John B. Conomos, Inc. v. Sun Co., Inc.

831 A.2d 696, 2003 Pa. Super. 310, 2003 Pa. Super. LEXIS 2535
CourtSuperior Court of Pennsylvania
DecidedAugust 22, 2003
StatusPublished
Cited by137 cases

This text of 831 A.2d 696 (John B. Conomos, Inc. v. Sun Co., Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John B. Conomos, Inc. v. Sun Co., Inc., 831 A.2d 696, 2003 Pa. Super. 310, 2003 Pa. Super. LEXIS 2535 (Pa. Ct. App. 2003).

Opinion

OPINION BY

LALLY-GREEN, J.:

¶ 1 This is an appeal from a judgment following a non-jury verdict in favor of Appellee, John B. Conomos, Inc. (“Conomos”), and against Appellant, Sun Company, Inc. (R & M) (“Sun”). We hold that, absent fraud or unconscionability, a bad faith breach is an insufficient basis for invalidating a limited liability provision where the parties had agreed by contract that one party (the breacher) could cancel the contract at any time at its option whether or not the other party was in default of its obligations, where the breacher cancelled the contract, and where the limitation of liability damages applied to cancellation. However, the trial court’s refusal to enforce the limitation of damages provision in the contract was harmless error under the facts of this case. We affirm.

¶ 2 The facts laid out by the trial court are as follows:

This matter was tried before me non-jury on various dates between January 9th and January 26, 2001. The issue involved a contract between Plaintiff [Appellee] (“Conomos”) and the Defendant [Appellant] (“Sun”) for painting of industrial piping at Sun’s Marcus Hook, Pennsylvania Refinery. Conomos brought suit to recover what it claimed to be the funds due it under the contract, as well as claiming exemplary damages under the Contractor and Subcontractor[ ] Payment Act [73 P.S. § 501 ei seg.]. After the close of testimony, Conomos requested leave to amend its complaint under Rule 1033 to also allege fraud by Sun.
*701 The facts show that in May, 1996 [unless otherwise indicated, all dates are in 1996] Conomos was invited to bid on this painting project and attended a pre-bid meeting at which interested bidders were shown the facility and given information about how the surface of the pipes was to be prepared before paint was applied. At that meeting, bidders were shown examples of what Sun was expecting as surface preparation, which related to industry standards developed by the Steel Structures Painting Council. 1 The “examples” were pieces of painted pipe or angle iron from which paint in varying degrees had been removed. The Steel Structured Painting Council standards are referred to as “SP” plus a numeric designation indicating the degree of surface preparation. They range from washing (SP-1); to hand tool cleaning (SP-2); to use of scrapers and light use of a power tool known as a “needle gun” (SP-3). Sun added some additional requirements to SP-3, which it called SP-3 modified. That modification contemplated light use of a “needle gun” for a few passes to see if the old paint was still adherent. The numeric designation continued on up to SP-11, which required removing all paint and leaving a paint free, shiny surface. Obviously, subjective evaluation plays a significant role in whether these standards are met. Therein lies the nub of this dispute. Conomos contends that the needle gun use required by Sun’s inspector was excessive and went well beyond the standard of paint flaking off with a few passes of the needle gun which was the SP-3 modified standard.
Conomos was the successful bidder on Sections 7, 8, and 9 of the contract and began work on June 10, 1996. The inspector on the project was a Mr. Don Desroches, who early on found the preparation of the pipe by Conomos to be unacceptable. This began on the second or third day of the project, and is reflected in the construction notes of the Conomos foreman, Mr. Ron Hester, who on June 12, noted (“Don is wanting everything off’) and on June 17th, (“Told him he has to leave up or we are moving out.”).
There was no easing up and Desroeh-es continued to impose inspection standards and surface preparation that Co-nomos believed to be unacceptable and beyond the scope of the industry standard. It complied with his requirements, but incurred additional expense as a result. Conomos wrote to Sun on July 15th, and indicated its problem and asked for consideration of its concerns including an upward revision of the contract price. When it received no response, it left the job on July 25th. Notwithstanding this action by Cono-mos, no response was received from Sun and a second letter was sent August 6th, and a third on August 29th. No meeting or resolution occurred until September 9th when Sun, by letter, cancelled the contract. According to its letter, Sun believed it owed Conomos the full price for area 7, that is, $23,037 plus one-half of area 8, that is, $27,712, less what it would cost Sun to finish the balance of area 8 and all of 9. Sun calculated that to be $18,739. The net due Conomos under the foregoing would *702 be $32,010. Sun did indeed pay that amount to Conomos over 1 year later on August 28,1997.
Conomos thereafter filed this suit for the balance due under the contact [sic], plus additional charges for the additional preparation required, as well as a claim under the Contractor and Subcontractor[ ] Payment Act. After cancellation of the contract, Sun awarded the completion thereof to MP Industrial Coatings (MP), the next lowest bidder to Cono-mos. The evidence showed that MP likewise had trouble with Desroches which led to a representative of the paint manufacturer acting as mediator over whether the painting done by MP was adequate. The mediator found the job by MP to be acceptable.

Trial Court Memorandum Order and Non-Jury Verdict, 6/26/01, at 1-4 (citations omitted) (footnotes omitted).

¶3 The trial court found that Sun breached the contract with Conomos, and characterized the breach as a “bad faith breach.” The court refused to permit Co-nomos to amend its complaint to allege fraud, stating that “I believe this effort is entirely too late. The factors on which Conomos attempts to assert this claim are not viable.” Id. at 8. The court also rejected Sun’s counterclaim for the costs incurred by Sun in completing the areas Conomos left unfinished. Id. at 5, 7. The trial court awarded Conomos $32,892.23 as contractual damages for extra services rendered and lost profits. Id. at 7. In addition, the court assessed $18,748.44 in penalties, and $12,000.00 in reasonable attorneys’ fees, under section 512 of the Contractor and Subcontractor Payment Act (“CSPA”). 2 Id. at 7-8. The sum of damages awarded for contractual claims and as section 512 remedies in the trial court’s original verdict came to $63,640.67. Id. at 8.

¶ 4 Following the trial court’s verdict awarding Conomos $63,640.67 in damages, both parties filed post-trial motions. Trial Court Memorandum Order, 11/13/01, at 2. Sun contended that the trial court’s verdict was against the weight of the evidence, which the court rejected. Id. at 2-3. The trial court also rejected Sun’s claim that any remedies resulting from the breach were subject to the contract’s limitation of damages clause, which set the contract price as a ceiling on what Conomos could recover for work completed prior to the end of their contractual relationship. Id. at 3-4. The trial court did not find the limited liability clause applicable because the cancellation provision containing the clause was not controlling. Id. at 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Swatt, A. v. Nottingham Village
2025 Pa. Super. 138 (Superior Court of Pennsylvania, 2025)
Hawbaker, J. v. Nottingham Village
2025 Pa. Super. 138 (Superior Court of Pennsylvania, 2025)
Mongell, F. v. Martell, P.
Superior Court of Pennsylvania, 2024
Com. v. Munoz-Rodriguez, A.
2024 Pa. Super. 250 (Superior Court of Pennsylvania, 2024)
Tedesco Excavating v. FWH Development
2024 Pa. Super. 129 (Superior Court of Pennsylvania, 2024)
Mazzuca, J. v. Abreu, S.
2024 Pa. Super. 24 (Superior Court of Pennsylvania, 2024)
E. Allen Reeves v. Old York, LLC
293 A.3d 284 (Superior Court of Pennsylvania, 2023)
Camper, C. v. Werner, B.
Superior Court of Pennsylvania, 2023
R. Thomas & D. Thomas v. County of Bucks TCB
Commonwealth Court of Pennsylvania, 2023
Keshav Convenience Store, LLC v. G & G Oil, Inc.
Superior Court of Pennsylvania, 2023
Independence Ave. v. Tradavo, Inc.
Superior Court of Pennsylvania, 2023
Alcorn, K. v. Alcorn, T.
Superior Court of Pennsylvania, 2021

Cite This Page — Counsel Stack

Bluebook (online)
831 A.2d 696, 2003 Pa. Super. 310, 2003 Pa. Super. LEXIS 2535, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-b-conomos-inc-v-sun-co-inc-pasuperct-2003.