Imperial Excavating & Paving, LLC v. Rizzetto Construction Management, Inc.

935 A.2d 557
CourtSuperior Court of Pennsylvania
DecidedOctober 23, 2007
StatusPublished
Cited by12 cases

This text of 935 A.2d 557 (Imperial Excavating & Paving, LLC v. Rizzetto Construction Management, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Imperial Excavating & Paving, LLC v. Rizzetto Construction Management, Inc., 935 A.2d 557 (Pa. Ct. App. 2007).

Opinion

OPINION BY PANELLA, J.:

¶ 1 Appellants, Rizzetto Construction Management, Inc. (“RCMI”) and United States Fidelity and Guaranty Company, Inc., appeal from the judgment entered on November 29, 2006, by the Honorable Edward D. Reibman of the Court of Common Pleas of Lehigh County. After careful review, we affirm.

¶ 2 The instant breach of contract action centers on work to be done on two soccer fields located at Southern Lehigh High School. RCMI was awarded a principal construction contract to perform extensive work for the Southern Lehigh School District. RCMI entered into a subcontract with Imperial Excavating and Paving, LLC (“Imperial”) for various tasks, including the removal of the existing topsoil at the site, as well as grading and compacting the subsoil.

¶ 3 Imperial removed the topsoil and compacted the subsoil before redistribut[559]*559ing compacted topsoil to a depth marked on stakes placed by an RCMI-employed surveyor. At the time that Imperial performed the grading, RCMI made no objection to the quality or performance of its work. Upon completion of the earthwork for the soccer fields, Imperial submitted its Applications and Certificates for Payment Forms and ceased work on the soccer fields.

¶ 4 RCMI then submitted its Application and Certification for Payment Form No. 1 to the Southern Lehigh School district which included a request for payment for the work performed by Imperial on the two soccer fields. Application and Certificate for Payment Form No. 1 was .dated September 11, 2001, and was signed by the architect on September 12, 2001. On September 25, 2001, Southern Lehigh School District, along with payment for other work, paid RCMI for the entirety of the earthwork performed on the soccer fields by Imperial less retainage, and RCMI in turn paid Imperial.

¶ 5 Following the completion of Imperial’s work on the soccer fields, RCMI subcontracted with Wolk’s Landscaping, Inc. (“Wolk”) to perform corrections of undulations and irregularities, rock removal, laser assisted grading, cultivating and restructure of the topsoil, cultivating and tilling of the subsoil, re-grading, additional stone picking, and seeding. More importantly, section 3.1A of the Lawns and Grasses component of the subcontract between Wolk’s Landscaping, Inc. and RCMI specifically provided that Wolk had to correct any irregularities in soil structuring and “apply 6 inches of top soil to seeded athletic fields.” Lawns and Grasses, 6/25/01, § 3.1(A)(1).

¶ 6 After Wolk completed all of its work and seeded the fields, Southern Lehigh School District allowed the fields to remain fallow for a period of two years. Thereafter, in the spring of 2003, Southern Lehigh began using the completed soccer fields and experienced problems, including inadequate topsoil grading, pooling of water with drainage problems, excess rocks and a lack of consistent growth of grass on the fields. Southern Lehigh hired soil experts and had an “As Built” survey performed. The survey revealed that the topsoil did not measure a uniform six inches but instead varied, with some' spots several inches above and some spots below the required level. Testing also indicated that the topsoil had not been culled and tilled properly and was in a compacted state. Thereafter, in August 2003, the School District formally notified RCMI of its rejection of the soccer fields and withheld $120,000 from a payment for other services.

If 7 RCMI subsequently alleged that Imperial had failed to perform grading, cultivation, and tilling of the topsoil as required by the written subcontract. As a result, RCMI withheld payment on other work performed by Imperial, in addition to re-tainage, to cover amounts expended to address the School District’s complaints concerning the soccer fields. Thereafter, in October 2003, RCMI hired the Brickman Group to perform work to correct problems with the soccer field. The cost of the work was $80,957.10. Invoices revealed that the work involved laser grading of topsoil, aeration, and seeding. Southern Lehigh School District formally accepted the repaired fields on October 17, 2005. RCMI also sought to impose charges of $2,350.00 and $2,500.00 on Imperial for the testing and surveying undertaken to ascertain the problems on the soccer fields, alleging that the costs were incurred in remedying Imperial’s non-conforming work.

¶ 8 On December 8, 2005, Imperial filed a complaint against RCMI seeking dam[560]*560ages for RCMI’s failure to pay for other work performed by Imperial on the Southern Lehigh School District project. RCMI counterclaimed on January 24, 2005, alleging that Imperial had failed to meet its contractual obligations regarding the two soccer fields. Prior to trial both parties settled all portions of the case except those arising out of work performed by Imperial with respect to additions and renovations to Southern Lehigh High School.

¶ 9 On January 9, 2006, a bench trial was held before the Honorable Edward D. Reibman, who, after receiving evidence from both parties, ordered the submission of post-trial briefs. Judge Reibman, by order and opinion dated June 29, 2006, found in favor of Imperial and against RCMI and United States Fidelity and Guaranty Company in the amount of $255,154.78, and additionally against RCMI -solely, in the amount of $7,175.50. Pursuant to the Prompt Payment Act,1 RCMI was also ordered to pay interest, penalties and attorneys fees.

¶ 10 Thereafter, RCMI filed a motion for post-trial relief on July 7, 2006. On November 20, 2006, Judge Reibman denied the motion except to amend certain aspects of the court’s award of interest and penalties and to award attorney’s fees in favor of Imperial in the amount of $22,509.55. This timely appeal followed.

¶ 11 On appeal, RCMI presents the following issues for review: •

I.Did the evidence cited by the court below constitute sufficient competent evidence to support its findings of fact that Imperial tendered full and satisfactory performance under the subcontract and that RCMI accepted that performance in the fall of 2001?
II. Were the findings of fact of the court below that Imperial ten- • dered full and satisfactory performance under the subcontract and that RCMI accepted that performance in the fall of 2001 consistent with the great weight of evidence presented at trial?
III. Did the trial court err in awarding Imperial Prompt Payment Act penalties on the judgment where RCMI’s withholding of payment bore a reasonable relationship to the value of its good faith claim against Imperial?

Appellant’s Brief, at 5 (all-capitalized and bolded typeface removed for readability).

¶ 12 RCMI first contends that the evidence presented at trial was insufficient to sustain a judgment in favor of Imperial. As recently explained by Judge Susan Peikes Gantman, when reviewing a challenge to the sufficiency of the evidence, the findings of the trial judge in a non-jury case must be given the same weight and effect on appeal as the verdict of a jury, and the findings will not be disturbed on appeal unless predicated upon errors of law or unsupported by competent evidence in the record. See Sovereign Bank v. Valentino, 914 A.2d 415, 420 (Pa.Super.2006). Our standard of review is narrow, given that “[a] sufficiency analysis ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiGuglielmo, A. v. Capen, C.
Superior Court of Pennsylvania, 2022
El-Gharbaoui, A. v. Ajayi, A.
2021 Pa. Super. 146 (Superior Court of Pennsylvania, 2021)
United Environmental Group, Inc. v. GKK McKnight, LP
176 A.3d 946 (Superior Court of Pennsylvania, 2017)
Clipper Pipe & Service, Inc. v. Ohio Casualty Insurance
115 A.3d 1278 (Supreme Court of Pennsylvania, 2015)
East Coast Paving & Sealcoating, Inc. v. North Allegheny School District
111 A.3d 220 (Commonwealth Court of Pennsylvania, 2015)
Waller Corp. v. Warren Plaza, Inc.
95 A.3d 313 (Superior Court of Pennsylvania, 2014)
Prime Group Remediation, Inc. v. T. Lomax & Associates, Inc.
29 Pa. D. & C.5th 1 (Philadelphia County Court of Common Pleas, 2013)
J.J. DeLuca Co. v. Toll Naval Associates
56 A.3d 402 (Superior Court of Pennsylvania, 2012)
Trowbridge v. McCaigue
992 A.2d 199 (Superior Court of Pennsylvania, 2010)
Zimmerman v. Harrisburg Fudd I, L.P.
984 A.2d 497 (Superior Court of Pennsylvania, 2009)
Mastercraft Woodworking Co. v. Jim Lagana Plumbing & Heating Inc.
9 Pa. D. & C.5th 251 (Berks County Court of Common Pleas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
935 A.2d 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/imperial-excavating-paving-llc-v-rizzetto-construction-management-inc-pasuperct-2007.