Seretto v. Rockland, South Thomaston & Owl's Head Railway

63 A. 651, 101 Me. 140, 1906 Me. LEXIS 5
CourtSupreme Judicial Court of Maine
DecidedJanuary 26, 1906
StatusPublished
Cited by2 cases

This text of 63 A. 651 (Seretto v. Rockland, South Thomaston & Owl's Head Railway) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seretto v. Rockland, South Thomaston & Owl's Head Railway, 63 A. 651, 101 Me. 140, 1906 Me. LEXIS 5 (Me. 1906).

Opinion

Peabody, J.

This action was brought by the plaintiff to recover certain sums alleged to be due him under a written contract for the [142]*142building of an electric railway. The case comes before the law court on report.

The work was commenced by the contractor about the middle of April, 1904, and was abandoned by him about the ninth day of July of that year, before it was fully completed. The contract was executed by the parties under seal. The plaintiff declares in debt by two counts, the first being based upon- the items of an account thereto annexed • amounting to fifteen thousand nine hundred sixty-eight and eight one hundredths dollars ($15,968.08), and the second for like amount for goods bargained and sold, money lent, money paid, money received and money due upon account stated. Under the general count the plaintiff specifies the nature of the defendant’s indebtedness to him. By counting in debt the plaintiff’s right to recover is restricted to certain sums of money alleged to be due by the terms of the.contract, as recovery for damages resulting from a breach of its covenants would require a.different form of action.

It is admitted by the plaintiff that the contract was not completed, blit he-justifies its non-fulfillment. by the fault of the defendant. The defendant claims that the plaintiff, without just cause, abandoned „ the work and did so expressly because it did not yield to the imposition of a condition which was not a part of its obligation ; and it alleges, as a further defense to the action, that tlie plaintiff has not proved performance of such part of the work as entitled him,to any instalment of the stipulated compensation.

If the failure of the plaintiff to fulfil the contract-was not caused by the fault or default of the defendant and any damages have resulted, they may be offered by way of recoupment to reduce the compensation to which the plaintiff would otherwise be entitled, 9 Cyc. 686, but if he was prevented or is excused by reason of the fault of the defendant from performing the contract, he would be entitled to recover such sums as had become due at the date of the writ according to the account annexed, or specified under the second count in the writ. Jewett et al. v. Weston, 11 Maine, 346; Norris v. School District, 12 Maine, 293; Atkinson v. Brown, 20 Maine, 67 ; Andrews v. Portland, 35 Maine, 475.

It is suggested, as a technical defense to this action, that the plain[143]*143tiff lias misconceived his remedy, even if there is merit in his claim, that it should have been assumpsit under the common counts, or covenant broken on a count declaring on the special contract. But the plaintiff upon his theory replies that in an action of debt he can recover the definite sums due under the special contract, whether for general work, extra work and materials, so far as the construction of the railroad has progressed, and for loss sustained by him on account of the enforced idleness of his workmen, as provided in the contract. The genera] rule is that debt lies wherever indebitatus assumpsit will lie. Larmon v. Carpenter, 70 Ill. St. 549; Van Deusen v. Blum, 18 Pick. 229; Veazie v. Bangor, 51 Maine, 509; Allard v. Belfast, 40 Maine, 369; Mc Vicker v. Beedy, 31 Maine, 314; Portland v. Atlantic & St. Lawrence R. R., 66 Maine, 485; Norris v. School District, supra. While this action is generally used for the recovery of a precise sum due under simple or special contracts, it may be maintained for a quantum meruit or quantum valebat. Smith v. First Cong., etc., 8 Pick. 178; Nat. Exchange Bank v. Abell, 63 Maine, 346. It would, therefore, be as available to the defendant to show any fact bearing upon the question of what the work done by the plaintiff was reasonably worth as if the action had been covenant broken or assumpsit. And the issue can be tried in this action whether the plaintiff' did general work, or did extra work and furnished extra materials, under the terms of the contract, to be ascertained as therein agreed, and whether, upon the facts proved, there were due to the plaintiff other sums of money at the date of the writ. In determining the sums, if any, due to the plaintiff he is limited in his proof to the specification of his claim, and against these items the defendant had the right to introduce counter proof. Gooding v. Morgan, 37 Maine, 419. The defendant offers no evidence, but relies upon the facts to which the plaintiff is limited by his form of action and tiie specification of his claim.

By the terms of the contract the plaintiff was to construct 21,920 feet of electric railway main track and 500 feet of second track, in accordance with specifications as to work and material, and extra work was to be done, constituting part of the construction of the railroad to which the provisions of the contract were to apply as fully [144]*144as to the general work specified therein. The defendant was to pay for the completed work $17,500 in instalments every thirty days as the work progressed, to the extent of eighty-five per cent, thereof, estimated and certified in writing by the engineer of the railroad, Howard C. Forbes. There are provisional agreements which definitely authorize the engineer to complete the contract if the work is abandoned by the contractor, or unnecessarily or unreasonably delayed, and for adjusting compensation under suck conditions ; and also providing for indemnifying the contractor for any loss occasioned through the fault of the railway by not being able •to deliver materials, or in any other respect failing to carry out its part- of the agreement.-

The report shows that a bill for extra work, rendered by the contractor, amounting to. .$1353.02, another for extra work amounting to $1611.02, a bill for regular contract work amounting to $4958.33, estimated and certified by the engineer, were paid. The controversy in this suit relates to the sums alleged to be due subsequently, during the further continuance of the work, from May 21st to about the first of July, 1904, which have not been paid. The first of the unpaid- accounts was- for extra work, amounting to $2016.80, under date of June 4, 1904, certified by Mr. Bowers, -who acted as the engineer of the railroad after the retirement of Mr. Forbes. The second was for extra work, amounting to $2141.47, under date of June 18, 1904, and the third account, dated July 2, 1904, was for extra work, amounting to $1922.59, the two last being .certified by Mr.- Keene, then acting as the engineer of the railroad. The plaintiff claims also to recover the balance of amount due on general work, under an estimate made by Mr. Keene and reported in writing to the company June 24, 1904, viz. $13,125, less amount paid on account of general work, $4958.33.

The contract between the parties provided, among, other things, “ Whenever the word engineer, or a pronoun in place of it, is used herein, it shall be and is mutually understood to refer to Howard C. Forbes, 4 State Street, Boston. And it was further ’provided, For completing the electric railway as herein specified the sum of Seventeen Thousand Five Hundred Dollars ($17,500,) which shall [145]*145be in installments every thirty (30) days as the work progresses to the extent of 85 per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Sturm Lumber Co.
111 S.E. 481 (West Virginia Supreme Court, 1922)
Farnum v. Kennebec Water Dist.
170 F. 173 (First Circuit, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
63 A. 651, 101 Me. 140, 1906 Me. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seretto-v-rockland-south-thomaston-owls-head-railway-me-1906.