Tedesco Excavating v. FWH Development

2024 Pa. Super. 129
Superior Court of Pennsylvania·Decided June 24, 2024·No. 995 WDA 2022·Published·Cited by 1 cases

Opinion

J-A29017-23

2024 PA Super 129

TEDESCO EXCAVATING & PAVING, : IN THE SUPERIOR COURT OF INC. : PENNSYLVANIA : v. : : FWH DEVELOPMENT, LLC : : Appellant : No. 995 WDA 2022

Appeal from the Judgment of Sentence Entered August 1, 2022 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD 19-006017

BEFORE: BOWES, J., KUNSELMAN, J., and MURRAY, J.

OPINION BY KUNSELMAN, J.: FILED: June 24, 2024

I. Introduction

In this construction-contract dispute, the Defendant, FWH Development,

LLC, appeals from the $678,238.31 judgment that the trial court entered, after

a jury verdict in favor of Tedesco Excavating & Paving, Inc. Because FWH

anticipatorily repudiated the contract, and Tedesco sued before FWH invoked

a termination provision in that contract, we affirm.

II. Factual & Procedural Background

FWH desired to build a residential and commercial development in Butler

County, along State Route 228, known as Whitetail Meadows. It hired Jerrod

Crosby of David E. Wooster & Associates to serve as the Project engineer. The

plans included redoing an intersection on Route 228.

Mr. Crosby placed the Route 228 work, which involved widening the road

and adding traffic lights, out for bids. Tedesco was the lowest bidder. At Mr.

Crosby’s recommendation, on May 19, 2015, FWH’s owner, Fred Hespenheide, J-A29017-23

signed a unit-price contract with Tedesco to perform the Route 228 work. The

contract price was $1,259,000.00. See Plaintiff’s Ex. 53, Agreement § 2 at 2,

6. The contract required the work to be completed in 220 days, and time was

of the essence. See id.

The contract included Article 15, “Suspension of Work and Termination.”

Id., Agreement § 4 at 32-34. Under Article 15.4, FWH could terminate the

contract “without cause” after providing Tedesco and Mr. Crosby seven days’

written notice. Id. at 33. If FWH invoked the provision, it agreed to pay

Tedesco “for completed and acceptable work executed in accordance with the

contract . . . including fair and reasonable sums for overhead and profit on

such work.” Id. (some capitalization omitted). However, Tedesco could not

collect “anticipated profits or revenues or other economic loss arising out of

or resulting from such termination.” Id.

Tedesco planned to complete the Route 228 work in 2015, but FWH soon

informed it that FWH lacked funding for the Project. Thus, FWH could not

commence the Project, and Tedesco was left with a gap in its 2015 paving

schedule. As a result, Tedesco lost the 35% profit it expected to earn from

the Route 228 work that summer. Still, Tedesco remained ready and eager

to do the work whenever FWH obtained financing. The parties communicated

intermittently over the next three years, but the Project never commenced.

On March 20, 2018, FWH asked Tedesco to send an escalation proposal

for price increases from the original contract price, due to the rise in fuel,

materials, and labor costs. Tedesco submitted a proposal to Mr. Crosby for

-2- J-A29017-23

an estimated 5% increase, per year. This proposal brought the contract price

to $1,560,000.00.

FWH still failed to start the Project in 2018. Instead, it hired Momentum,

a Seattle-based company, to replace Wooster & Associates and Mr. Crosby as

site manager. Momentum sent Bob Saunders to monitor the subcontractors

and “the construction management on site and [to do] all of that work, labor

bids, supervising bids.” N.T., 5/12/22, at 538.

Mr. Saunders eventually met with Tedesco. He requested an updated

escalation proposal. On August 15, 2018, Tedesco e-mailed Mr. Saunders a

new contract price of $1,652,463.70. Mr. Saunders did not reply.

Seven months later, on March 25, 2019, in a communication to a third

party, Mr. Saunders stated that FWH “awarded the contract for site paving

and the [Route 228] improvements” to Shields Paving, Tedesco’s competitor.

Plaintiff’s Ex. 60 at 1.

Then, on April 4, 2019, FWH’s attorney wrote to Tedesco’s subcontractor

and Tedesco. He admitted FWH had no intention of honoring its contract with

Tedesco.1 According to FWH’s attorney:

In 2015, it was intended that Tedesco [would] serve as the [Route 228] contractor for the Whitetail Meadows . . . Project in Adams Township, Butler County . . .

. . . In late 2018, Tedesco submitted a revised estimate for the cost of the [Route 228] work. Tedesco’s revised cost estimate was substantially in excess of the original cost estimate provided by Tedesco in 2015. Tedesco’s revised cost estimate was also in ____________________________________________

1 FWH’s attorney has passed away. Thus, he did not testify at trial.

-3- J-A29017-23

excess of other cost estimates for the [Route 228] work FWH received from other contractors. As a result, [FWH will] no longer use Tedesco to complete the [Route 228] work for the Project.

Plaintiff’s Ex. 61 at 2.

Three weeks later, on April 23, 2019, Tedesco sued FWH for breach of

contract in the Court of Common Pleas of Allegheny County. It sought an

anticipated 35% overhead and lost profits from the Route 228 work.

Soon “after [FWH] got sued,” on May 3, 2019, it wrote Tedesco. N.T.,

5/12/22, at 576; see also N.T., 5/11/22, at 443 (accord). The letter stated,

“Pursuant to Section 15.4 of the General Conditions of the [May 19, 2015]

agreement, [FWH] hereby provides the requisite seven days’ notice of its

intention to terminate the agreement for convenience. Said termination will

be effective May 10, 2019.” Defendant’s Ex. 4 (some capitalization omitted).

The matter proceeded to a jury trial. The jurors found FWH in breach

of the 2015 contract and awarded Tedesco $401,046.00 for overhead and lost

profits. FWH sought post-trial relief. Also, Tedesco moved to mold the verdict

to include interest and attorneys’ fees under Pennsylvania’s Contractor and

Subcontractor Payment Act (“CASPA”).2 The trial court denied FWH’s motion

and partially granted Tedesco’s motion. It added $135,664.87 in interest;

$133,682.00 in attorneys’ fees; and $7,845.44 in legal costs to the verdict.

The trial court entered judgment in favor of Tedesco for $678,238.31.

FWH appealed to this Court.

____________________________________________

2 See 73 P.S. §§ 501-517.

-4- J-A29017-23

III. Analysis

FWH raises the following nine issues:3

1. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to meet conditions precedent?

2. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to identify or prove material breach?

3. Whether the trial court erred as a matter of law in entering judgment for Tedesco for breach of contract where the trial court refused to apply the intent of the parties through the terms of the agreement, including the termination provision, which explicitly prohibits recovery of lost profit and overhead?

4. Whether the trial court erred as matter of law in entering judgment for Tedesco for breach of contract where Tedesco failed to prove its damages with reasonable certainty?

5.

Free access — add to your briefcase to read the full text and ask questions with AI

Tedesco Excavating v. FWH Development, 2024 Pa. Super. 129 (Pa. Ct. App. 2024).

2024 Pa. Super. 129 (Tedesco Excavating v. FWH Development) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tedesco Excavating v. FWH Development
2024 Pa. Super. 129 (Superior Court of Pennsylvania, 2024)