuracy of the rolls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry Shenk Co. v. Erie County
178 A. 662 (Supreme Court of Pennsylvania, 1935)
Warner Quinlan Co. v. Ben Charat, Inc.
143 Misc. 443 (Appellate Terms of the Supreme Court of New York, 1932)
The People v. Greenspawn
179 N.E. 98 (Illinois Supreme Court, 1931)
Hodas v. Davis
203 A.D. 297 (Appellate Division of the Supreme Court of New York, 1922)
Shmargon v. Rosenstein
192 A.D. 143 (Appellate Division of the Supreme Court of New York, 1920)
Franklin Motor Car Co. v. Kast
157 S.W. 841 (Missouri Court of Appeals, 1913)
McCants v. Thompson
1911 OK 41 (Supreme Court of Oklahoma, 1911)
Farnum v. Kennebec Water Dist.
170 F. 173 (First Circuit, 1909)
Wallabout Bank v. Peyton
123 A.D. 727 (Appellate Division of the Supreme Court of New York, 1908)
Godfrey v. Rowland
17 Haw. 577 (Hawaii Supreme Court, 1906)
International & Great Northern Railroad v. Startz
94 S.W. 207 (Court of Appeals of Texas, 1906)
Manchester Assur. Co. v. Oregon Railroad
79 P. 60 (Oregon Supreme Court, 1905)
State Bank v. Brown
96 A.D. 441 (Appellate Division of the Supreme Court of New York, 1904)
Rathborne v. Hatch
80 A.D. 115 (Appellate Division of the Supreme Court of New York, 1903)
Harmon v. Decker
68 P. 11 (Oregon Supreme Court, 1902)
Susewind v. Lever
61 P. 644 (Oregon Supreme Court, 1900)
Spaulding v. Coeur D'Alene Railway & Navigation Co.
51 P. 408 (Idaho Supreme Court, 1897)
Wellston Coal Co. v. Franklin Paper Co.
57 Ohio St. (N.S.) 182 (Ohio Supreme Court, 1897)
Sherlock v. German-American Insurance
21 A.D. 18 (Appellate Division of the Supreme Court of New York, 1897)
National Ulster County Bank v. Madden
21 N.E. 408 (New York Court of Appeals, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
16 Wend. 586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merrill-v-ithaca-owego-rail-road-nysupct-1837.