Farnum v. Kennebec Water Dist.

170 F. 173, 95 C.C.A. 355, 1909 U.S. App. LEXIS 4684
CourtCourt of Appeals for the First Circuit
DecidedMay 7, 1909
DocketNo. 799
StatusPublished

This text of 170 F. 173 (Farnum v. Kennebec Water Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farnum v. Kennebec Water Dist., 170 F. 173, 95 C.C.A. 355, 1909 U.S. App. LEXIS 4684 (1st Cir. 1909).

Opinion

PUTNAM, Circuit Judge.

This is a suit at common law in which t(¡e Circuit Court directed a verdict for the defendant. Thereupon the plaintiff sued out a writ of error. It is convenient throughout to call the plaintiff below the plaintiff, and the defendant below the defendant. An agreement was 'filed under the statute waiving a jury, and, so far as all substantial purposes are concerned, the case was submitted to the court on an auditor’s report. The record is in such form that it enables this court to order an affirmance of the judgment, or a reversal followed b}r a judgment for the plaintiff for the amount claimed by him, less some minor corrections made by the auditor. Chicago, etc., Railway Company v. Clark, 178 U. S. 353, 364, 20 Sup. Ct. 924, 44 L. Ed. 1099.

July 22, 1904, the plaintiff made a contract with the defendant for laying in Maine a pipe water line a distance of a number of miles. The contract was not for a round sum, but was based on quantities, with the. usual provision for monthly estimate by the engineer, with a reservation of 15 per cent, until the final estimate. It contained the following provision:

“Delay in furnishing materials to tlie contractor shall not constitute ground for damage claims, but if the work be interrupted thereby, the time for completing the same shall be correspondingly extended.”

By the terms of the contract the work was to have been completed by December 15, 1904, subject to the provision for delay in furnishing materials cited. The -work was not completed at the time named; but this was caused by delay on the part of the district in furnishing pipe. On January 4, 1905, the defendant took possession of the work and evicted the plaintiff. The plaintiff did not abandon >the work, but expressed himself ready and willing to complete it within the proper extension of time to which he was entitled. He had lost money by the work.under his contract to the time of eviction. The balance of the incompleted work at the contract price would have amounted to about $15,000; but for the plaintiff to have completed the work would have entailed on him a further loss of from $2,000 to $3,000. The estimates have been paid him- according to the contract, and they related to everything which he had done or furnished before his eviction. It was stated at bar by the defendant that, under a provision of the contract which permitted the defendant to pay bills incurred by plaintiff on the work, the same to be charged against the amount due him or to become due him, he has, in fact, been paid more than the entire estimates; so that, in fact, no reserve is due him. Nevertheless, whether the reserve has been paid him is. not shown by the record nor admitted by .both parties.

Under these circumstances the plaintiff claims to restate the entire account from the beginning, to reject the prices, based on qualities named in the contract, and to recover under a quantum meruit reason[175]*175able amounts for work done and materials furnished. If the account is to be restated as claimed, there would have been due him at the time the suit was brought, aside from any question of interest, $24,673.05; and the dispute here is over that sum.

It will be seen at once that the proposition of the plaintiff is on its face extraordinary. The work was done under a contract and paid for within 15 per cent, according to that contract; and yet the plaintiff claims that the defendant’s breach is retroactive in its effect, to such an extent as to annul what was in fact done, and make that which was executed executory. Unless the authorities are the other way, this certainly is not in accordance with the fundamental principles of the law. It is true that in a contract of this nature the earlier part of the work is sometimes the more expensive, on account of the cost of installation of machinery, tools, and materials, so that sometimes the earlier part of the work is not profitable while the latter part is, and so that the contractor looks for his profit to come from his ability to close the whole enterprise. On the other hand, sometimes it is the other way, and, in the early part of work of this character, the contractor skims the surface, gets large estimates, and abandons his contract, leaving it to be finished at a loss to the party with whom it was made. Therefore, it is impossible here to give any weight pro or con to atiy suggestions of that character. If the condition of things is like that first suggested, the contractor had his remedy by bringing an action for breach. If, on the other hand, he sues on the common counts, as he certainly may under some circumstances, he does it at his own option. There is no necessity arising out of the circumstances which makes it proper, in order to secure justice, that the apparent rules of law should be violated or strained.

On the other hand, the plaintiff brings to us numerous decisions which he thinks sustain his propositions. In applying these, two important things are to be remembered. One is that those authorities which simply hold that an action lies on the common counts do not meet the issue here; because it must be conceded that, wherever there is a breach, and in consequence thereof the adverse party elects to abandon the contract, an action on the common counts lies for what has been done or furnished, as the same form of action would lie if the entire work had been completed. That it would lie under the latter condition, and also under the former, has been settled for a century. No issue of such a general character is here at all, so that we have no occasion to consider any authorities simply reiterating that rule. The other thing to be considered is that in some decisions the work to be done was of such a character, or the agreed compensation therefor was to be in such form, that it was impossible to formulate any practical rule except that which the plaintiff maintains; and in none of them had the contract actually been executed by payments in whole or in part for eacli and every item of work done or materials furnished, as in the case at bar. Dixon v. Fridette, 81 Me. 122, 16 Atl. 412, Wright v. Haskell, 45 Me. 489, and Mullaly v. Austin, 97 Mass. 30, were of the general character which we say do not assist us in this case. The plaintiff also cites decisions in no way authoritative with us, and we limit our detailed investigaton to such as are.

[176]*176The rule has been fixed in Maine under the conditions of departure by the contractor from the terms of the contract. It is laid down in White v. Oliver, 36 Me. 92, and has always been adhered to. There it was decided that, if the contractor for the erection of a building has departed from the contract as to the size of the building or tire quality of the work, and the building has been accepted, he is entitled to recover the contract prices, deducting whatever the work may be worth less on account of departures; so that, under the circumstances supposed, the defendant could not have shown that the value of the work accepted should be computed from a lower standard. Consequently, where the breach is by the other party, as in the case at bar, justice, which should hold an even hand, requires the application of the same rule.

We have examined all the cases decided by the Supreme Judicial Court of the state of Maine so far as brought to our attention, and also all others which we could discover. One case which brings in the circumstance of a breach of condition by the person for whom the work is to be done is Holden Company v. Westervelt, 67 Me.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cucullu v. Hernandez
103 U.S. 105 (Supreme Court, 1881)
Chicago v. Tilley
103 U.S. 146 (Supreme Court, 1881)
Goodwin v. Colorado Mortgage Investment Co.
110 U.S. 1 (Supreme Court, 1884)
United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Lovell v. St. Louis Mutual Life Insurance
111 U.S. 264 (Supreme Court, 1884)
Chicago, Milwaukee & St. Paul Railway Co. v. Clark
178 U.S. 353 (Supreme Court, 1900)
Clark v. . the Mayor, C. of New-York
4 N.Y. 338 (New York Court of Appeals, 1850)
White v. Oliver
36 Me. 92 (Supreme Judicial Court of Maine, 1853)
Wright v. Haskell
45 Me. 489 (Supreme Judicial Court of Maine, 1858)
Holden Steam Mill Co. v. Westervelt
67 Me. 446 (Supreme Judicial Court of Maine, 1877)
Dixon v. Fridette
16 A. 412 (Supreme Judicial Court of Maine, 1888)
Poland v. Face
60 A. 795 (Supreme Judicial Court of Maine, 1905)
Seretto v. Rockland, South Thomaston & Owl's Head Railway
63 A. 651 (Supreme Judicial Court of Maine, 1906)
Merrill v. Ithaca & Owego Rail Road
16 Wend. 586 (New York Supreme Court, 1837)
Mullaly v. Austin
97 Mass. 30 (Massachusetts Supreme Judicial Court, 1867)
Fitzgerald v. Allen
128 Mass. 232 (Massachusetts Supreme Judicial Court, 1880)

Cite This Page — Counsel Stack

Bluebook (online)
170 F. 173, 95 C.C.A. 355, 1909 U.S. App. LEXIS 4684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farnum-v-kennebec-water-dist-ca1-1909.