Prime Group Remediation, Inc. v. T. Lomax & Associates, Inc.

29 Pa. D. & C.5th 1, 2013 Phila. Ct. Com. Pl. LEXIS 46
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedFebruary 20, 2013
DocketNo. 0272
StatusPublished

This text of 29 Pa. D. & C.5th 1 (Prime Group Remediation, Inc. v. T. Lomax & Associates, Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prime Group Remediation, Inc. v. T. Lomax & Associates, Inc., 29 Pa. D. & C.5th 1, 2013 Phila. Ct. Com. Pl. LEXIS 46 (Pa. Super. Ct. 2013).

Opinion

OVERTON, J.,

This matter is before the appellate court in response to the order reproduced below, issued on November 2, 2012.

Upon consideration of the post-trial motions of the defendant, T. Lomax & Associates, Inc., and any opposition thereto, it is hereby ordered that the motions are denied.

T. Lomax and Associates, Inc. filed an appeal.

FACTS1

Prime Group Remediation, Inc., (hereinafter “Prime”) andT.LomaxandAssociates,Inc.,(hereinafter“appellant”) entered into an oral contract for asbestos remediation at the Bluford School located in Philadelphia, Pennsylvania. [3]*3The parties agreed that Prime would be paid $75,000 for the asbestos remediation. The contract was negotiated on the appellant’s behalf by Paul Mikalic, who was employed by Prime at the time.

Prime completed its work at the Bluford School on or about August 31, 2009. Prime, through its officers, executed a partial release on or about October 22, 2009. The release was prepared by Keating General Contractors (hereinafter “Keating”) and did not release the appellant but did release the School District of Philadelphia, Keating, and Federal Insurance Company. No general releases were executed.

Prime received $67,500.00 for its work it had completed, leaving a claim for retainage of $7,500.00. Prime sent two (2) invoices; one dated July 21, 2009 and the second dated August 18, 2009. Both invoices listed a retainage. The appellant did not deny the receipt of these invoices. Vincent J. Primavera, Jr., Vice President of Prime, testified that the retainage was not due until completion of the entire project.

Mr. Mikalic, who had left Prime’s employ and began for the appellant, testified that Prime failed to remove a trailer that Prime used to depose of the asbestos waste in a timely fashion. The trailer was said to be physically preventing any additional work to be done on the project. The appellant claimed a breach by Prime’s failure to remove the disposal trailer. Consequently, Mr. Mikalic decided to hire USA Environmental Management Inc. to complete the work on behalf of the appellant because of [4]*4his perceived breach by Prime. Prime conceded that they were responsible for the cost of the trailer removal which was $2,400.00.

PROCEDURAL HISTORY

On August 9,2011, plaintiff, Prime Group Remediation, Inc. (“Prime”) filed a complaint for breach of contract against defendant, T. Lomax and Associates, Inc. (“appellant”). Prime alleged that the appellant failed to pay Prime the entire amount of their contract, which was $75,000.

On May 7, 2012, the appellant filed a motion for summary judgment. On June 13, 2012, the Honorable Idee C. Fox denied the appellant’s motion for summary judgment.

On October 17,2012, this court found in favor of Prime. On November 2, 2012, this court denied the appellant’s post-trial motion. On December 6, 2012, appellant filed a timely appeal. Statements of matters complained of on appeal were requested and properly tendered on January 2, 2013. Appellant raised the following issues in its statement of matters Complained of on appeal pursuant to Pa. R.A.P. 1925 (b):

1. The court erred in denying Lomax’s motion for summary judgment in its order of June 13, 2012;
2. The court erred in denying Lomax’s motion for summary judgment by failing to deem Lomax’s new matter admitted due to the plaintiff, Prime Group Remediation, Inc.’s (“Prime”) failure to respond to [5]*5same;
3. The court erred in denying Lomax’s motion for summary judgment by failing to deem Lomax’s requests for admissions, which were served on January 20, 2012, admitted due to Prime’s responding to same on Februaiy 23, 2012, two weeks after responses were due under PA.R.C.P. No. 4014;
4. The court erred in denying Lomax’s motion for summary judgment in failing to estopp Prime from contradicting its prior testimony in the Philadelphia Municipal Court under claim #SC-11-01-25-5949 that it had not performed work at the Bluford School project after August 31, 2009;
5. The court erred in denying Lomax’s summary judgment motion and at trial in not finding that the sub-contractor and material supplier’s partial release of claims and liens affidavit and the subcontract’s partial rlease of claims and liens applied to bar Prime from seeking any additional monies from Lomax for the Bluford School project other than the $67,500.00 paid by Lomax to Prime;
6. The court erred in denying Lomax’s summary judgment motion and at trial in not finding that Prime was stopped from arguing that it was owed any money over the $67,500.00 paid to it by Lomax because prime admitted in the sub-subcontractor and material supplier’s partial release of claims and liens affidavit that it had been paid in full by Lomax through August [6]*631,2009.
7. The court erred at trial in not granting Lomax’s request at trial for a compulsory non-suit based upon the language of the sub-contractor and material suppier’s partial release of claims and liens affidavit and the subcontractor’s partial release of claims and liens;
8. The court erred by awarding $2,000.00 to Prime at trial for the award was not based on facts of record, but was based on pure speculation and conjecture, and was improper;
9. The court erred at trial by refusing to permit Lomax offer evidence regarding performing work at another location and monies incurred for materials;
10. The court erred at trial by finding that Lomax breach its contract with Prime;
11. The court’s finding at trial that there was retainage was against the weight of the evidence; and,
12. Since the trial court’s order denying Lomax’s post trial motions, docketed on November 6, 2012, did not set forth the basis for the court’s ruling, Lomax further states that the trial court erred in denying the appellants’ post-trial motions seeking a compulsory non-suit, that the verdict be set aside, and/or awarding a new trial and reserve its right to file a supplemental statement in response to the trial court’s Rule 1925(a) opinion.

[7]*7This opinion is offered in response to said appeal.

DISCUSSION

Appellant’s claims are discussed in turn and are without merit.

A. Appellant’s claims 1, 2, 3, and 4 were not preserved for appellate review.

Appellant’s claims 1,2, 3, and 4 were not preserved for appellate review and consequently are deemed waived. On October 31, 2012, the appellant filed a post-trial motion with this court. However, that motion did not include any of the aforementioned claims.2 Therefore, these claims were not preserved for appellate review and are deemed waived. See Lane Enterprises, Inc. v. L.B. Foster Co., 710 A.2d 54, (Pa. 1998) (“Pa. R. Civ. P.227.1 requires parties to file post-trial motions in order to preserve issues for appeal. If an issue has not been raised in a post-trial motion, it is waived for appeal purposes”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United National Insurance v. J.H. France Refractories Co.
668 A.2d 120 (Supreme Court of Pennsylvania, 1995)
Commonwealth v. King
721 A.2d 763 (Supreme Court of Pennsylvania, 1998)
Hatbob v. Brown
575 A.2d 607 (Supreme Court of Pennsylvania, 1990)
Lane Enterprises, Inc. v. L.B. Foster Company
710 A.2d 54 (Supreme Court of Pennsylvania, 1998)
Poleri v. Salkind
683 A.2d 649 (Superior Court of Pennsylvania, 1996)
Commonwealth v. Kennedy
959 A.2d 916 (Supreme Court of Pennsylvania, 2008)
United National Insurance v. J.H. France Refractories Co.
612 A.2d 1371 (Superior Court of Pennsylvania, 1992)
Eisenhauer v. Clock Towers Associates
582 A.2d 33 (Supreme Court of Pennsylvania, 1990)
Armbruster v. Horowitz
813 A.2d 698 (Supreme Court of Pennsylvania, 2002)
Taliferro v. Johns-Manville Corp.
617 A.2d 796 (Superior Court of Pennsylvania, 1992)
Imperial Excavating & Paving, LLC v. Rizzetto Construction Management, Inc.
935 A.2d 557 (Superior Court of Pennsylvania, 2007)
Commonwealth v. Flamer
53 A.3d 82 (Superior Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
29 Pa. D. & C.5th 1, 2013 Phila. Ct. Com. Pl. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prime-group-remediation-inc-v-t-lomax-associates-inc-pactcomplphilad-2013.