Tedesco Excavating v. FWH Development

2024 Pa. Super. 129
Superior Court of Pennsylvania·Decided June 24, 2024·No. 995 WDA 2022·Published·Cited by 1 cases

Opinion

2024 PA Super 129

TEDESCO EXCAVATING & PAVING, : IN THE SUPERIOR COURT OF INC. : PENNSYLVANIA :

v. :

:

FWH DEVELOPMENT, LLC :

:

Appellant : No. 995 WDA 2022

Appeal from the Judgment of Sentence Entered August 1, 2022 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD 19-006017

BEFORE: BOWES, J., KUNSELMAN, J., and MURRAY, J. OPINION BY KUNSELMAN, J.: FILED: June 24, 2024 I. Introduction

In this construction-contract dispute, the Defendant, FWH Development, LLC, appeals from the $678,238.31 judgment that the trial court entered, after a jury verdict in favor of Tedesco Excavating & Paving, Inc. Because FWH anticipatorily repudiated the contract, and Tedesco sued before FWH invoked a termination provision in that contract, we affirm.

II. Factual & Procedural Background FWH desired to build a residential and commercial development in Butler County, along State Route 228, known as Whitetail Meadows. It hired Jerrod Crosby of David E. Wooster & Associates to serve as the Project engineer. The plans included redoing an intersection on Route 228.

Mr. Crosby placed the Route 228 work, which involved widening the road and adding traffic lights, out for bids. Tedesco was the lowest bidder. At Mr. Crosby’s recommendation, on May 19, 2015, FWH’s owner, Fred Hespenheide,

signed a unit-price contract with Tedesco to perform the Route 228 work. The contract price was $1,259,000.00. See Plaintiff’s Ex. 53, Agreement § 2 at 2, 6. The contract required the work to be completed in 220 days, and time was of the essence. See id.

The contract included Article 15, “Suspension of Work and Termination.”

Id., Agreement § 4 at 32-34. Under Article 15.4, FWH could terminate the contract “without cause” after providing Tedesco and Mr. Crosby seven days’ written notice. Id. at 33. If FWH invoked the provision, it agreed to pay Tedesco “for completed and acceptable work executed in accordance with the contract . . . including fair and reasonable sums for overhead and profit on such work.” Id. (some capitalization omitted). However, Tedesco could not collect “anticipated profits or revenues or other economic loss arising out of or resulting from such termination.” Id.

Tedesco planned to complete the Route 228 work in 2015, but FWH soon informed it that FWH lacked funding for the Project. Thus, FWH could not commence the Project, and Tedesco was left with a gap in its 2015 paving schedule. As a result, Tedesco lost the 35% profit it expected to earn from the Route 228 work that summer. Still, Tedesco remained ready and eager to do the work whenever FWH obtained financing. The parties communicated intermittently over the next three years, but the Project never commenced.

On March 20, 2018, FWH asked Tedesco to send an escalation proposal for price increases from the original contract price, due to the rise in fuel, materials, and labor costs. Tedesco submitted a proposal to Mr. Crosby for

an estimated 5% increase, per year. This proposal brought the contract price to $1,560,000.00.

FWH still failed to start the Project in 2018. Instead, it hired Momentum, a Seattle-based company, to replace Wooster & Associates and Mr. Crosby as site manager. Momentum sent Bob Saunders to monitor the subcontractors and “the construction management on site and [to do] all of that work, labor bids, supervising bids.” N.T., 5/12/22, at 538.

Mr. Saunders eventually met with Tedesco. He requested an updated escalation proposal. On August 15, 2018, Tedesco e-mailed Mr. Saunders a new contract price of $1,652,463.70. Mr. Saunders did not reply.

Seven months later, on March 25, 2019, in a communication to a third party, Mr. Saunders stated that FWH “awarded the contract for site paving and the [Route 228] improvements” to Shields Paving, Tedesco’s competitor. Plaintiff’s Ex. 60 at 1.

Then, on April 4, 2019, FWH’s attorney wrote to Tedesco’s subcontractor and Tedesco. He admitted FWH had no intention of honoring its contract with Tedesco.1 According to FWH’s attorney:

In 2015, it was intended that Tedesco [would] serve as the [Route 228] contractor for the Whitetail Meadows . . . Project in Adams Township, Butler County . . .

. . . In late 2018, Tedesco submitted a revised estimate for the cost of the [Route 228] work. Tedesco’s revised cost estimate was substantially in excess of the original cost estimate provided by Tedesco in 2015. Tedesco’s revised cost estimate was also in

1 FWH’s attorney has passed away. Thus, he did not testify at trial.

excess of other cost estimates for the [Route 228] work FWH received from other contractors. As a result, [FWH will] no longer use Tedesco to complete the [Route 228] work for the Project.

Plaintiff’s Ex. 61 at 2.

Three weeks later, on April 23, 2019, Tedesco sued FWH for breach of contract in the Court of Common Pleas of Allegheny County. It sought an anticipated 35% overhead and lost profits from the Route 228 work.

Soon “after [FWH] got sued,” on May 3, 2019, it wrote Tedesco. N.T., 5/12/22, at 576; see also N.T., 5/11/22, at 443 (accord). The letter stated, “Pursuant to Section 15.4 of the General Conditions of the [May 19, 2015] agreement, [FWH] hereby provides the requisite seven days’ notice of its intention to terminate the agreement for convenience. Said termination will be effective May 10, 2019.” Defendant’s Ex. 4 (some capitalization omitted).

The matter proceeded to a jury trial. The jurors found FWH in breach of the 2015 contract and awarded Tedesco $401,046.00 for overhead and lost profits. FWH sought post-trial relief. Also, Tedesco moved to mold the verdict to include interest and attorneys’ fees under Pennsylvania’s Contractor and Subcontractor Payment Act (“CASPA”).2 The trial court denied FWH’s motion and partially granted Tedesco’s motion. It added $135,664.87 in interest; $133,682.00 in attorneys’ fees; and $7,845.44 in legal costs to the verdict.

The trial court entered judgment in favor of Tedesco for $678,238.31.

FWH appealed to this Court.

2 See 73 P.S. §§ 501-517.

III. Analysis

FWH raises the following nine issues:3

1. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to meet conditions precedent?

2. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to identify or prove material breach?

3. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where the trial court refused to apply the intent of the parties through the terms of the agreement, including the termination provision, which explicitly prohibits recovery of lost profit and overhead?

4. Whether the trial court erred as matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to prove its damages with reasonable certainty?

5. Whether the trial court abused its discretion by denying FWH’s objections at trial requesting that Tedesco be precluded from providing testimony on projects allegedly similar in scope to the FWH project, when Tedesco failed to lay a proper foundation and provide FWH with underlying

Free access — add to your briefcase to read the full text and ask questions with AI

Tedesco Excavating v. FWH Development, 2024 Pa. Super. 129 (Pa. Ct. App. 2024).

2024 Pa. Super. 129 (Tedesco Excavating v. FWH Development) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tedesco Excavating v. FWH Development
2024 Pa. Super. 129 (Superior Court of Pennsylvania, 2024)